Residential/Commercial Building Permit — North Ogden, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://cms3.revize.com/revize/northogdencity/Documents/Departments/Finance%20Department/05-2026%20Consolidated%20Fee%20Schedule%20-%20Permanent.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential/Commercial Building Permit in North Ogden, Utah
Required for new construction, additions, remodels, repairs, re-roofing/siding, electrical remodeling, plumbing replacement, and furnace/AC replacement in North Ogden. Both the Single-Family Residential Permit and Commercial Building Permit fee are valuation-based, calculated per the 1997 Uniform Building Code Section 107.2 Table 1-A plus 20%, per the city's official Consolidated Fee Schedule (Resolution 05-2026, adopted May 12, 2026, effective May 13, 2026 — the current edition; the previously-cited Resolution 03-2026 PDF link went dead and was confirmed superseded on 2026-07-13).
Verified 2026-07-19 · Source
When you need this permit
- New construction, additions, remodels, and repairs including re-roofing/siding, electrical remodeling, plumbing replacement, furnace/AC replacement
- Commercial structures, additions to or structural remodels of commercial buildings, and non-structural commercial remodels over 3,000 sq ft require a stamp/seal by a State-licensed professional Contractor
- Residential Plan Check Fee Deposit of $500.00, or Commercial Plan Check Fee Deposit of $1,000.00, due at submittal
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Building/Electrical/Mechanical/Plumbing Inspections
Scheduled through the Building Department, (801) 737-9837 or (801) 737-2218, Monday–Thursday 8:00 AM–5:00 PM and Friday 8:00 AM–1:00 PM. No published minimum advance-notice window was found (unlike Highland's 24-hour requirement).
See the full North Ogden inspection guide — scheduling & re-inspection fees →
Tips
- North Ogden calculates its Building Permit Fee off the 1997 Uniform Building Code Table 1-A (plus a 20% surcharge) rather than a current-edition ICC valuation table or its own self-published flat schedule — an older reference standard than several neighboring Utah cities use.
- A Stop Work (Red Tag) for building without a permit carries a steep escalation: $250 for a first offense, jumping to $1,000 for each additional offense.
- Impact fees differ significantly by dwelling classification (single-family vs. multi-family vs. ADU) — always confirm which tier applies before budgeting for a project.
- The Deposit for Off-Site Improvements (all new construction) rose from $1,000.00 to $1,500.00 when Resolution 05-2026 superseded Resolution 03-2026 in May 2026 — budget for the higher figure.
- Residential rooftop and ground-mount solar PV installations fall under this same general valuation-based Building/Electrical Permit — a full review of the Resolution 05-2026 Consolidated Fee Schedule's Building Department section (2026-07-19) and North Ogden's official Building Codes page found no distinct solar-specific permit type, fee line item, or process description; confirm current requirements directly with the Building Department, (801) 737-9837, before applying.
- North Ogden has no distinct EV charger / EVSE permit type or fee either: the same Resolution 05-2026 Consolidated Fee Schedule PDF was re-checked directly (fetched and searched 2026-07-20) and contains zero mentions of 'EV,' 'electric vehicle,' 'charging station,' or 'EVSE.' A residential EV charger install is expected to fall under this same general valuation-based Building/Electrical Permit as standard electrical work; confirm directly with the Building Department, (801) 737-9837, before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the North Ogden building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in North Ogden
Residential/Commercial Building Permit in other cities
Compare residential/commercial building permit fees across Utah →
Look up this fee in a different city →