Residential Building Permit (New Construction) in Wenatchee, Washington

Required for new one- and two-family dwellings and townhouses in Wenatchee, reviewed under the International Residential Code as adopted at WCC 2.04.010 — which names the 2018 edition.

Verified 2026-09-16 · Source

When you need this permit

  • “The 2018 International Residential Code … with amendments as set forth in Chapter 51-51 WAC as the same exists now or may hereafter be amended” (WCC 2.04.010), with Appendix J and Appendix M (Home Day Care) specifically adopted
  • THE NAMED YEAR IS 2018 AND THE CITED WAC CHAPTER CURRENTLY CARRIES 2021 — confirm the operative edition with the building official
  • Only Class A, B or C roofing assemblies may be installed within the city limits (R902.1 as amended)
  • Sheds up to 200 sq ft are exempt but must sit five feet from all property lines and one foot clear of other structures, or they count as attached and need a permit
  • Permits expire if work does not start within 180 days, if work stops for 180 days, or two years after issuance regardless of progress (WCC 2.06.010)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Permit fee
NO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Show full citationNO FEE SCHEDULE APPEARS IN WCC CHAPTER 2.04 OR WCC CHAPTER 2.06. Neither WCC Chapter 2.04 (all three sections) nor WCC Chapter 2.06 (Permits, its single section) states a permit fee or points to one. The only fee reference found anywhere in Title 2 is an ADMINISTRATIVE APPEAL fee — the International Property Maintenance Code as amended provides that “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010”. WCC 1.99.010 sits in Title 1 and was NOT opened for this entry. Ask the city for the current schedule.
Not published in code; ask the city
Administrative appealIPMC Sections 109.6 and 111.1 as amended: “Appeals shall be subject to an administrative appeal fee in accordance with WCC § 1.99.010.” That section sits in WCC Title 1 and was not opened for this entry, so no amount is asserted.
Set by WCC 1.99.010; ask the city

Review timeline

Plan review
Not published — contact the department

How long did your Residential Building Permit (New Construction) permit actually take in Wenatchee?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    Tips

    • Check the edition before you design. Wenatchee's code names the 2018 IRC while the Chapter 51-51 WAC it incorporates “as the same exists now or may hereafter be amended” currently carries 2021. Every neighbouring city in this guide that names a year names 2021. This guide does not decide which governs here, and neither should you — ask the building official and get the answer in writing before it costs you a redesign.
    • The shed exemption has geometry attached, and failing it is not a small thing: up to 200 square feet is exempt only with a five-foot setback from all property lines and one foot clear of other structures, and the code says a structure that misses those “is considered attached and a building permit is required” — which changes what you are building, not just what you file.
    • Roof covering is constrained citywide rather than by zone: Class A, B or C assemblies only, anywhere inside the city limits.

    Frequently asked questions

    Wenatchee requires a residential building permit (new construction) for: “The 2018 International Residential Code … with amendments as set forth in Chapter 51-51 WAC as the same exists now or may hereafter be amended” (WCC 2.04.010), with Appendix J and Appendix M (Home Day Care) specifically adopted; THE NAMED YEAR IS 2018 AND THE CITED WAC CHAPTER CURRENTLY CARRIES 2021 — confirm the operative edition with the building official; Only Class A, B or C roofing assemblies may be installed within the city limits (R902.1 as amended); Sheds up to 200 sq ft are exempt but must sit five feet from all property lines and one foot clear of other structures, or they count as attached and need a permit; Permits expire if work does not start within 180 days, if work stops for 180 days, or two years after issuance regardless of progress (WCC 2.06.010). If your project isn't listed, confirm with City of Wenatchee – Community Development Department at (509) 888-6200 before starting work.

    In Wenatchee, the published Permit fee is: Not published in code; ask the city. Additional published fees: Administrative appeal — Set by WCC 1.99.010; ask the city. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Up to two years, with two earlier ways to lose it. WCC 2.06.010: “All building permits shall expire by limitation and be declared void if (a) work is not started within 180 days of obtaining a permit, or (b) work is abandoned for 180 days or more after beginning work, or (c) after two years from the date of permit issuance, regardless of whether the work is finished.” An AFTER-THE-FACT permit is far tighter — invalid unless work commences within 60 days of issuance, or if work is suspended or abandoned for 60 days.

    You'll need: Building Permit Application; Construction Documents. Depending on your project, Wenatchee may also ask for: Special Inspection Agency Documentation. See the required-documents checklist on this page for details on each.

    Apply through City of Wenatchee – Community Development Department at 301 Yakima Street, Wenatchee, WA 98801. Phone: (509) 888-6200. Official information: https://www.wenatcheewa.gov/.

    The code names 2018 and the state chapter it incorporates now carries 2021, and this guide does not resolve that. WCC 2.04.010 adopts “The 2018 International Residential Code published by the International Code Council, Inc. (ICC), with amendments as set forth in Chapter 51-51 WAC as the same exists now or may hereafter be amended”, with Appendices J and M. The amendments chapter, WCC 2.04.020, is written against the “2018 International Residential Code” to match, so the named year is deliberate rather than a stale cross-reference. But the rolling WAC clause points at a chapter that today adopts the 2021 IRC. Confirm the operative edition with the building official.

    Sources & verification

    Verified against official sources. Last reviewed 2026-09-16.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wenatchee building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

    Wenatchee's permit history isn't searchable here yet

    This page covers what the permit requires. What we don't have for Wenatchee yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

    Your email, and the place — never an address. We only use it to tell you when Wenatchee lands. Privacy.

    Compare residential building permit (new construction) fees across Washington

    Look up this fee in a different city →

    Embed this data card →

    Related guides

    Now live

    Build your Wenatchee project checklist

    Describe your project once and get every permit, document, and fee it triggers in Wenatchee — in one checklist. Free, for any city and any number of projects.

    Get started →