Do I Need a Permit to Install an EV Charger in Washington?

EV charger installation permit requirements. Level 1 vs Level 2, panel capacity, and available rebates.

Level 2 (240V) chargers yes. Level 1 (120V plug-in) no.

Level 1 vs Level 2

Level 1 chargers plug into a standard 120V outlet and do not require a permit. Level 2 chargers require a dedicated 240V circuit (usually 40-50 amps) and always require an electrical permit. Level 2 is what most EV owners install for practical daily charging speeds.

Panel Capacity

A Level 2 EV charger draws 40A and requires a 50A breaker. Many older homes have 100A or 150A panels that may not have capacity. If your panel is full, you'll need a sub-panel or panel upgrade ($1,500-$3,000 additional). An electrician can do a load calculation to determine if your current panel can handle it.

Installation Location

Most home EV chargers are installed in the garage, near the electrical panel. Longer runs from the panel to the charger increase wire cost. Outdoor installations require a weatherproof-rated charger (NEMA 4 or 4X enclosure).

Rebates and Incentives

Many utilities offer rebates for residential EV charger installations. Federal tax credits may also apply. Check current programs with your utility before installation — rebates often require pre-approval and may have specific equipment requirements.

Level 2 chargers need an electrical permit ($40-$75). Fast approval, one inspection. Check for utility rebates first.

Permit fees by city in Washington

Verified from each city’s published fee schedule. Where a city has no separate fee listed for this project, open the city page for the current requirements and amount.

21 rows

Permit fees by city in Washington
Permit feeSource
Bonney LakeSet by city council resolutionVerifiedvia Residential building permitResidential building permit
Des MoinesSet by the City Manager or designeeVerifiedElectrical permit
EdmondsSet by council resolution; not in codeVerifiedElectrical Permit
IssaquahNot published in the code — ask cityVerifiedElectrical Permit
KenmoreSet by adopted fee scheduleVerifiedvia Residential building permitResidential building permit
Lake StevensSet by city council resolutionVerifiedElectrical Permit
LongviewAsk the city — chapter repeal pendingVerifiedElectrical Permit
LynnwoodSet by city council fee ordinanceVerifiedElectrical Permit
Maple ValleySet by Development Fee ScheduleVerifiedvia Residential building permitResidential building permit
Mercer IslandSet by city council resolutionVerifiedElectrical permit
Moses LakeSet by city council resolutionVerifiedElectrical permit
Mountlake TerraceSet by annually adopted fee scheduleVerifiedElectrical permit
PullmanSet by city council resolutionVerifiedElectrical permit
PuyallupSet by city manager executive orderVerifiedElectrical Permit
SammamishSee city page for the current Residential Building Permit feeResidential Building Permit
SeaTacSet by City of SeaTac Fee ScheduleVerifiedElectrical permit
SeattleSee city page for the current Electrical Permit feeElectrical Permit
TumwaterSet by city council resolutionVerifiedvia Residential building permitResidential building permit
University PlaceNot established; ask city or L&IVerifiedElectrical Permit
Walla WallaFrom $30.00, tiered by valuationVerifiedvia Residential building permitResidential building permit
WenatcheeNot published in code; ask the cityVerifiedElectrical Permit

See the national overview for this permit →