Do I Need a Permit to Install Solar Panels in Washington?
Solar panel permit requirements. Permits, inspections, utility interconnection, and available incentives.
Yes — both a building and electrical permit are required.
Two Permits Required
Solar installations require a building permit (for structural mounting on your roof or ground) and an electrical permit (for wiring from panels to inverter to panel). Most solar installers handle the entire permitting process as part of their service.
Roof Access Requirements
Fire code requires 3-foot access pathways on the roof for firefighter access. Panels cannot cover the entire roof — specific setbacks from ridges, valleys, and edges are required. Your installer will design the layout to comply.
Utility Interconnection
Before your system can be energized and connected to the grid, you need an interconnection agreement with your local utility. This is separate from the city permit. Your installer typically handles this, but it can add 2-4 weeks to the timeline.
Incentives (Read This Carefully — They Change Often)
Solar incentives shift frequently and vary by state and utility, so don't rely on older guides. State tax credits and the federal residential Clean Energy Credit (the ITC, Section 25D) have changed eligibility windows in recent years, and some may no longer apply to new installations. Your utility may offer net-billing terms or limited rebates. Because programs change often, confirm exactly what is available the week you sign — and never let an installer's quote assume a credit that no longer exists.
Yes, permits are required but your solar installer handles them. Budget 5-14 days for permit review plus 2-4 weeks for utility interconnection.
Permit fees by city in Washington
Verified from each city’s published fee schedule. Where a city has no separate fee listed for this project, open the city page for the current requirements and amount.
21 rows
| Permit fee | Source | |
|---|---|---|
| Bonney Lake | Set by city council resolutionVerifiedvia Residential building permit | Residential building permit → |
| Des Moines | Set by the City Manager or designeeVerified | Electrical permit → |
| Edmonds | Set by council resolution; not in codeVerified | Electrical Permit → |
| Issaquah | Not published in the code — ask cityVerified | Electrical Permit → |
| Kenmore | Set by adopted fee scheduleVerifiedvia Residential building permit | Residential building permit → |
| Lake Stevens | Set by city council resolutionVerified | Electrical Permit → |
| Longview | Ask the city — chapter repeal pendingVerified | Electrical Permit → |
| Lynnwood | Set by city council fee ordinanceVerified | Electrical Permit → |
| Maple Valley | Set by Development Fee ScheduleVerifiedvia Residential building permit | Residential building permit → |
| Mercer Island | Set by city council resolutionVerified | Electrical permit → |
| Moses Lake | Set by city council resolutionVerified | Electrical permit → |
| Mountlake Terrace | Set by annually adopted fee scheduleVerified | Electrical permit → |
| Pullman | Set by city council resolutionVerified | Electrical permit → |
| Puyallup | Set by city manager executive orderVerified | Electrical Permit → |
| Sammamish | See city page for the current Residential Building Permit fee | Residential Building Permit → |
| SeaTac | Set by City of SeaTac Fee ScheduleVerified | Electrical permit → |
| Seattle | See city page for the current Electrical Permit fee | Electrical Permit → |
| Tumwater | Set by city council resolutionVerifiedvia Residential building permit | Residential building permit → |
| University Place | Not established; ask city or L&IVerified | Electrical Permit → |
| Walla Walla | From $30.00, tiered by valuationVerifiedvia Residential building permit | Residential building permit → |
| Wenatchee | Not published in code; ask the cityVerified | Electrical Permit → |