Commercial/Industrial Zoning Certificate (county's commercial "Building Permit" stand-in) in Unincorporated Albany County, Wyoming

Albany County issues NO conventional IBC-based commercial building permit — the county has never adopted a building code (see codesAdopted), so there is no county structural, mechanical, plumbing, or life-safety plan review for commercial construction. What DOES exist is a genuinely distinct commercial application track within the county's Zoning Certificate mechanism: the 'Commercial/Industrial Structure Zoning Certificate & Rural Address Application' (a separate form from the residential application, form revision 04/2026, one application per structure), which adds commercial-only submittal requirements — building plans, a landscaping site plan meeting Zoning Resolution Chapter 6 Section 1, and a parking site plan meeting Chapter 6 Section 6 — and its own fee tier ($500 for the first commercial/industrial structure vs $300 for a site-built home). Whether the business use itself is allowed at the site is governed by Land Use Table 4.1 (Zoning Resolution Chapter 4 Section 2, reproduced as Appendix V of the application): uses marked A are allowed by right, uses marked C need a separate Conditional Use permit ($750, public hearing), and uses marked P are prohibited in that zoning district. The actual construction-code layer for many commercial occupancies comes from the STATE instead: Wyoming State Fire Marshal plan review under W.S. § 35-9-108 (public buildings over 5,000 sq ft, multistory public buildings, bars/restaurants/nightclubs/theaters/churches of any size, child care centers over 10 children, fuel-dispensing facilities) plus state electrical permitting — see this file's fire-sprinkler-alarm-permit and electrical-wiring-permit-state-program entries.

Verified 2026-08-01 · Source

When you need this permit

  • Confirm the proposed use is permitted in the parcel's zoning district via Land Use Table 4.1 (application Appendix V) — A = allowed by right; C = requires a separate Conditional Use permit ($750.00, public-hearing process); P = prohibited. E.g., office buildings, retail, restaurants, and bakeries are allowed by right in the Commercial (C) district but prohibited in most residential districts; heavy manufacturing is allowed by right only in Industrial (I)
  • One application per structure; incomplete applications are returned and review does not begin until a complete application is submitted with fees paid
  • Complete site plan AND building plans showing setbacks from property lines — floor plans drawn to scale (recommended 1/4" = 1') with exterior/interior dimensions, room labels and uses, doors, basement dimensions, and plumbing fixture locations (application Appendix I)
  • Landscaping site plan per Zoning Resolution Chapter 6 Section 1 (application Appendix III) — applies to all Commercial/Industrial-zoned unincorporated areas: 6-ft-high screening buffer where adjacent to residential uses, one coniferous tree per 50 linear ft of road frontage within 20 ft of the right-of-way plus four tall shrubs per 50 linear ft, with substitution and alternate-plan options
  • Parking site plan per Zoning Resolution Chapter 6 Section 6 (application Appendix IV) — offices/financial 1 space per 300 sq ft, retail 1 per 400 sq ft, service shops 1 per 250 sq ft, restaurants/bars 1 per 3 seats, industrial 1 per employee plus company vehicles, hotels/motels 1 per unit plus 1 per employee; 10 ft × 20 ft minimum stalls; disabled parking per 28 CFR Part 36; loading on county roads needs Board of County Commissioners permission
  • Approach License for any driveway accessing a state, county, or city road (WYDOT / Albany County Road & Bridge / City of Laramie), plus access documentation, proof of ownership, easement documentation, and plat copy if in a platted subdivision
  • Parcels of two (2) acres or less: the site plan must be performed by a professional surveyor before the application can be approved; structures within the Dedicated Plat of Centennial require a property survey
  • Setbacks: 10 ft in Commercial (C), Neighborhood Business (NB), and Industrial (I) districts; 20 ft in Agricultural (A) (setback table printed on the application)
  • Fees must be received before application review begins; a $200.00 late fee applies to any construction begun prior to approval

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial/Industrial Structure (primary, 1st structure)Cross-verified between the application form's own fee table and the Land Use Permit Fee Schedule (approved April 7, 2026), both fetched 2026-08-01
$500.00
Addition to existing Commercial/Industrial structure
$200.00
Accessory Structure (incidental to the primary structure)
$300.00
Small Accessory Building (less than 500 sq ft)
$200.00
Structure Change of UseSee this file's change-of-use-permit entry
$100.00
Rural Address Assignment
$100.00
Conditional Use (only if the use requires it per Land Use Table 4.1)
$750.00
Late fee (construction begun prior to approval)
$200.00

Review timeline

Plan reviewUnincorporated Albany County’s published plan-review target
1–30 business days

How long did your Commercial/Industrial Zoning Certificate (county's commercial "Building Permit" stand-in) permit actually take in Unincorporated Albany County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Right-of-entry inspection (as needed)

    The application grants Albany County personnel the right to enter the property for any inspection purposes necessary to exercise the permit — a land-use/placement check. There is NO county foundation/framing/mechanical/plumbing inspection sequence because no building code is adopted; electrical inspection is the state's (WSFM), and state fire-protection inspections apply only to occupancies covered by W.S. § 35-9-108.

See the full Unincorporated Albany County inspection guide — scheduling & re-inspection fees →

Tips

  • This is a zoning/land-use approval, NOT a construction-code review. For many commercial occupancy types the real code review is the Wyoming State Fire Marshal's plan review under W.S. § 35-9-108 (public buildings over 5,000 sq ft, multistory public buildings, bars/restaurants/nightclubs/theaters/churches regardless of size, child care centers over 10 children, fuel-dispensing facilities) — those projects also cannot be occupied until WSFM issues a certificate of occupancy. See this file's fire-sprinkler-alarm-permit entry.
  • Check Land Use Table 4.1 (Appendix V of the application) BEFORE designing: if your use is marked 'C' in your zoning district you need a $750 Conditional Use permit with a public hearing on top of this application, and if it's marked 'P' the use is prohibited there outright.
  • The county strongly recommends obtaining the zoning certificate and the Small Wastewater (septic) permit at the same time, especially on small lots, so the septic field location can be verified.
  • Zoning Certificates expire two years from approval if not put to use; the county does not review private covenants — covenant compliance is solely the owner's responsibility.
  • Call Wyoming One Call (811) at least two business days before digging.
  • Outdoor signage needs its own Sign Permit (see this file's sign-permit entry) — the commercial application asks whether one has been submitted.

Frequently asked questions

Unincorporated Albany County requires a commercial/industrial zoning certificate (county's commercial "building permit" stand-in) for: Confirm the proposed use is permitted in the parcel's zoning district via Land Use Table 4.1 (application Appendix V) — A = allowed by right; C = requires a separate Conditional Use permit ($750.00, public-hearing process); P = prohibited. E.g., office buildings, retail, restaurants, and bakeries are allowed by right in the Commercial (C) district but prohibited in most residential districts; heavy manufacturing is allowed by right only in Industrial (I); One application per structure; incomplete applications are returned and review does not begin until a complete application is submitted with fees paid; Complete site plan AND building plans showing setbacks from property lines — floor plans drawn to scale (recommended 1/4" = 1') with exterior/interior dimensions, room labels and uses, doors, basement dimensions, and plumbing fixture locations (application Appendix I); Landscaping site plan per Zoning Resolution Chapter 6 Section 1 (application Appendix III) — applies to all Commercial/Industrial-zoned unincorporated areas: 6-ft-high screening buffer where adjacent to residential uses, one coniferous tree per 50 linear ft of road frontage within 20 ft of the right-of-way plus four tall shrubs per 50 linear ft, with substitution and alternate-plan options; Parking site plan per Zoning Resolution Chapter 6 Section 6 (application Appendix IV) — offices/financial 1 space per 300 sq ft, retail 1 per 400 sq ft, service shops 1 per 250 sq ft, restaurants/bars 1 per 3 seats, industrial 1 per employee plus company vehicles, hotels/motels 1 per unit plus 1 per employee; 10 ft × 20 ft minimum stalls; disabled parking per 28 CFR Part 36; loading on county roads needs Board of County Commissioners permission; Approach License for any driveway accessing a state, county, or city road (WYDOT / Albany County Road & Bridge / City of Laramie), plus access documentation, proof of ownership, easement documentation, and plat copy if in a platted subdivision; Parcels of two (2) acres or less: the site plan must be performed by a professional surveyor before the application can be approved; structures within the Dedicated Plat of Centennial require a property survey; Setbacks: 10 ft in Commercial (C), Neighborhood Business (NB), and Industrial (I) districts; 20 ft in Agricultural (A) (setback table printed on the application); Fees must be received before application review begins; a $200.00 late fee applies to any construction begun prior to approval. If your project isn't listed, confirm with Albany County Planning Department at (307) 721-2568 before starting work.

In Unincorporated Albany County, the published Commercial/Industrial Structure (primary, 1st structure) is: $500.00. Additional published fees: Addition to existing Commercial/Industrial structure — $200.00; Accessory Structure (incidental to the primary structure) — $300.00; Small Accessory Building (less than 500 sq ft) — $200.00; Structure Change of Use — $100.00; Rural Address Assignment — $100.00; Conditional Use (only if the use requires it per Land Use Table 4.1) — $750.00; Late fee (construction begun prior to approval) — $200.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Albany County's published plan-review target for a commercial/industrial zoning certificate (county's commercial "building permit" stand-in) is 1–30 business days.

You'll need: Commercial/Industrial Structure Zoning Certificate & Rural Address Application. Depending on your project, Unincorporated Albany County may also ask for: Conditional Use Application. See the required-documents checklist on this page for details on each.

Unincorporated Albany County requires 1 inspection(s) for a commercial/industrial zoning certificate (county's commercial "building permit" stand-in), in order: Right-of-entry inspection (as needed). Schedule each through Albany County Planning Department ((307) 721-2568).

Apply through Albany County Planning Department at 1002 S 3rd Street, Laramie, WY 82070. Phone: (307) 721-2568, email: planning@albanycountywy.gov. Office hours: Monday–Thursday, 7:30am–5:00pm (business by phone, email, and mail also available; staff may be unavailable during posted hours, call ahead to guarantee availability — per albanycountywy.gov/253/Planning, checked 2026-07-17). Official information: https://www.albanycountywy.gov/253/Planning.

No. Albany County has adopted no building code and performs no structural or life-safety plan review. Commercial and industrial construction in the unincorporated county instead requires the Commercial/Industrial Structure Zoning Certificate & Rural Address Application ($500 for the first structure) — a zoning/placement review with commercial-specific landscaping and parking standards. Separately, electrical work is permitted by the Wyoming State Fire Marshal's state program, and many commercial occupancies (restaurants, bars, public buildings over 5,000 sq ft, etc.) require State Fire Marshal building/fire plan review and a state certificate of occupancy under W.S. § 35-9-108.

No — it is a separate application form with additional requirements: building plans, a landscaping site plan (Zoning Resolution Ch. 6 Sec. 1), a parking site plan (Ch. 6 Sec. 6), and a $500 first-structure fee. It is filed one-per-structure and reviewed by the same Planning Department under the same Zoning Resolution.

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Albany County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Albany County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.