Solar Energy Permit in Unincorporated Albany County, Wyoming

Albany County has no general adopted building code / building permit for unincorporated-area construction (consistent with this database's other Albany County permitTypes, which are limited to zoning certificates, floodplain, wastewater, and driveway-access permits), so there is no county-issued structural/mounting permit for a small residential rooftop solar installation. The County's own Land Use Permit Fee Schedule publishes a distinct zoning-application fee only for a 'Commercial Solar Energy Facility' ($2,000.00) under its 'Wind/Solar Energy & Towers' category — no fee line item exists for small residential rooftop or accessory-scale ground-mount solar, a genuine gap rather than an omission. Electrical interconnection work is issued by the Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety), not the County, per this database's electrical-wiring-permit-state-program record for Albany County.

Verified 2026-07-20 · Source

When you need this permit

  • No county building permit applies to unincorporated Albany County — the County has not adopted a general building code, consistent with its other published permit types (zoning, floodplain, wastewater, driveway access)
  • A Zoning Certificate / Land Use Permit fee of $2,000.00 applies specifically to a 'Commercial Solar Energy Facility' under the County's Wind/Solar Energy & Towers fee category — this is understood to mean utility-scale/commercial solar generation facilities, not small residential rooftop or accessory-scale installations
  • No published fee, zoning-certificate requirement, or process specific to small residential rooftop or ground-mount solar was located on the County's own Planning Department pages or Land Use Permit Fee Schedule — genuinely unresolved rather than assumed exempt
  • The ELECTRICAL interconnection portion of any solar installation is issued by the Wyoming State Fire Marshal's Office under W.S. § 35-9-119, not Albany County — apply via wyelectrician.imagetrendlicense.com

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial Solar Energy Facility (Zoning Certificate)Albany County Land Use Permit Fee Schedule, 'Wind/Solar Energy & Towers' category — no fee line item exists for small residential rooftop or accessory-scale solar
$2,000.00
Electrical Wiring Permit (state, standard)Wyoming State Fire Marshal electrical program, not a County fee — RE-CONFIRMED live on 2026-07-20 by direct fetch of wsfm.wyo.gov/electrical-safety/wiring-permits-1: 'A fee of $50.00 shall be paid for any electrical wiring permit issued by the Department.' (Temporary wiring permits are $40.00.) Statutory basis: W.S. § 35-9-119/120.
$50.00

Review timeline

Plan review
Not published — contact the department

How long did your Solar Energy Permit permit actually take in Unincorporated Albany County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical (State WSFM, separate permit)

    Conduit, disconnects, inverter, and interconnection point verified by a Wyoming State Fire Marshal-assigned inspector under the separate state electrical wiring permit

See the full Unincorporated Albany County inspection guide — scheduling & re-inspection fees →

Tips

  • Albany County publishes a solar-specific fee only for COMMERCIAL/utility-scale solar facilities ($2,000.00 zoning certificate) — there is no published fee, process, or confirmation of whether a small residential rooftop or ground-mount system needs any County zoning sign-off at all. Call the Planning Department (307-721-2568) before assuming either way.
  • Regardless of whether a County zoning certificate applies, the electrical interconnection permit for any solar system comes from the Wyoming State Fire Marshal's Office, not Albany County — see this database's electrical-wiring-permit-state-program entry for details.

Frequently asked questions

Unincorporated Albany County requires a solar energy permit for: No county building permit applies to unincorporated Albany County — the County has not adopted a general building code, consistent with its other published permit types (zoning, floodplain, wastewater, driveway access); A Zoning Certificate / Land Use Permit fee of $2,000.00 applies specifically to a 'Commercial Solar Energy Facility' under the County's Wind/Solar Energy & Towers fee category — this is understood to mean utility-scale/commercial solar generation facilities, not small residential rooftop or accessory-scale installations; No published fee, zoning-certificate requirement, or process specific to small residential rooftop or ground-mount solar was located on the County's own Planning Department pages or Land Use Permit Fee Schedule — genuinely unresolved rather than assumed exempt; The ELECTRICAL interconnection portion of any solar installation is issued by the Wyoming State Fire Marshal's Office under W.S. § 35-9-119, not Albany County — apply via wyelectrician.imagetrendlicense.com. If your project isn't listed, confirm with Albany County Planning Department at (307) 721-2568 before starting work.

In Unincorporated Albany County, the published Commercial Solar Energy Facility (Zoning Certificate) is: $2,000.00. Additional published fees: Electrical Wiring Permit (state, standard) — $50.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Albany County does not publish a plan-review timeline for this permit. Contact Albany County Planning Department at (307) 721-2568 for current turnaround.

You'll need: Wyoming State Fire Marshal Electrical Wiring Permit. Depending on your project, Unincorporated Albany County may also ask for: Zoning Certificate / Land Use Permit Application (commercial-scale solar only). See the required-documents checklist on this page for details on each.

Unincorporated Albany County requires 1 inspection(s) for a solar energy permit, in order: Electrical (State WSFM, separate permit). Schedule each through Albany County Planning Department ((307) 721-2568).

Apply through Albany County Planning Department at 1002 S 3rd Street, Laramie, WY 82070. Phone: (307) 721-2568, email: planning@albanycountywy.gov. Office hours: Monday–Thursday, 7:30am–5:00pm (business by phone, email, and mail also available; staff may be unavailable during posted hours, call ahead to guarantee availability — per albanycountywy.gov/253/Planning, checked 2026-07-17). Official information: https://www.albanycountywy.gov/253/Planning.

Unincorporated Albany County, Wyoming has adopted: Albany County has NOT adopted a countywide building code and does NOT issue a general IBC/IRC-style building permit for private construction in unincorporated areas. Under Wyoming's local-option delegation statute (W.S. § 35-9-121), county-level building-code enforcement authority is opt-in via application to the State Fire Marshal; Albany County has not taken that authority, so the State Fire Marshal's Office retains BOTH building and electrical jurisdiction countywide (WSFM 'Local and State Jurisdictions' chart, header reads 'UPDATED 7/7/2026' — corrected 2026-07-17 from a stale '5/11/2026' citation, embedded at https://wsfm.wyo.gov/electrical-safety, lists Albany County BLDG INSP/PR = S and ELEC INSP/PR = S, re-confirmed unchanged 2026-07-17).; The county's OWN site confirms this: Albany County Planning's permit menu and Land Use Permit Fee Schedule (https://www.albanycountywy.gov/253/Planning ; fee schedule PDF https://www.albanycountywy.gov/DocumentCenter/View/6249/Fee-Schedule) contain NO International Building Code / International Residential Code adoption and NO 'building permit' fee line — only zoning, floodplain, wastewater, subdivision, sign, tower, and wind/solar fees. The county's own application labels its zoning approval for new residential/commercial structures 'Zoning Certificate & Rural Address (Building Permit)' — i.e., the county's stand-in for a building permit is a ZONING review against the Albany County Zoning Resolution, not a state building-code plan review/inspection.; The Albany County Zoning Certificate application (https://www.albanycountywy.gov/DocumentCenter/View/4521/Zoning-Certificate-Application) confirms review is 'by the Planning Department' for compliance with 'the Albany County Zoning Resolution' — land-use/setback/use compliance, not IBC/IRC structural or life-safety code compliance.; Practical takeaway: if you are building in unincorporated Albany County, you generally do NOT need a county building permit for the construction itself, but you DO need the county's Zoning Certificate (a land-use/placement approval, sometimes informally called the 'building permit' by the county) plus any of the real exceptions below that apply to your project (floodplain, septic/small wastewater, driveway access, state electrical).. Local amendments apply — see the Unincorporated Albany County overview page for the full list.

This could not be conclusively confirmed. The County has no general building code/building permit for unincorporated areas, and its Land Use Permit Fee Schedule lists a solar-specific fee only for a 'Commercial Solar Energy Facility' ($2,000.00) — no fee or process is published for small residential rooftop or ground-mount solar. Confirm directly with the Planning Department (307-721-2568) before installing.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Albany County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.