Riverton building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Riverton, Wyoming.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 816 N. Federal Blvd., Riverton, WY 82501
- Phone
- (307) 856-2999
- Office hours
- Mon–Fri (contact department for current hours); building permitting/inspection line (307) 857-7708
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Temporary Electric Service
After installation of the temporary meter base post with approved grounding; may be installed by a licensed electrical contractor or homeowner
- 2
Footing
Forms and rebar in place and tied before concrete placement
- 3
Foundation Wall
After forms are in place and vertical/horizontal rebar tied, before concrete placement
- 4
Perimeter Drain
Before backfill is placed around foundation walls enclosing an interior space below finished grade
- 5
Underground Plumbing
After all underground waste/vent/water plumbing is installed and pressure tested, before backfill/concrete
- 6
Interior Footings
After forms and rebar in place; interior footings isolated from the floor slab
- 7
Rough Plumbing / Rough Electric / Rough Mechanical / Gas
Required after wiring/boxes, waste/vent/water piping, venting/ductwork, and gas piping are installed, prior to insulation and sheetrock
- 8
Rough Framing / Penetration Sealing
After rough electrical, plumbing, mechanical, gas, roofing, and framing are complete and the structure is weather tight
- 9
Sewer and Water
After sewer and water service lines are installed, before backfill
- 10
Final Inspection
After the building is completed and ready for occupancy; a Certificate of Occupancy is required before moving in furnishings or occupying the structure
Applies to: Commercial Tenant Improvement Permit
- 1
Rough-In (MEP)
Mechanical, electrical, plumbing rough-in before wall closure
- 2
Rough Framing/Penetration Sealing
After rough trades complete, structure weather-tight
- 3
Final
Complete, ready for Certificate of Occupancy
Applies to: Electrical Permit
- 1
Temporary Electric Service
After temporary meter base post with approved grounding is installed
- 2
Rough Electric
After all wiring and boxes are installed, before insulation/sheetrock
- 3
Final
Part of the overall Final Inspection for the project; electrical inspector tags the installation as approved or requiring correction
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
After all venting and ductwork is installed, before insulation/sheetrock
- 2
Gas
After gas piping is installed
- 3
Final
Part of the project's overall Final Inspection
Applies to: Plumbing Permit
- 1
Underground Plumbing
After all underground waste/vent/water plumbing installed and pressure tested, before backfill/concrete
- 2
Rough Plumbing
After all waste, vent, and water piping is installed, before insulation/sheetrock
- 3
Final
Part of the project's overall Final Inspection
Applies to: Residential Addition / Remodel Permit
- 1
Footing / Foundation (if applicable)
Before concrete pour, if new footings are part of the addition
- 2
Rough Framing/Electric/Plumbing/Mechanical
Before insulation/sheetrock cover
- 3
Final Inspection
All work complete, ready for occupancy
Applies to: EV Charging Station Permit (Electrical Permit)
- 1
Rough Electric (if applicable)
Conduit runs, wire sizing, and disconnect placement before cover
- 2
Final
EVSE breaker sizing, working clearances, and final electrical connections verified
Applies to: Fire Sprinkler / Fire Alarm / Fire Suppression System Permit
- 1
Rough-In / Underground Piping (if applicable)
Underground and rough overhead sprinkler piping, or fire alarm rough wiring/device placement, inspected before concealment, per the approved Department plans and the 2024 IFC as adopted by the City (Ordinance No. 25-003)
- 2
Final Acceptance Test
Hydrostatic/flow acceptance test (sprinkler) or functional alarm test, witnessed prior to occupancy, per the approved plans and 2024 IFC acceptance-testing requirements
Applies to: Solar PV Permit
- 1
Rough Electric
Conduit runs, wire sizing, disconnect placement before cover
- 2
Final
Racking/roof-penetration sealing and final electrical connections verified
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Riverton building permits
Get alerts for Riverton
We'll email you when Riverton's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.