Required for installation of rooftop or ground-mounted solar photovoltaic systems in Riverton. Zoning treats a solar energy system as part of the building for height and lot-area purposes (RMC Chapter 17.24); construction is permitted under the standard building/electrical permit process.

Verified 2026-07-01 · Source

When you need this permit

  • Solar panels and related installation equipment shall not exceed the height limitation for the applicable zoning district (RMC § 17.24.020.A)
  • Solar energy system is considered part of the building and counts toward lot area/coverage limitations for the zoning district (RMC § 17.24.020.B)
  • Electrical scope (interconnection wiring, inverter, disconnects) requires an electrical permit under RMC Chapter 15.08
  • Structural evaluation of the roof/racking attachment recommended given Riverton's 30 psf ground snow load and 100 mph wind design speed (RMC § 15.04.040 local design criteria)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Solar Installation — no dedicated fee line in Resolution No. 1355City of Riverton Resolution No. 1355 does not list a solar-PV-specific line item; per the framework's 'general valuation table' rule this is a verified fee treatment, not a gap — confirm exact classification with the Building Department at (307) 856-2999
Charged under the applicable general valuation/alteration fee category (new construction $0.42–$0.53/sq ft if part of new build, or the Electrical Alteration/Service Upgrade minimums if a standalone retrofit)

Review timeline

Plan reviewTypical estimate — confirm current times with the Riverton building department
~1–20 business days

How long did your Solar PV Permit permit actually take in Riverton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electric

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    Racking/roof-penetration sealing and final electrical connections verified

See the full Riverton inspection guide — scheduling & re-inspection fees →

Tips

  • Riverton's zoning code (RMC § 17.24.020) treats a solar array as part of the building for both height-limit and lot-coverage purposes — a large ground-mount array could count against your lot's maximum building coverage percentage (40% in R-2, for example).
  • There is no separate solar-specific fee line in Resolution No. 1355 — budget for the standard alteration/electrical fee categories, or the new-construction per-square-foot rate if the array is part of new construction.
  • Design for Riverton's local design criteria: 30 psf ground snow load, 100 mph basic wind speed, Seismic Design Category C — relevant to roof-mount racking structural calculations.

Frequently asked questions

Riverton requires a solar pv permit for: Solar panels and related installation equipment shall not exceed the height limitation for the applicable zoning district (RMC § 17.24.020.A); Solar energy system is considered part of the building and counts toward lot area/coverage limitations for the zoning district (RMC § 17.24.020.B); Electrical scope (interconnection wiring, inverter, disconnects) requires an electrical permit under RMC Chapter 15.08; Structural evaluation of the roof/racking attachment recommended given Riverton's 30 psf ground snow load and 100 mph wind design speed (RMC § 15.04.040 local design criteria). If your project isn't listed, confirm with City of Riverton Community Development Department — Building Division at (307) 856-2999 before starting work.

No. City of Riverton Resolution No. 1355 does not include a dedicated solar-PV fee line; solar installations are charged under the general alteration or electrical permit fee categories (or the new-construction per-square-foot rate, if built with a new structure). Confirm the exact classification with the Building Department.

Plan review for a solar pv permit in Riverton typically runs 1–20 business days. This is an estimate, not a published figure — confirm current review times with City of Riverton Community Development Department — Building Division at (307) 856-2999.

You'll need: Application for Building Permit; Electrical Plan. See the required-documents checklist on this page for details on each.

Riverton requires 2 inspection(s) for a solar pv permit, in order: Rough Electric, Final. Schedule each through City of Riverton Community Development Department — Building Division ((307) 856-2999).

Apply through City of Riverton Community Development Department — Building Division at 816 N. Federal Blvd., Riverton, WY 82501. Phone: (307) 856-2999, email: kpetersen@rivertonwy.gov. Office hours: Mon–Fri (contact department for current hours); building permitting/inspection line (307) 857-7708. Official information: https://www.rivertonwy.gov/departments/community_dev/building_permits___inspections/index.php.

Riverton, Wyoming has adopted: 2024 International Building Code (IBC), including appendices A, B, C, F, H, I, J, K — adopted by Enrolled Ordinance No. 25-003 (effective March 22, 2025); 2024 International Residential Code (IRC), including appendices AA, BA, BB, BC, BD, BE, BF, BG, BH, BO, CA, CB, CC, CD, CE, CF (excluding Chapter 11) — Ordinance No. 25-003; 2024 International Mechanical Code (IMC), including appendix A — Ordinance No. 25-003; 2024 International Plumbing Code (IPC), including appendices C, D, E, F — Ordinance No. 25-003; 2024 International Fuel Gas Code (IFGC), including appendices A, B, C, D — Ordinance No. 25-003; 2024 International Fire Code (IFC), including appendices A–G — Ordinance No. 25-003; 2024 International Code Council Performance Code (ICCPC) — Ordinance No. 25-003; 2024 International Property Maintenance Code (IPMC), including appendices A, B — Ordinance No. 25-003; 2024 International Existing Building Code (IEBC) — Ordinance No. 25-003; National Electrical Code (NEC) — NFPA 70; Riverton Municipal Code § 15.08.110(B)(2) ties compliance to 'the latest edition of the National Electrical Code,' which per wsfm.wyo.gov/electrical-safety is now the 2026 edition, effective statewide July 1, 2026 (the 2023 edition was the applicable 'latest edition' from July 1, 2023 until then) — adopted by the City of Riverton itself as Riverton Municipal Code Chapter 15.08 'Electrical Code'; enforced by the city's own electrical inspector, NOT solely the Wyoming State Fire Marshal's default statewide program; National Fire Codes (NFC), current editions, NFPA; National Housing Construction and Safety Standards Act of 1974 (as amended through May 30, 2006, HUD) — governs manufactured/mobile home construction; ICC/ANSI A117.1-2017 — Accessible and Usable Buildings and Facilities. Local amendments apply — see the Riverton overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.