Sheridan building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Sheridan, Wyoming.

Verified 2026-07-13 · Source

How to schedule

Inspections are requested through the building department below.

Address
55 Grinnell Plaza, Sheridan, WY 82801
Phone
(307) 674-5941
Office hours
Mon–Fri 7:00 a.m.–4:00 p.m.

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation / Footings

    Before concrete pour, below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Change of Occupancy Use Permit (Certificate of Occupancy)

  1. 1

    Fire Safety

    Verifies fire-safety compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  2. 2

    Building Structure

    Verifies structural/building-code compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  3. 3

    Sanitation

    Verifies sanitation compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  4. 4

    Zoning

    Verifies the intended use complies with the applicable zoning district prior to occupancy (City Code Section 7-24.1(b))

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    After framing complete before walls covered

  2. 2

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  3. 3

    Fire / Knox Box

    Knox box installation verification (required on all commercial occupancies per local amendment); fire sprinkler/alarm inspections currently routed through the State per City's posted notice

  4. 4

    Final / Certificate of Occupancy

    All work complete, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings)

    Before concrete pour, below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors installed, ready for occupancy

Applies to: Deck Permit

  1. 1

    Footing

    Pier/footing depth verification below 42-inch frost line, before concrete pour

  2. 2

    Framing

    Ledger attachment, joist hangers, structural connections before decking installed

  3. 3

    Final

    Guardrails, stairs, and decking complete per approved plans

Applies to: Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping — 10 lbs held for 15 minutes on threaded gas piping per local IFGC amendment

  2. 2

    Rough-In / Equipment

    Equipment installation and ductwork before walls closed

  3. 3

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Underground / Under-slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — includes 5 psi/15-minute air test per local IPC amendment

  3. 3

    Final

    All fixtures connected, no leaks, venting verified

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    All devices installed, panel labeled, system energized

Applies to: EV Charger / EVSE Permit (Electrical Simple Permit)

  1. 1

    Rough-In

    Circuit wiring, conduit, and panel connections before walls are closed, if applicable

  2. 2

    Final

    Charger mounted, connections verified, system energized

Applies to: Fire Sprinkler / Fire Alarm / Fire Suppression System Permit

  1. 1

    System Rough-In

    Piping, wiring, and device placement before concealment, per approved plans

  2. 2

    Final / Acceptance Test

    Functional/acceptance testing of the completed fire alarm, sprinkler, or suppression system per the approved plans and adopted Fire Code

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    All connections and racking/roof penetrations verified, system energized

Re-inspection fees

Residential Building Permit (New Construction)Re-Inspection (each, up to 3 times) · City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Building Inspection & Code Enforcement" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13
$58.75

Sources & verification

Verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sheridan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Sheridan building permits

Get alerts for Sheridan

We'll email you when Sheridan's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.