Sheridan building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Sheridan, Wyoming.

Verified 2026-07-13 · Source

How to schedule

Inspections are requested through the building department below.

Address
55 Grinnell Plaza, Sheridan, WY 82801
Phone
(307) 674-5941
Office hours
Mon–Fri 7:00 a.m.–4:00 p.m.

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation / Footings

    Before concrete pour, below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Change of Occupancy Use Permit (Certificate of Occupancy)

  1. 1

    Fire Safety

    Verifies fire-safety compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  2. 2

    Building Structure

    Verifies structural/building-code compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  3. 3

    Sanitation

    Verifies sanitation compliance of the location prior to occupancy (City Code Section 7-24.1(b))

  4. 4

    Zoning

    Verifies the intended use complies with the applicable zoning district prior to occupancy (City Code Section 7-24.1(b))

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing / Structural

    After framing complete before walls covered

  2. 2

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in before walls closed

  3. 3

    Fire / Knox Box

    Knox box installation verification (required on all commercial occupancies per local amendment); fire sprinkler/alarm inspections currently routed through the State per City's posted notice

  4. 4

    Final / Certificate of Occupancy

    All work complete, ready for occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing / Foundation (if new footings)

    Before concrete pour, below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical rough-in before walls closed

  4. 4

    Final

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend below the 42-inch local frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed

  4. 4

    Final

    All work complete, smoke/CO detectors installed, ready for occupancy

Applies to: Deck Permit

  1. 1

    Footing

    Pier/footing depth verification below 42-inch frost line, before concrete pour

  2. 2

    Framing

    Ledger attachment, joist hangers, structural connections before decking installed

  3. 3

    Final

    Guardrails, stairs, and decking complete per approved plans

Applies to: Mechanical / HVAC Permit

  1. 1

    Gas Piping Pressure Test

    Required before concealing gas piping — 10 lbs held for 15 minutes on threaded gas piping per local IFGC amendment

  2. 2

    Rough-In / Equipment

    Equipment installation and ductwork before walls closed

  3. 3

    Final

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Underground / Under-slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — includes 5 psi/15-minute air test per local IPC amendment

  3. 3

    Final

    All fixtures connected, no leaks, venting verified

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed

  2. 2

    Final

    All devices installed, panel labeled, system energized

Applies to: EV Charger / EVSE Permit (Electrical Simple Permit)

  1. 1

    Rough-In

    Circuit wiring, conduit, and panel connections before walls are closed, if applicable

  2. 2

    Final

    Charger mounted, connections verified, system energized

Applies to: Fire Sprinkler / Fire Alarm / Fire Suppression System Permit

  1. 1

    System Rough-In

    Piping, wiring, and device placement before concealment, per approved plans

  2. 2

    Final / Acceptance Test

    Functional/acceptance testing of the completed fire alarm, sprinkler, or suppression system per the approved plans and adopted Fire Code

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final

    All connections and racking/roof penetrations verified, system energized

Re-inspection fees

Residential Building Permit (New Construction)Re-Inspection (each, up to 3 times) · City of Sheridan FY27 Master Fee Schedule (approved July 6, 2026), p.11, "Building Inspection & Code Enforcement" — figure confirmed unchanged from Resolution #34-23 as of re-verification 2026-07-13
$58.75

Sheridan building permits

Get alerts for Sheridan

We'll email you when Sheridan's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.