Electrical Permit in Sheridan, Wyoming
The City of Sheridan is the electrical Authority Having Jurisdiction (AHJ) inside city limits — Ordinance No. 2290 adopts the 2023 NEC as a City technical code enforced by the City of Sheridan Building Department, and the Wyoming Department of Fire Prevention & Electrical Safety's own "Local and State Jurisdictions" chart lists Sheridan (the municipality) as holding local ("L") electrical inspection AND electrical plan review authority under W.S. § 35-9-121, rather than the State ("S"). The State Chief Electrical Inspector's office administers electrical permitting only where no local authority has been delegated (shown as "S" on the same chart) — that does not apply within the City of Sheridan.
Verified 2026-07-13 · Source
When you need this permit
- Sheridan's Ordinance No. 2290 adopts the 2023 NEC as a City technical code, amends NEC Section 230.70(A)(1) (exterior service disconnect requirement), and provides that wherever the Fire Code references the NEC it means "the latest adopted electrical code of the City of Sheridan" — the City's own Building Department (created under the same ordinance, Section 103.1 as applied to each adopted technical code) administers and enforces it
- The Wyoming Dept. of Fire Prevention & Electrical Safety's "Local and State Jurisdictions" chart (updated 5/11/2026) lists the City of Sheridan with "L" (municipality/county enforces) for both the ELEC INSP and ELEC PR columns — confirming the City, not the State, is the electrical AHJ inside city limits
- Electrical service upgrades in existing buildings are a City Simple Permit at a flat fee
- New electrical work bundled with new construction, additions, remodels, or other Detailed Building Permit work is covered under the general Residential/Commercial New/Add/Alter valuation-based permit fee — the City does not publish a separate itemized electrical rough-in/service-size fee table beyond the flat Simple Permit fees
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring and conduit installed before walls closed
- 2
Final
All devices installed, panel labeled, system energized
See the full Sheridan inspection guide — scheduling & re-inspection fees →
Tips
- The City of Sheridan Building Department is the electrical AHJ within city limits — confirmed both by Ordinance No. 2290 (City-adopted 2023 NEC, City-amended Section 230.70(A)(1), City Building Department enforcement) and independently by the Wyoming Dept. of Fire Prevention & Electrical Safety's own jurisdictions chart, which marks Sheridan "L" (local) for both electrical inspection and electrical plan review.
- The Wyoming State Fire Marshal's regional electrical inspector office located in Sheridan serves Sheridan COUNTY's unincorporated areas and other Sheridan County towns (marked "S" on the state's chart) — it does not perform electrical permitting/inspection inside the City of Sheridan itself.
- Apply for City electrical permits through the same OpenGov Permit & Licensing Portal (sheridanwy.portal.opengov.com) used for other City building permits.
- 2026-07-17 re-verification: live Municode City Code Ch. 7, §7-2(5) (version dated Apr 30, 2026, current) still reads "The 2023 Edition of the National Electric Code as adopted by the city council shall be amended as follows... Section 230.70(A)(1)..." — confirming Ordinance No. 2290's 2023 NEC adoption remains unchanged. The Wyoming State Fire Marshal's statewide move to the 2026 NEC (effective 2026-07-01) does not reach the City of Sheridan because electrical is enforced locally here (WSFM chart marks Sheridan "L"/"L"), not by the State.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sheridan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sheridan
Electrical Permit in other cities
Compare electrical permit fees across Wyoming →
Look up this fee in a different city →
Now live
Build your Sheridan project checklist
Describe your project once and get every permit, document, and fee it triggers in Sheridan — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →