EV Charger / EVSE Permit (Electrical Simple Permit) — Sheridan, Wyoming · Requirements sheet
Verified 2026-07-20 · Source: https://www.sheridanwy.gov/i_want_to/pay_for/a_building_permit
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Electrical Simple Permit) in Sheridan, Wyoming
The City of Sheridan is the electrical Authority Having Jurisdiction (AHJ) inside city limits (Ordinance No. 2290, 2023 NEC as amended, enforced by the City Building Department). The City's Master Fee Schedule has no dedicated EV-charger/EVSE line item — unlike Solar Panel, which is its own named flat-fee Simple Permit ($250) — so an EV charging station (Level 2 or DC fast charger) installation is most consistent with the City's 'Electrical Service Upgrade' Simple Permit category, the only standalone electrical-specific flat-fee line the City publishes outside of work bundled into a larger Detailed Building Permit.
Verified 2026-07-20 · Source
When you need this permit
- Electrical work must comply with the City's amended 2023 NEC (Ordinance No. 2290)
- Apply through the OpenGov Permit & Licensing Portal (sheridanwy.portal.opengov.com)
- A standalone EV charger circuit/service addition in an existing building is most consistent with the City's 'Electrical Service Upgrade' Simple Permit category (no dedicated EV-charger line item was found on the FY27 Master Fee Schedule); confirm the correct fee category with the Building Department before applying
- If the EV charger is installed as part of new construction or a larger addition/remodel, it is instead covered under that project's Detailed Building Permit valuation-based fee, not a standalone Simple Permit
- A separate service-upgrade coordination with Rocky Mountain Power (the local electric utility) may be required for higher-capacity commercial EV charger installations, independent of the City permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Circuit wiring, conduit, and panel connections before walls are closed, if applicable
- 2
Final
Charger mounted, connections verified, system energized
See the full Sheridan inspection guide — scheduling & re-inspection fees →
Tips
- Sheridan has a dedicated flat-fee Simple Permit for Solar Panel ($250) but no equivalent dedicated line for EV chargers — the closest documented category is the $40 Electrical Service Upgrade Simple Permit; confirm classification with the Building Department before applying.
- The City of Sheridan (not the State of Wyoming) is the electrical AHJ inside city limits, per Ordinance No. 2290 and the Wyoming Dept. of Fire Prevention & Electrical Safety's own jurisdictions chart — apply through the City's OpenGov portal, not the State.
- If your EV charger installation is bundled with new construction or a larger remodel/addition, it will be covered under that project's Detailed Building Permit valuation-based fee instead of a standalone Simple Permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sheridan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sheridan
EV Charger / EVSE Permit (Electrical Simple Permit) in other cities
Compare ev charger / evse permit (electrical simple permit) fees across Wyoming →
Look up this fee in a different city →