Deck Permit — Sheridan, Wyoming · Requirements sheet
Verified 2026-07-13 · Source: https://www.sheridanwy.gov/i_want_to/pay_for/a_building_permit
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Deck Permit in Sheridan, Wyoming
Decks are explicitly named by the City of Sheridan's Building Division as a project type requiring a Detailed Building Permit (plan review) under the 2024 IRC as amended by Ordinance No. 2290.
Verified 2026-07-13 · Source
When you need this permit
- Plan review required (Detailed Building Permit track)
- Structural connection to primary dwelling and footing depth (below 42-inch frost line) must be shown on plans
- Contractor must hold a current City of Sheridan contractor license (or owner-builder per City policy — confirm with Building Division) Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Footing
Pier/footing depth verification below 42-inch frost line, before concrete pour
- 2
Framing
Ledger attachment, joist hangers, structural connections before decking installed
- 3
Final
Guardrails, stairs, and decking complete per approved plans
See the full Sheridan inspection guide — scheduling & re-inspection fees →
Tips
- The City's building permit page lists "adding a deck" specifically as an example of a project requiring plan review — decks are not treated as a Simple Permit in Sheridan.
- As of the City's FY27 Master Fee Schedule (approved July 6, 2026), decks now have their own dedicated fee line — "Residential Deck Permit" at (Valuation x 0.02) x (0.8), the same lower rate as a garage — rather than being billed under the general Residential New/Add/Alter formula (x 0.03) as under the prior 2023 fee schedule. Confirm this rate is applied at permit issuance, since the City's general building-permit page has not been independently re-checked for wording updates reflecting this change.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Sheridan building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Sheridan
Deck Permit in other cities
Compare deck permit fees across Wyoming →
Look up this fee in a different city →
Related guides
Now live
Build your Sheridan project checklist
Describe your project once and get every permit, document, and fee it triggers in Sheridan — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →