Fire Sprinkler / Fire Alarm Permit (State Program) in Unincorporated Sheridan County, Wyoming

Sheridan County and its constituent volunteer rural fire protection districts (Big Horn, Clearmont, Dayton, Sheridan Area Rural, Story, and Tongue River) do not run a fire-protection-system plan-review or permitting program of their own. Installation, addition, or alteration of a fire alarm, fire sprinkler, fire suppression, or special hazard system anywhere in Wyoming — including unincorporated Sheridan County — is permitted and inspected by the Wyoming State Fire Marshal's Office (WSFM), Dept. of Fire Prevention & Electrical Safety, the same state agency that runs the electrical wiring permit program already documented in this jurisdiction's Electrical Permit entry.

Verified 2026-07-22 · Source

When you need this permit

  • State of Wyoming fire protection system plan review and Permit to Construct required through WSFM for installation, addition, or alteration of a fire alarm, fire sprinkler, fire suppression, or special hazard system — required 'regardless of size or valuation' per WSFM's Plan Review program page
  • Apply through the WSFM eLicensing, ePermit, and ePayment Portal
  • Plans are accepted or rejected within 5 business days of receipt
  • Complete submittals are reviewed within 21 further business days of acceptance; if WSFM requests additional information, review completes within 10 business days of receiving it or the original 21-day window, whichever is later
  • Review fees are calculated from the fee schedule in Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3; the applicant is notified of the exact fee once plans are accepted, and payment is due before the Permit to Construct is issued
  • Upon completion and passing of all required inspections, WSFM issues a Certificate of Occupancy or Letter of Compliance
  • None of the six rural fire protection districts serving unincorporated Sheridan County administer their own sprinkler/alarm permitting or plan review — confirmed on Sheridan County's own Fire Protection Districts page, which lists only district governance/meeting contacts, not a permitting function

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire protection system plan review / Permit to Construct feeWSFM's Plan Review page states the fee is calculated from Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3, and the applicant is notified of the specific amount once plans are accepted; the current Chapter 2 rules text could not be retrieved in readable form during this review (the version located was a scanned/image PDF). Contact WSFM at (307) 777-7288 to confirm current fees.
Not published as a flat dollar figure

Review timeline

Plan reviewUnincorporated Sheridan County’s published plan-review target
5–26 business days

How long did your Fire Sprinkler / Fire Alarm Permit (State Program) permit actually take in Unincorporated Sheridan County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Plan Review Fire Inspection

    Fire & life-safety plan review and inspection conducted during construction to confirm compliance with state-adopted codes

  2. 2

    Final Inspection / Certificate of Occupancy or Letter of Compliance

    Performed upon completion of the installed system; WSFM issues a Certificate of Occupancy or Letter of Compliance once all required inspections pass

See the full Unincorporated Sheridan County inspection guide — scheduling & re-inspection fees →

Tips

  • Sheridan County itself has no fire-protection-system permitting program — this is a state, not a county, permit, issued by the Wyoming State Fire Marshal's Office, the same state agency that already administers electrical wiring permits for the unincorporated county (see this jurisdiction's Electrical Permit entry).
  • The six volunteer rural fire protection districts serving unincorporated Sheridan County are locally governed fire-response districts, not permitting authorities — do not confuse them with WSFM.
  • Because the plan-review requirement applies 'regardless of size or valuation,' even a small residential fire alarm addition technically requires a WSFM Permit to Construct — confirm scope with WSFM at (307) 777-7288 before starting work.

Frequently asked questions

Unincorporated Sheridan County requires a fire sprinkler / fire alarm permit (state program) for: State of Wyoming fire protection system plan review and Permit to Construct required through WSFM for installation, addition, or alteration of a fire alarm, fire sprinkler, fire suppression, or special hazard system — required 'regardless of size or valuation' per WSFM's Plan Review program page; Apply through the WSFM eLicensing, ePermit, and ePayment Portal; Plans are accepted or rejected within 5 business days of receipt; Complete submittals are reviewed within 21 further business days of acceptance; if WSFM requests additional information, review completes within 10 business days of receiving it or the original 21-day window, whichever is later; Review fees are calculated from the fee schedule in Dept. of Fire Prevention & Electrical Safety Rules, Chapter 2, Section 3; the applicant is notified of the exact fee once plans are accepted, and payment is due before the Permit to Construct is issued; Upon completion and passing of all required inspections, WSFM issues a Certificate of Occupancy or Letter of Compliance; None of the six rural fire protection districts serving unincorporated Sheridan County administer their own sprinkler/alarm permitting or plan review — confirmed on Sheridan County's own Fire Protection Districts page, which lists only district governance/meeting contacts, not a permitting function. If your project isn't listed, confirm with Sheridan County Public Works Department (Planning / Building Official) at (307) 674-2920 or (307) 675-2420 before starting work.

In Unincorporated Sheridan County, the published Fire protection system plan review / Permit to Construct fee is: Not published as a flat dollar figure. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Sheridan County's published plan-review target for a fire sprinkler / fire alarm permit (state program) is 5–26 business days.

You'll need: WSFM Fire Protection System Plan Review Application (eLicensing/ePermit portal). See the required-documents checklist on this page for details on each.

Unincorporated Sheridan County requires 2 inspection(s) for a fire sprinkler / fire alarm permit (state program), in order: Plan Review Fire Inspection, Final Inspection / Certificate of Occupancy or Letter of Compliance. Schedule each through Sheridan County Public Works Department (Planning / Building Official) ((307) 674-2920 or (307) 675-2420).

Apply through Sheridan County Public Works Department (Planning / Building Official) at 224 South Main Street, Suite 428, Sheridan, WY 82801. Phone: (307) 674-2920 or (307) 675-2420, email: publicworks@sheridancountywy.gov. Office hours: Mon–Fri 8:00am–5:00pm (Sheridan County general office hours per the sheridancountywy.gov site footer, re-confirmed 2026-07-16; not separately published as Public-Works-specific hours). Official information: https://www.sheridancountywy.gov/departments/planning/building_in_the_county/index.php.

Unincorporated Sheridan County, Wyoming has adopted: NO countywide building code / NO general building permit for private construction in unincorporated Sheridan County. Per the Wyoming State Fire Marshal's 'Local and State Jurisdictions' chart, Sheridan County (county-level row) is listed BLDG INSP/PR = STATE and ELEC INSP/PR = STATE — the county has NOT taken general countywide building-code delegation under W.S. § 35-9-121, so the State Fire Marshal / state program has building and electrical jurisdiction across most of unincorporated Sheridan County.; IMPORTANT NUANCE (confirmed on the county's own site): Sheridan County DOES have an adopted 'Building Standards, Sheridan County, Wyoming' rule (adopted Nov. 18, 1991; last amended May 16, 2023, filed as County Clerk doc. #2023-785780) that adopts the 2021 International Building Code, 2021 IRC, 2021 IMC, 2021 IFGC, 2021 IPC, 2021 International Fire Code, the 2022 National Electrical Code, and the Uniform Code for the Abatement of Dangerous Buildings — but ARTICLE I, Section 3 (Applicability) confirms this code applies ONLY within a mapped 'Sheridan County Building Standards Area' (a defined zone around/adjoining the City of Sheridan shown on the Appendix A Planning Map), PLUS specific legacy subdivisions the BOCC imposed permitting/inspection on before Dec. 5, 2006, all NEW subdivisions approved after Dec. 5, 2006, and any structure built under a Conditional Use Permit. It does NOT apply countywide.; Farms and ranches on 40 acres or more of deeded land are specifically EXEMPT from the Building Standards code entirely (Article I, Sec. 3(b)(1)), as are county hospitals, mines/oilfield/refinery facilities, and railway buildings.; Where the Building Standards DO apply (the mapped area / qualifying subdivisions / CUP structures): a building permit is required before construction of any building/structure valued over $5,000 (Article III, Sec. 1), enforced by the Sheridan County Building Official.; Where the Building Standards do NOT apply (the vast majority of unincorporated Sheridan County — rural and agricultural land outside the mapped area): there is no county building permit for private construction; a Zoning Permit (land-use/setback compliance, not a structural building-code permit) is still required countywide for new construction or change of use.; Electrical: wiring permits/inspections are issued by the Wyoming State Fire Marshal's Office — Dept. of Fire Prevention & Electrical Safety (Chief Electrical Inspector), not Sheridan County, per the county's own Zoning Permit application which directs applicants doing new electrical work to WSFM..

The Wyoming State Fire Marshal's Office (Dept. of Fire Prevention & Electrical Safety), not Sheridan County or any of its local rural fire districts. WSFM plan review applies to any new, added, or altered fire alarm, sprinkler, suppression, or special hazard system statewide, regardless of size or valuation. Plans are accepted/rejected within 5 business days and complete submittals are reviewed within 21 further business days. Source: wsfm.wyo.gov/fire-prevention/plan-review.

Sources & verification

Verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Sheridan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.