How to schedule

Inspections are requested through the building department below.

Address
200 S. Willow Street, Jackson, WY 83001 (P.O. Box 1727, Jackson, WY 83001-1727)
Phone
307-733-3959 (Building Official/fee estimates: 307-733-7030; Inspection Line: 307-732-5745)
Office hours
Applications submitted through the Teton County Online Portal (SmartGov); New Residential Construction, Commercial New Construction, and Miscellaneous (under 500 sq ft) permits require a scheduled submission/take-in week booked via the Bookings page. Trade permits (mechanical, plumbing, demolition, re-roof) do not require a submission week and are typically issued within 48 hours.

Published scheduling rules

  • Do not assume electrical inspections can be scheduled via the County SmartGov portal — even though they may appear as an option, Jackson Hole Fire/EMS must be contacted directly (County Building page note). (Electrical Permit)
  • Do not assume electrical inspections can be scheduled via the County SmartGov portal — Jackson Hole Fire/EMS must be contacted directly even though an option may appear to exist online. (Electric Vehicle (EV) Charging Station / EVSE Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation / Footings

    Before concrete pour; footings must extend below the 34-inch frost line

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical (Jackson Hole Fire/EMS), and plumbing rough-in before walls are closed

  4. 4

    Insulation / Energy

    Insulation and 2021 IECC energy compliance verification before drywall

  5. 5

    Final

    All work complete; required for Certificate of Occupancy

Applies to: Commercial Building Permit (New Construction / Tenant Improvement)

  1. 1

    Foundation

  2. 2

    Framing / Rough-In

  3. 3

    Final

Applies to: Electric Vehicle (EV) Charging Station / EVSE Permit

  1. 1

    Electrical Rough-In

    EVSE circuit wiring and disconnect placement before concealment; conducted by Jackson Hole Fire/EMS, not schedulable through the County's SmartGov portal

  2. 2

    Electrical Final

    Charging equipment installed and energized per 2023 NEC Article 625

Applies to: Electrical Permit

  1. 1

    Electrical Rough-In

    Conducted by Jackson Hole Fire/EMS — cannot be scheduled through the County's online portal; contact Jackson Hole Fire/EMS directly

  2. 2

    Electrical Final

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Rough — System Installation

    Sprinkler piping, alarm wiring, and device rough-in inspected before concealment

  2. 2

    Final — Fire and Life Safety Inspection

    Hydrostatic test (sprinkler systems) or functional alarm test witnessed by Jackson Hole Fire/EMS before the system is placed in service; a $250 re-inspection fee applies after 2 or more failed inspections

Applies to: Plumbing Permit, Mechanical / Fuel Gas Permit

  1. 1

    Rough-In

  2. 2

    Final

Applies to: Residential Addition / Remodel (Miscellaneous Building Permit)

  1. 1

    Framing / Rough-In

    Applicable framing, MEP rough-in depending on scope

  2. 2

    Final

    Final inspection on completion

Re-inspection fees

Fire Sprinkler / Fire Alarm PermitConstruction Permit Re-Inspection Fee · Resolution 25-031, Fire and Electrical Division Fees section
$175.00/hr (1-hour minimum)
Fire Sprinkler / Fire Alarm PermitFire and Life Safety Re-inspection (after 2+ failed inspections) · Resolution 25-031, Fire and Electrical Division Fees section
$250.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teton County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Teton County building permits

Get alerts for Unincorporated Teton County

We'll email you when Unincorporated Teton County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.