Electric Vehicle (EV) Charging Station / EVSE Permit in Unincorporated Teton County, Wyoming
Unincorporated Teton County has no distinct EV charger/EVSE permit application or fee line. Like all other electrical work in the county, EV charging equipment installation is permitted, plan-reviewed (where applicable), and inspected by the Electrical Division of the Jackson Hole Fire/EMS Department — a jointly-funded Town of Jackson / Teton County fire district — not the County Building Division and not the Wyoming State Fire Marshal's statewide program. This mirrors the county's Solar PV/Energy Storage System permit, which is also processed as an electrical permit through Jackson Hole Fire/EMS. Governed by the 2023 National Electrical Code (NEC), which includes Article 625 (Electric Vehicle Power Transfer System) provisions for EVSE circuits and disconnects.
Verified 2026-07-20 · Source
When you need this permit
- No standalone EV charger/EVSE permit application exists; apply directly with Jackson Hole Fire/EMS's Electrical Division using the standard Electrical Permit Application
- Governed by the 2023 NEC (County Building Codes Resolution Section 101.4.8), which includes Article 625 (Electric Vehicle Power Transfer System) requirements
- Electrical permit fee is based on the bid submitted for the electrical work to be performed (Jackson Hole Fire/EMS fee methodology), not a flat EV-specific fee
- Electrical plan review is mandatory for industrial/commercial installations and residential services over 400 amps; standard residential EVSE circuit additions below that threshold do not require plan review
- Contact Jackson Hole Fire/EMS Electrical Division directly (307-733-4732 or 307-732-8689) to confirm current requirements and fees, since these are not published in the County's own Planning & Building fee schedule
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Electrical Rough-In
EVSE circuit wiring and disconnect placement before concealment; conducted by Jackson Hole Fire/EMS, not schedulable through the County's SmartGov portal
- 2
Electrical Final
Charging equipment installed and energized per 2023 NEC Article 625
See the full Unincorporated Teton County inspection guide — scheduling & re-inspection fees →
Tips
- There is no dedicated EV charger permit category — apply through Jackson Hole Fire/EMS's standard Electrical Permit process, the same office that handles the county's Solar PV/Energy Storage System permits.
- Do not assume electrical inspections can be scheduled via the County SmartGov portal — Jackson Hole Fire/EMS must be contacted directly even though an option may appear to exist online.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teton County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Teton County
Electric Vehicle (EV) Charging Station / EVSE Permit in other cities
Compare electric vehicle (ev) charging station / evse permit fees across Wyoming →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Teton County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Teton County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →