VerifiedRequired for new one- and two-family dwellings and other residential structures in unincorporated Teton County. Governed by the 2024 IRC. New Residential Construction submittals require a scheduled take-in week through the Teton County Online Portal (SmartGov); a WUI review/permit number (Jackson Hole Fire/EMS) must be obtained first, since all of Teton County is now mapped Wildland-Urban Interface.
Verified 2026-07-01 · Source
When you need this permit
- WUI permit number from Jackson Hole Fire/EMS (via SmartGov Public Portal) obtained BEFORE building permit submittal — effective county-wide since Jan 1, 2025
- Submission week/take-in appointment scheduled via the County's Bookings page for New Residential Construction
- Compliance with 2024 IRC and County-amended climatic/geographic design criteria (115 mph wind, Seismic D1/D2, 34-inch frost depth, site-specific ground snow load per GIS)
- Engineered design by a Wyoming-licensed civil or structural engineer, except detached non-habitable structures under 600 sq ft
- Energy compliance per 2021 IECC; Energy Mitigation Program fee/credit worksheet for conditioned space over 2,500 sq ft
- Compliance with Teton County Land Development Regulations (LDRs) — setbacks, FAR, housing mitigation if applicable — verified by the Planning Division as part of the Planning Review Fee
- Small Wastewater Facility (septic) permit from the Engineering Division if not on sewer
- Grading and Erosion Control permit/information (Plan Level or Statement Level) from the Engineering Division
- Certificate of Occupancy required before occupancy, following final inspection
Required documents
- Req
Residential New Construction Checklist
Teton County Building Division submittal checklist for new residential construction
- Req
Site Plan
Property lines, easements, setbacks, adjacent structures, snow storage, and WUI-required distances between structures and property boundaries
- Req
Construction Drawings
Full plan set: foundation, framing, floor plans, elevations, mechanical/plumbing/electrical layouts
- Req
Structural Calculations
Stamped by a Wyoming-licensed engineer, addressing 115 mph wind, Seismic D1/D2, and site-specific snow loads
- Req
Energy Calculation (REScheck or equivalent)
- Req
WUI Review Memo and Permit Number
Issued by Jackson Hole Fire/EMS Prevention Bureau after SmartGov WUI application review
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (new construction) | 1st 2,500 sq ft x construction cost/sq ft x 0.006, plus next 2,500 sq ft x 0.009, plus remaining sq ft x 0.012 (valuation from the current ICC Building Valuation Data table); remodels valued at 75% of new-construction valuation | TETON COUNTY FEE SCHEDULE 2026, effective January 1, 2026 (tetoncountywy.gov/DocumentCenter/View/38871); minimum Building Permit Fee $305.00 |
| Plan Review Fee | 65% of the Total Building Permit Fee | Charged in addition to the Building Permit Fee; TETON COUNTY FEE SCHEDULE 2026 |
| Planning Review Fee | $125.00 + $60.00 per 1,000 sq ft over 5,000 sq ft | Separate Planning Division review fee for LDR compliance; TETON COUNTY FEE SCHEDULE 2026 |
Review timeline
~5–20 business days
Typical estimate — confirm current times with the Unincorporated Teton County building department
Inspection process
- 1
Foundation / Footings
Before concrete pour; footings must extend below the 34-inch frost line
- 2
Framing
After framing complete, before insulation or wall cover
- 3
MEP Rough-In
Mechanical, electrical (Jackson Hole Fire/EMS), and plumbing rough-in before walls are closed
- 4
Insulation / Energy
Insulation and 2021 IECC energy compliance verification before drywall
- 5
Final
All work complete; required for Certificate of Occupancy
Tips
- Inspections must occur at least every 180 days to keep a permit active, per County FAQ.
- A permit application is deemed abandoned 180 days after filing unless pursued in good faith or issued (IRC/IBC Section 105.3.2 amendment).
- Electrical (Fire Department) inspections cannot be scheduled through the online portal even though they may appear as an option — contact Jackson Hole Fire/EMS directly.
- Up to 80% of paid fees may be refunded if you decide not to build, per written application within 180 days of the plan review payment (IBC Section 108.6/109.6 amendment).
Frequently asked questions
- Is all of unincorporated Teton County in the Wildland-Urban Interface?
- Yes. Effective January 1, 2025, all private land parcels in Teton County (unincorporated county and Town of Jackson) are within the mapped WUI and subject to IWUIC review by Jackson Hole Fire/EMS before a building permit will be accepted.
- Who handles electrical permits for a home in unincorporated Teton County?
- The Electrical Division of the Jackson Hole Fire/EMS Department — a jointly-funded Town of Jackson / Teton County fire district — not the Wyoming State Fire Marshal's statewide program and not the County Building Division directly.
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
- Teton County Planning & Building Services Department — Building Division — official building department
- Teton County Building Division
- 2025 Teton County Building Codes Resolution (effective Feb 1, 2025)
- TETON COUNTY FEE SCHEDULE 2026 (effective Jan 1, 2026)
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teton County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Teton County
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.