Solar PV / Energy Storage System Permit in Unincorporated Teton County, Wyoming
VerifiedPhotovoltaic solar electric systems in unincorporated Teton County require both a building/electrical permit and interact with the County's Energy Mitigation Program, which offers a fee credit for qualifying solar installations. Electrical plan review is mandatory for all Solar PV/Energy Storage System (battery) installations, per Jackson Hole Fire/EMS's Electrical Permits, Inspections & Reviews requirements.
Verified 2026-07-01 · Source
When you need this permit
- Electrical plan review is required for all Solar PV/Energy Storage System (battery) installations (Jackson Hole Fire/EMS)
- Structural review for roof-mount or ground-mount racking, per applicable 2024 IBC/IRC provisions
- Energy Mitigation Program credit application (if claiming the photovoltaic credit) submitted with the residential/commercial energy mitigation worksheet
Required documents
- Req
Electrical Permit Application (Jackson Hole Fire/EMS)
- Opt
Energy Mitigation Program Credit Worksheet
To claim the photovoltaic solar electric system credit against Energy Mitigation Program fees
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit Fee (Solar PV/ESS) | Set by Jackson Hole Fire/EMS Electrical Division — contact directly for current amount | TETON COUNTY FEE SCHEDULE 2026, Electrical Permit Fees section |
| Energy Mitigation Program credit for Photovoltaic Solar Electric System | $5,000 credit per kW | Offsets Energy Mitigation Program fees for qualifying residential/commercial construction over the applicable square-footage threshold; TETON COUNTY FEE SCHEDULE 2026, Energy Mitigation Program Fees section |
Review timeline
~5–20 business days
Typical estimate — confirm current times with the Unincorporated Teton County building department
Inspection process
- 1
Electrical Final
Conducted by Jackson Hole Fire/EMS
Tips
- The $5,000/kW Energy Mitigation credit is separate from, and in addition to, the electrical permit process for the physical Solar PV installation.
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
- Teton County Planning & Building Services Department — Building Division — official building department
- TETON COUNTY FEE SCHEDULE 2026 — Energy Mitigation Program Fees and Electrical Permit Fees sections
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Teton County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Teton County
Get the AI compliance checklist