Fire Sprinkler / Fire Alarm Permit in Unincorporated Teton County, Wyoming

Required for installation of automatic fire-extinguishing (sprinkler) systems and fire alarm/detection systems in unincorporated Teton County, administered by the Jackson Hole Fire/EMS Department's Fire and Electrical Division. The Board of County Commissioners has adopted a separate 2024 Fire Code Resolution (2024 International Fire Code plus 2024 International Wildland Urban Interface Code) for the unincorporated county, per the recital text of the Jackson Hole Fire/EMS 2025 Master Fee Schedule (Resolution 25-031). That Master Fee Schedule is explicitly scoped to 'Unincorporated Areas of Teton County outside of the Town of Jackson,' effective January 1, 2026 — the mirror image of the Town of Jackson's own jurisdiction file, where this same schedule is documented as explicitly NOT applying. The County's own Planning & Building 2026 Schedule of Fees corroborates this division of labor directly, stating under Inspection and Review Fees: 'Fire sprinkler and alarm systems: Contact Jackson Hole Fire/EMS for permits and fees.' Separately, the County's own Building Codes Resolution requires all structures 5,000 sq ft or larger, regardless of occupancy, to be protected by an approved automatic fire sprinkler system (Section 903.2 amendment).

Verified 2026-07-22 · Source

When you need this permit

  • Apply via Jackson Hole Fire/EMS through the shared SmartGov Public Portal (co-teton-wy.smartgovcommunity.com), under one of the Fire permit categories: Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, or Fire Sprinkler Residential (Teton County Permit Applications page)
  • All structures 5,000 sq ft or larger, regardless of occupancy, must be protected by an approved automatic fire sprinkler system installed per the IBC and/or NFPA 13, 13D, or 13R as applicable — agricultural buildings with non-residential uses comprising 10% or less of floor area are exempted (Teton County Building Codes Resolution, Section 903.2 amendment, effective July 1, 2025)
  • Governed by the County's own 2024 Fire Code Resolution (2024 International Fire Code and 2024 IWUIC), administered by Jackson Hole Fire/EMS, as referenced in the preamble of Resolution 25-031
  • A plan review is required before installation, billed hourly with a stated minimum charge; use of outside consultants for plan review is billed at actual cost if Fire/EMS staff cannot perform the review in-house
  • Fire sprinkler/alarm permit fees are NOT published in or processed through the County Planning & Building Schedule of Fees — the County's own fee schedule directs applicants to contact Jackson Hole Fire/EMS directly

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Review FeeJackson Hole Fire/EMS 2025 Master Fee Schedule, Resolution 25-031, effective January 1, 2026 (unincorporated Teton County only) — Fire and Electrical Division Fees section; directly re-chased against the downloaded PDF, 2026-07-22
$150.00/hr (1-hour minimum)
Additional Plan Review (due to changes/revisions)Resolution 25-031, Fire and Electrical Division Fees section
$100.00/hr (1-hour minimum)
Construction Permit Re-Inspection FeeResolution 25-031, Fire and Electrical Division Fees section
$175.00/hr (1-hour minimum)
Work Started Before Permit IssuanceResolution 25-031, Fire and Electrical Division Fees section
2x Permit Fee
Fire and Life Safety Inspection FeeResolution 25-031, Fire and Electrical Division Fees section
$100.00
Fire and Life Safety Re-inspection (after 2+ failed inspections)Resolution 25-031, Fire and Electrical Division Fees section
$250.00
Fire and Electrical Permit Fee — valuation-based construction permitResolution 25-031, Fire and Electrical Permit Fee Table (fees based on valuation of systems and equipment installation) — directly re-chased against the downloaded PDF, 2026-07-22
$1.00-$500.00 = $40 flat fee; $501-$2,000 = $40 for first $500 plus $2.00 per $100 over $500; $2,001-$25,000 = $70 for first $2,000 plus $15.00 per $1,000 over $2,000; $25,001-$50,000 = $415.00 for first $25,000 plus $11.00 per $1,000 over $25,000; $50,001-$100,000 = $690.00 for first $50,000 plus $8.00 per $1,000 over $50,000; $100,001-$500,000 = $1,090.00 for first $100,000 plus $6.00 per $1,000 over $100,000; $500,001-$1,000,000 = $3,490.00 for first $500,000 plus $5.00 per $1,000 over $500,000; over $1,000,000 = $5,990.00 for first $1,000,000 plus $4.00 per $1,000 over $1,000,000
Operational Fire PermitsResolution 25-031, Fire and Electrical Division Fees section — for ongoing/operational permits, distinct from the one-time construction permit
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm Permit permit actually take in Unincorporated Teton County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough — System Installation

    Sprinkler piping, alarm wiring, and device rough-in inspected before concealment

  2. 2

    Final — Fire and Life Safety Inspection

    Hydrostatic test (sprinkler systems) or functional alarm test witnessed by Jackson Hole Fire/EMS before the system is placed in service; a $250 re-inspection fee applies after 2 or more failed inspections

See the full Unincorporated Teton County inspection guide — scheduling & re-inspection fees →

Tips

  • The 2025 Jackson Hole Fire/EMS Master Fee Schedule (Resolution 25-031) governs HERE — unincorporated Teton County outside the Town of Jackson — the opposite of the Town of Jackson's own jurisdiction file, where this same schedule is documented as explicitly not applying and the Town's Resolution 25-18 governs instead. Do not swap the two fee schedules between files.
  • The Town of Jackson's jurisdiction file documents a separate $18.00 'For each Fire Sprinkler System' line item under its own municipal Plumbing Permit fee table (JMC 15.24.030). No equivalent county Plumbing Permit line item for fire sprinkler system tie-ins was found in the County's own 2026 Schedule of Fees Plumbing Permit Fees table during this research — omitted rather than assumed to also apply in the unincorporated county.

Frequently asked questions

Unincorporated Teton County requires a fire sprinkler / fire alarm permit for: Apply via Jackson Hole Fire/EMS through the shared SmartGov Public Portal (co-teton-wy.smartgovcommunity.com), under one of the Fire permit categories: Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, or Fire Sprinkler Residential (Teton County Permit Applications page); All structures 5,000 sq ft or larger, regardless of occupancy, must be protected by an approved automatic fire sprinkler system installed per the IBC and/or NFPA 13, 13D, or 13R as applicable — agricultural buildings with non-residential uses comprising 10% or less of floor area are exempted (Teton County Building Codes Resolution, Section 903.2 amendment, effective July 1, 2025); Governed by the County's own 2024 Fire Code Resolution (2024 International Fire Code and 2024 IWUIC), administered by Jackson Hole Fire/EMS, as referenced in the preamble of Resolution 25-031; A plan review is required before installation, billed hourly with a stated minimum charge; use of outside consultants for plan review is billed at actual cost if Fire/EMS staff cannot perform the review in-house; Fire sprinkler/alarm permit fees are NOT published in or processed through the County Planning & Building Schedule of Fees — the County's own fee schedule directs applicants to contact Jackson Hole Fire/EMS directly. If your project isn't listed, confirm with Teton County Planning & Building Services Department — Building Division at 307-733-3959 (Building Official/fee estimates: 307-733-7030; Inspection Line: 307-732-5745) before starting work.

Yes. Resolution 25-031 explicitly scopes itself to 'Unincorporated Areas of Teton County outside of the Town of Jackson,' effective January 1, 2026. This is the reverse of the situation inside Town of Jackson limits, where the Town's own Resolution 25-18 Appendix A fee schedule governs fire permits instead.

Unincorporated Teton County does not publish a plan-review timeline for this permit. Contact Teton County Planning & Building Services Department — Building Division at 307-733-3959 (Building Official/fee estimates: 307-733-7030; Inspection Line: 307-732-5745) for current turnaround.

You'll need: Fire Alarm/Sprinkler Permit Application (via SmartGov Public Portal); Fire Protection System Plans. Depending on your project, Unincorporated Teton County may also ask for: Associated Building Permit Number. See the required-documents checklist on this page for details on each.

Unincorporated Teton County requires 2 inspection(s) for a fire sprinkler / fire alarm permit, in order: Rough — System Installation, Final — Fire and Life Safety Inspection. Schedule each through Teton County Planning & Building Services Department — Building Division (307-733-3959 (Building Official/fee estimates: 307-733-7030; Inspection Line: 307-732-5745)).

Apply through Teton County Planning & Building Services Department — Building Division at 200 S. Willow Street, Jackson, WY 83001 (P.O. Box 1727, Jackson, WY 83001-1727). Phone: 307-733-3959 (Building Official/fee estimates: 307-733-7030; Inspection Line: 307-732-5745), email: permittech@tetoncountywy.gov. Office hours: Applications submitted through the Teton County Online Portal (SmartGov); New Residential Construction, Commercial New Construction, and Miscellaneous (under 500 sq ft) permits require a scheduled submission/take-in week booked via the Bookings page. Trade permits (mechanical, plumbing, demolition, re-roof) do not require a submission week and are typically issued within 48 hours.. Official information: https://www.tetoncountywy.gov/560/Building.

Unincorporated Teton County, Wyoming has adopted: 2024 International Building Code (IBC), including Appendix C (Group U-Agricultural Buildings) and Appendix I (Patio Covers) — Teton County Building Codes Resolution, effective February 1, 2025; 2024 International Residential Code (IRC), including Appendix BB (Tiny Houses) and Appendix AF (Radon Control Methods) — effective February 1, 2025; 2024 International Plumbing Code (IPC), including Appendix E (Sizing of Water Piping System); 2024 International Mechanical Code (IMC), including Appendix A (Combustion Air Openings and Chimney Connector Pass-Throughs); 2024 International Fuel Gas Code (IFGC), all appendices excluded; 2021 International Energy Conservation Code (IECC), all appendices excluded; 2024 International Existing Building Code (IEBC), including Appendix A (Guidelines for the Seismic Retrofit of Existing Buildings); 2024 International Property Maintenance Code (IPMC), applied only to the extent referenced provisions relate to fire and life safety; 2023 National Electrical Code (NEC) — enforced by the Electrical Division of the Jackson Hole Fire/EMS Department (Section 101.4.8 Electrical, County Building Codes Resolution); 2024 International Wildland-Urban Interface Code (IWUIC) — adopted jointly by the Town of Jackson and Teton County; enforced by Jackson Hole Fire/EMS. Local amendments apply — see the Unincorporated Teton County overview page for the full list.

Jackson Hole Fire/EMS's Fire and Electrical Division — the same jointly-funded Town of Jackson / Teton County fire district that also administers electrical permits for the county — not the Teton County Planning & Building Services Department directly. The County's own 2026 Schedule of Fees confirms this, stating simply to contact Jackson Hole Fire/EMS for fire sprinkler and alarm permits and fees.