Residential Addition / Remodel / Alteration Permit in Flagstaff, Arizona

Required for additions, remodels, and structural alterations to existing one- and two-family dwellings in Flagstaff, including decks over 30 inches high or over 200 sq ft, garages, and interior remodels affecting structural or life-safety elements. Reviewed against the 2018 IRC as adopted by the City of Flagstaff. Apply through the Citizen Access Portal.

Verified 2026-07-03 · Source

When you need this permit

  • Building permit required for additions, remodels, and alterations affecting structural, fire, or life-safety elements
  • Decks over 30 inches above finished grade, over 200 sq ft, or attached to the main structure require a Building Permit; smaller detached decks use the Minor Improvement Permit (Zoning) instead
  • Small Residential Plans category (per City review-timeframe schedule) explicitly includes additions, garages, decks, remodels, repairs, carports, storage sheds greater than 200 sq ft, ramadas, greenhouses, and sun rooms
  • Plans must comply with City of Flagstaff Building Design Criteria (60 psf ground snow load, 115 mph wind, Seismic Category C, 30-inch frost depth)
  • Additions/alterations to existing 1-2 family dwellings are exempt from the new-construction EV charging circuit requirement

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee (valuation-based, ICC February 2017 BVD methodology)City of Flagstaff Resolution 2017-21; BVD does not apply cleanly to alterations/repairs of existing structures per ICC guidance, but the City uses this methodology as its general fee basis
Gross Area x Square Foot Construction Cost x 0.01 permit fee multiplier, plus 65% plan review fee

Review timeline

Plan reviewFlagstaff’s published plan-review target
20–35 business days

How long did your Residential Addition / Remodel / Alteration Permit permit actually take in Flagstaff?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Required before concrete pour for deck posts, garage foundations, or addition footings

  2. 2

    Framing

    Structural framing, connections to existing structure

  3. 3

    Final

    All work complete per approved plans

See the full Flagstaff inspection guide — scheduling & re-inspection fees →

Tips

  • 'Small Residential Plans' (additions, garages, decks, remodels, repairs, carports, sheds over 200 sq ft, ramadas, greenhouses, sun rooms) get a 10-working-day Administrative Completeness Review + 25-working-day Substantive Review = 35 working days overall.
  • Revisions to already-approved plans have a separate, shorter timeframe: 10 working days Administrative Completeness Review + 10 working days Substantive Review = 20 working days overall.
  • Decks 30 inches or less above grade, unattached, and 200 sq ft or under may qualify for the $80 Minor Improvement (Zoning) Permit instead of a full Building Permit — confirm with the Planner of the Day.

Frequently asked questions

A Building Permit is required for decks over 30 inches above finished grade, over 200 sq ft, or attached to the main structure. Smaller, detached decks can use the $80 Minor Improvement Permit (Zoning) instead. Source: City of Flagstaff Minor Improvement Permit Application checklist.

In Flagstaff, the published Building Permit Fee (valuation-based, ICC February 2017 BVD methodology) is: Gross Area x Square Foot Construction Cost x 0.01 permit fee multiplier, plus 65% plan review fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Flagstaff's published plan-review target for a residential addition / remodel / alteration permit is 20–35 business days.

You'll need: Residential Building Permit Application (PDF); Construction Drawings. See the required-documents checklist on this page for details on each.

Flagstaff requires 3 inspection(s) for a residential addition / remodel / alteration permit, in order: Footing/Foundation, Framing, Final. Schedule each through City of Flagstaff Building Safety Section (Planning & Development Services, Community Development Division) (928-213-2000).

Apply through City of Flagstaff Building Safety Section (Planning & Development Services, Community Development Division) at 211 W Aspen Avenue, Flagstaff, AZ 86001. Phone: 928-213-2000, email: BuildingPermits@flagstaffaz.gov. Office hours: City Hall is open 8:00 am to 4:30 pm. Commercial permit attachments too large for the portal: Commercial.BuildingPermits@flagstaffaz.gov. Inter-departmental submittals: FrontCounter@flagstaffaz.gov.. Official information: https://www.flagstaff.az.gov/494/Building-Safety.

Flagstaff, Arizona has adopted: Arizona has no mandatory statewide building code edition — cities and counties each adopt and amend their own codes (per Arizona Revised Statutes framework for municipal building regulation; no state building-code-adoption agency parallel to Montana's DLI exists). The City of Flagstaff independently administers its own Building Safety program within city limits, separate from Coconino County's building department, which handles unincorporated county areas. Source: City of Flagstaff Building Safety page (flagstaff.az.gov/494/Building-Safety) and Building Permits page.; 2018 International Building Code (IBC) — adopted by City of Flagstaff Resolution 2019-26 and Ordinance 2019-16 on June 18, 2019, effective July 19, 2019 (the '2018 Suite of Codes'). Source: City of Flagstaff 2019 Adopted Building Codes (PDF); 2018 International Residential Code (IRC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Existing Building Code (IEBC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Mechanical Code (IMC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Plumbing Code (IPC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019 (Arizona/Flagstaff uses the IPC, not the Uniform Plumbing Code); 2018 International Fuel Gas Code (IFGC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Energy Conservation Code (IECC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Swimming Pool and Spa Code (ISPSC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; 2018 International Solar Energy Provisions (ISEP) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; a compilation of solar energy provisions from the IBC, IRC, IECC, IMC, IPC, IFC, and ISPSC; 2017 NFPA 70 / National Electrical Code (NEC) — adopted per Resolution 2019-26 / Ordinance 2019-16, effective July 19, 2019; ICC A117.1-2017, Accessible and Usable Buildings and Facilities — adopted per Resolution 2019-26 / Ordinance 2019-16; 1997 Uniform Housing Code, 1997 Uniform Administrative Code, and 1997 Uniform Code for the Abatement of Dangerous Buildings (ICBO) — retained as adopted codes per Flagstaff City Code Title 4, Chapter 4-01; All codes amended locally by Flagstaff City Code Title 4, Building Regulations (Chapters 4-01 through 4-11), on file with the City Clerk. Source: Flagstaff City Code Title 4 Building Regulations amendments document (2019 Amendments to the Adopted Codes, PDF, rev. 05/14/2019); Statewide overlay: Arizona Revised Statutes Section 9-468 sets mandatory statewide standards for solar photovoltaic and solar water heating construction permits (limits on required plan documentation, prohibits requiring a PE stamp absent a written justification, and caps solar permit fees at actual cost of issuance) — binding on the City of Flagstaff as a municipality. Source: azleg.gov ARS 9-468; Arizona Revised Statutes Sections 9-835 and 9-836 set statutory residential building-permit plan-review timeframes (Administrative Completeness Review and Substantive Review stages) that the City of Flagstaff's published review timeframes implement. Source: City of Flagstaff Residential Building Permits Plan Review Process and Timeframes (PDF). Local amendments apply — see the Flagstaff overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Flagstaff building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.