Unincorporated Coconino County building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Coconino County, Arizona.

Verified 2026-07-07 · Source

How to schedule

Inspections are requested through the building department below.

Address
2500 N. Fort Valley Road, Building 1, Flagstaff, AZ 86001-1287
Phone
928-679-8850 (toll-free 800-559-9289); fax 928-679-8851
Office hours
Monday-Friday, 8:00 a.m.-5:00 p.m. Director: Jay Christelman; Assistant Director: Jess McNeely. All building permit applications and document submittals for unincorporated Coconino County are made online through the Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); only PDF files are accepted for plan review submittals.

Inspection sequence

Applies to: Residential Building Permit (Single-Family Dwelling, ADU, Model Home, Tiny House)

  1. 1

    Foundation/Footing

    Before concrete pour — verify footing depth, dimensions, and reinforcement per 2018 IRC

  2. 2

    Framing

    After framing, sheathing, and rough-in trades complete — before insulation or wall cover

  3. 3

    Insulation

    Insulation installed per 2018 IECC/IRC requirements before wall cover

  4. 4

    Final

    All work complete per approved plans; Certificate of Occupancy issued

Applies to: Commercial Building Permit (New Construction, Tenant Improvement, Remodel)

  1. 1

    Footing/Foundation

    Before concrete pour — per 2018 IBC

  2. 2

    Framing / Structural

    After structural framing complete, before wall cover

  3. 3

    Final

    All work complete per approved plans; Certificate of Occupancy issued

Applies to: Manufactured Home / Factory-Built Building Permit

  1. 1

    Foundation/Set

    Verify blocking, anchoring, and foundation/tie-down system per manufacturer specifications and state installation standards

  2. 2

    Utility Connections

    Electrical, plumbing, and gas connections verified

  3. 3

    Final

    Skirting, steps/decks, and all utility connections complete; unit ready for occupancy

Applies to: Plumbing Permit

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    Fixtures connected, water heater and gas connections verified, no leaks

Applies to: Residential Miscellaneous Permit (Additions, Remodels, Decks, Fences, Sheds, Pools, Re-Roofing, and More)

  1. 1

    Footing/Foundation

    Before concrete pour for additions, decks, retaining walls, pools

  2. 2

    Framing / Structural

    Structural connections, framing, and any electrical/mechanical/plumbing rough-in before cover

  3. 3

    Final

    Completed work verified against approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and box placement before wall cover; or service equipment installed before energizing

  2. 2

    Final

    All electrical work complete and operational per 2017 NEC

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Wiring and conduit for the EV charger circuit installed before wall cover, if applicable, per 2017 NEC

  2. 2

    Final

    EVSE equipment connected and operational, breaker sizing and grounding verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In / Equipment

    Equipment installed and ductwork complete before wall cover or concealment

  2. 2

    Final

    Equipment operational; combustion air and venting verified per 2018 IMC/IFGC

Re-inspection fees

Manufactured Home / Factory-Built Building PermitFactory Built Building — Residential / Commercial / Classroom (includes 3 inspections) · Part III. Installation re-inspection not covered by the permit: $120.00 per inspection.
Per-story/per-linear-foot fee per Part III (each category includes 3 inspections)

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Coconino County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Coconino County building permits

Get alerts for Unincorporated Coconino County

We'll email you when Unincorporated Coconino County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.