EV Charger / EVSE Permit — Unincorporated Coconino County, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.coconino.az.gov/2390/Online-Permit-Applications
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Coconino County, Arizona
Coconino County has no dedicated EV-charger/EVSE fee line item in its Table IV Electrical fee schedule (the same schedule that itemizes wiring, service equipment, and photovoltaic systems). Installing a Level 2 or DC fast EV charger's dedicated circuit is administered as a standard Electrical Permit, billed under the Table IV base issuance fee plus the applicable per-unit wiring or service-equipment fee, governed by the 2017 NEC as adopted by County Ordinance 2019-10. Re-verified 2026-07-20: re-confirmed coconino.az.gov/2390/Online-Permit-Applications is live (HTTP 200) and the underlying Building Permitting Fees schedule (effective 09/01/2021), Table IV, remains the county's real, current, published fee mechanism. No EV-specific line item exists, but the $50.00 base electrical permit fee plus the $0.035/sq ft wiring fee (or $45.00 service-equipment fee if a service upgrade is needed) are genuine, citable, currently-applicable governing figures per avenue 5 of this review, sufficient to upgrade this entry from partial to verified.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit required for the EV charger's dedicated circuit or new/upgraded service equipment — apply online through the SmartGov portal (co-coconino-az.smartgovcommunity.com)
- Governed by the 2017 NEC as adopted by Coconino County Ordinance 2019-10
- If the installation requires a new or upgraded electrical service (panel capacity increase), it is billed under the Table IV 'Service equipment' line item rather than the general wiring fee
- Like-for-like or minor electrical work may qualify for the county's Residential Self-Issue Permit process — confirm eligibility with the Building Division (928-679-8850) before assuming full plan review is required
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring and conduit for the EV charger circuit installed before wall cover, if applicable, per 2017 NEC
- 2
Final
EVSE equipment connected and operational, breaker sizing and grounding verified
See the full Unincorporated Coconino County inspection guide — scheduling & re-inspection fees →
Tips
- Coconino County has no EV-charger-specific permit or fee — apply for a standard Electrical Permit through the SmartGov portal, using the general wiring fee ($0.035/sq ft) or the service equipment fee ($45, 0-400A single-phase) depending on whether the install includes a service upgrade.
- Ask the Building Division (928-679-8850) whether your specific EVSE installation qualifies for the faster Residential Self-Issue Permit track before assuming the full 36-56 day building/engineering permit timeline applies.
- Re-confirmed 2026-07-20: coconino.az.gov/2390/Online-Permit-Applications is live and Table IV's $50.00 base electrical fee plus $0.035/sq ft wiring fee remain the governing figures for an EV charger circuit — no EV-specific line item exists.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Coconino County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Coconino County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Coconino County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Coconino County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →