Plumbing Permit in Unincorporated Coconino County, Arizona

Required for plumbing installation, alteration, or repair work in unincorporated Coconino County, governed by the 2018 International Plumbing Code (IPC). Billed under the county's per-unit Table IV Plumbing fee schedule. Wastewater-connected work requires coordination with the Environmental Quality Division. Applications submitted online through the SmartGov portal.

Verified 2026-07-07 · Source

When you need this permit

  • Required for installation, alteration, or repair of plumbing systems, fixtures, water heaters, and gas piping in unincorporated Coconino County
  • Governed by the 2018 IPC as adopted by County Ordinance 2019-10
  • Apply online through the SmartGov portal (co-coconino-az.smartgovcommunity.com)
  • For areas with community sewers (e.g., Pinewood, Kachina Village), proof of available sewer connection is required; for onsite wastewater/septic systems, Environmental Quality Division review is required alongside the building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fee to issue plumbing permitCoconino County Building Permitting Fees schedule (effective 09/01/2021), Table IV, Plumbing section.
$50.00 base
Plumbing fixture or trapTable IV, Plumbing section — the source PDF's exact figures for the per-fixture/per-system plumbing line items (fixture/trap, building sewer, water heater, water piping, gas piping by outlet count) showed row/column ambiguity on text extraction; the base-fee-plus-per-fixture STRUCTURE is confirmed, but reconfirm exact current dollar figures directly with the county (928-679-8850) before quoting a specific number.
$3.00 each system (per Table IV structure)
Gas piping system: 1 to 4 outlets / each additional outlet over 4Table IV, Plumbing section.
Evaluated as private garage/utility/miscellaneous per Valuation Table I for 1-4 outlets; per-outlet add-on beyond 4
Plan Review Fee (where full plan review is required)Coconino County Building Permitting Fees schedule, Part I, Section D.
65% of the calculated permit fee

Review timeline

Plan reviewUnincorporated Coconino County’s published plan-review target
36–56 business days

How long did your Plumbing Permit permit actually take in Unincorporated Coconino County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground/Slab

    Before concrete pour — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed

  3. 3

    Final

    Fixtures connected, water heater and gas connections verified, no leaks

See the full Unincorporated Coconino County inspection guide — scheduling & re-inspection fees →

Tips

  • Properties in community-sewer areas (Pinewood, Kachina Village, and similar) must show proof of available sewer connection; properties relying on an onsite wastewater system need a coordinated Environmental Quality Division review alongside the building/plumbing permit.
  • The minimum fee for any single Coconino County permit is $50.00, inclusive of plan review unless additional review is required.

Frequently asked questions

Unincorporated Coconino County requires a plumbing permit for: Required for installation, alteration, or repair of plumbing systems, fixtures, water heaters, and gas piping in unincorporated Coconino County; Governed by the 2018 IPC as adopted by County Ordinance 2019-10; Apply online through the SmartGov portal (co-coconino-az.smartgovcommunity.com); For areas with community sewers (e.g., Pinewood, Kachina Village), proof of available sewer connection is required; for onsite wastewater/septic systems, Environmental Quality Division review is required alongside the building permit. If your project isn't listed, confirm with Coconino County Community Development Department, Building and Safety Division at 928-679-8850 (toll-free 800-559-9289); fax 928-679-8851 before starting work.

In Unincorporated Coconino County, the published Fee to issue plumbing permit is: $50.00 base. Additional published fees: Plumbing fixture or trap — $3.00 each system (per Table IV structure); Gas piping system: 1 to 4 outlets / each additional outlet over 4 — Evaluated as private garage/utility/miscellaneous per Valuation Table I for 1-4 outlets; per-outlet add-on beyond 4; Plan Review Fee (where full plan review is required) — 65% of the calculated permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Coconino County's published plan-review target for a plumbing permit is 36–56 business days.

You'll need: Online Permit Applications Portal Submission. Depending on your project, Unincorporated Coconino County may also ask for: Plumbing Schematic. See the required-documents checklist on this page for details on each.

Unincorporated Coconino County requires 3 inspection(s) for a plumbing permit, in order: Underground/Slab, Rough-In, Final. Schedule each through Coconino County Community Development Department, Building and Safety Division (928-679-8850 (toll-free 800-559-9289); fax 928-679-8851).

Apply through Coconino County Community Development Department, Building and Safety Division at 2500 N. Fort Valley Road, Building 1, Flagstaff, AZ 86001-1287. Phone: 928-679-8850 (toll-free 800-559-9289); fax 928-679-8851, email: plansubmittals@coconino.az.gov. Office hours: Monday-Friday, 8:00 a.m.-5:00 p.m. Director: Jay Christelman; Assistant Director: Jess McNeely. All building permit applications and document submittals for unincorporated Coconino County are made online through the Online Permit Applications portal (co-coconino-az.smartgovcommunity.com); only PDF files are accepted for plan review submittals.. Official information: https://www.coconino.az.gov/624/Building-and-Safety.

Unincorporated Coconino County, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 11 for counties). Coconino County Community Development Department, Building and Safety Division, is the code enforcement agency and building official for all unincorporated areas of the county (areas outside Flagstaff, Page, Fredonia, Tusayan, and Williams, and outside the Coconino County portion of Sedona).; As of this record's verification date (July 2026), the Coconino County Building Division's current adopted codes are: 2018 International Residential Code (IRC); 2018 International Building Code (IBC); 2018 International Mechanical Code (IMC); 2018 International Fuel Gas Code (IFGC); 2018 International Plumbing Code (IPC); 2018 International Energy Conservation Code (IECC); 2018 International Existing Building Code (IEBC); and 2017 National Electrical Code (NEC). Adopted via County Ordinance 2019-10 ('2019-10 Coconino County Building Ordinance — adopting the 2018 Suite of Building Codes with Amendments'). Source: Coconino County Building Codes, Ordinances, Design Criteria page (coconino.az.gov/2391/Building-Codes-Ordinances-Design-Criteri), 'Current Codes and Ordinances' section, rendered/read directly July 2026.; Every six years the Community Development Department, in partnership with the Building Safety Advisory Board (BSAB), leads a process to adopt updated codes. As of this record's date, the County has begun a public process toward adopting the 2024 ICC code suite and 2023 NEC — an open house was held March 23, 2026 at 2500 N. Fort Valley Rd. (Thomas Auditorium), and a slide deck covering the 2024 IECC, IBC, IPC, IMC, IFGC and 2023 NEC changes was presented — but as of this record's lastVerified date that update had NOT yet been formally adopted. The 2018 ICC / 2017 NEC baseline remains the current, controlling code. Source: Coconino County Building Codes, Ordinances, Design Criteria page, 'Building Code Adoption' section.; Additional adopted county ordinances/codes beyond the base ICC/NEC suite: Potable Rainwater Collection and Distribution Systems Code (an amendment to the IRC); 2020-11 Earthen Building and Construction Ordinance (regulating quality, type of material, testing, and workmanship for earthen buildings/structures). Source: Coconino County Building Codes, Ordinances, Design Criteria page.; The Innovative Materials and Systems Pilot Program (part of the 2019-10 Ordinance) allows owner-builders to seek an exemption from standard adopted-code provisions when building with alternative methods and materials, under conditions evaluated by the Building Official — administered in coordination with the County's broader 'Building with Alternative Methods and Materials' / Alternative Methods and Materials Permit Program (ATAG certification and consultation process) run out of the Community Development Department. Source: Coconino County Building Codes, Ordinances, Design Criteria page; Coconino County Community Development page (coconino.az.gov/136/Community-Development), 'Building with Alternative Methods and Materials' section.; Manufactured homes and factory-built buildings follow a joint state/local structure: the Arizona Department of Fire, Building and Life Safety (Office of Manufactured Housing) sets manufacturer/installer/retailer licensing and issues state-level installation permits, while local site/foundation/utility compliance is handled by Coconino County under a dedicated Manufactured Homes and Factory Built Building Permit fee schedule (Part III of the county's Building Permitting Fees) and a 7-business-day review ceiling under the county's own timeframes policy. Source: Coconino County Online Permit Applications page (coconino.az.gov/2390/Online-Permit-Applications), 'Manufactured Homes & Factory Built Projects' section; Coconino County Building Permitting Fees schedule, Part III.; Properties within the Sedona Fire District (including Oak Creek Canyon) are additionally subject to the 2018 Wildland and Urban Interface Codes as adopted by that fire district; fire suppression systems are required in addition to Wildland-Urban-Interface-code compliance, and the Sedona Fire Marshal conducts concurrent plan reviews with Coconino County to ensure compliance. Source: Coconino County Building Codes, Ordinances, Design Criteria page, 'Building Within the Sedona Fire District' section.. Local amendments apply — see the Unincorporated Coconino County overview page for the full list.

The 2018 International Plumbing Code (IPC), as adopted by County Ordinance 2019-10, as of this record's verification date. Source: https://www.coconino.az.gov/2391/Building-Codes-Ordinances-Design-Criteri

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Coconino County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.