Graham County breaks the common Arizona pattern: rather than relegating fire entirely to an independent fire district, the County has adopted the 2003 International Fire Code as part of its own Graham County Building Code, and its Community Development Director serves as the building official charged with administering and enforcing that code. However, the County publishes no separate fire-permit fee line and no fire application — fire protection system work is handled through the building permit, and the exact intake path is not published.

Reviewed 2026-08-15 · Source

When you need this permit

  • Graham County Planning and Zoning Ordinance Section 5.14.2(7) adopts by reference the 'International Fire Code, 2003 edition, published by the International Code Council, Inc.' as one of the codes making up the Graham County Building Code (Section 5.14.2(1) adopts the 2003 IBC 'together with the following national and international codes')
  • The County's own Planning & Zoning web page independently lists '2003 International Fire Code' under 'Codes Adopted by Graham County'
  • Zoning Ordinance Section 5.14.4 (Building official designated): 'The Community Development Director shall serve as the building official. The building official or his duly authorized representative, is the authority charged with the administration and enforcement of the Graham County Building Code.' Because the adopted Building Code includes the 2003 IFC, that administration and enforcement authority extends to the fire code.
  • Zoning Ordinance Section 5.14.1 states the Graham County building code's purposes include regulating 'the site preparation and construction, alteration, moving, demolition, repair, use and occupancy of buildings, structures and building service equipment within the jurisdiction' and to 'Provide for issuance of permits and collection of fees'
  • Fire apparatus access is a published Certificate of Occupancy condition — Zoning Ordinance Section 5.13.7(4), whose preamble frames items 1-5 as 'an example of requirements that must be met' when applying for rezoning, building permits, or improvements of any kind: 'Prior to the issuance of a Certificate of Occupancy, the physical access (as indicated on the legal survey (if required) or as indicated on the approved site plan) must be completed, and must satisfy the requirements for fire apparatus access in accordance with the International Fire Code adopted by Graham County.'
  • Zoning Ordinance Section 5.14.3: a copy of the Graham County Building Codes is available for public inspection at the Planning and Zoning Department, 2nd floor, 921 Thatcher Blvd., Safford, during regular working hours — the adopted code text is not published online
  • Apply through the County's iWorQ citizen portal (Building / Addition / Remodel application) or in person at Planning & Zoning; upload the Plot Plan Sketch and building plans or the submission will be rejected

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire protection system work — building permit feeGraham County Inspection Fees PDF, Section 5.18.1 Inspection and Plan Review Fees — read from a 200 dpi rendered image of the single-page PDF (text extraction of this table mis-stacks the valuation column against the fee column and is not usable). NO fire-specific fee line exists anywhere in the Graham County Fee Schedule (REV 08/02/2022); this is the County's general valuation-based building permit formula.
Valuation-based per Zoning Ordinance Section 5.15 / Section 5.18.1: $1.00-$500.00 = $20; $501.00-$2,000.00 = $20.00 for the first $500.00 plus $1.00 for each additional $100.00; $2,001.00-$25,000.00 = $20.00 for the first $2,000.00 plus $4.00 for each additional $1,000.00; $25,001.00-$50,000.01 = $112.00 for the first $25,000.00 plus $3.00 for each additional $1,000.00; $50,000.00-$100,000.00 = $187.00 for the first $50,000.00 plus $2.00 for each additional $1,000.00; $100,001.00-$500,000.00 = $287.00 for the first $100,000.00 plus $1.50 for each additional $1,000.00; $500,001.00 and up = $887.00 for the first $500,000.00 plus $1.00 for each additional $1,000.00
Administrative fee (added to permit fee)Graham County Fees for Planning & Zoning Department, REV 08/02/2022 — read from a 200 dpi rendered image. The schedule lists this immediately below the Building Permit row as 'Administrative fee (added to permit fee).'
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm Permit (Fire Protection System) permit actually take in Unincorporated Graham County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough / concealed fire protection piping and wiring

    Fire protection system components inspected before concealment as part of the County's building inspection sequence; Graham County employs its own building inspectors

  2. 2

    Final / Certificate of Occupancy

    Before a Certificate of Occupancy issues, physical access must be complete and satisfy the fire apparatus access requirements of the International Fire Code adopted by Graham County

See the full Unincorporated Graham County inspection guide — scheduling & re-inspection fees →

Tips

  • This is a genuine Arizona pattern-break. Many Arizona counties adopt no fire code and hand the whole subject to an independent fire district; Graham County adopted the 2003 International Fire Code as part of its own Building Code and made its Community Development Director the building official charged with administering it.
  • But the practical mechanics are not published. There is no fire-permit fee line in the Fee Schedule (REV 08/02/2022) and no fire application among the iWorQ portal's five application types (Building/Addition/Remodel, Solar/Electrical/Gas Only, Temporary RV, Manufactured Home, Outbuilding). Call Planning & Zoning at 928-428-0410 before designing your submittal.
  • The adopted 2003 IFC text is not online. Zoning Ordinance Section 5.14.3 says a copy of the Graham County Building Codes is available for public inspection at the Planning and Zoning Department, 2nd floor, 921 Thatcher Blvd., Safford, during regular working hours.
  • The code edition is old — 2003 IFC alongside a 2003 IBC/IRC/IEBC, a 1994 Uniform Plumbing Code and a 2002 (or, per a conflicting section of the same ordinance, 1999) NEC. Design assumptions carried over from a 2018- or 2021-code jurisdiction will not map cleanly.
  • Fire apparatus access is a hard gate on the Certificate of Occupancy, not a soft one: the physical access shown on the legal survey or approved site plan must be complete and satisfy the adopted IFC's fire apparatus access requirements before a CofO issues.

Frequently asked questions

Unincorporated Graham County requires a fire sprinkler / fire alarm permit (fire protection system) for: Graham County Planning and Zoning Ordinance Section 5.14.2(7) adopts by reference the 'International Fire Code, 2003 edition, published by the International Code Council, Inc.' as one of the codes making up the Graham County Building Code (Section 5.14.2(1) adopts the 2003 IBC 'together with the following national and international codes'); The County's own Planning & Zoning web page independently lists '2003 International Fire Code' under 'Codes Adopted by Graham County'; Zoning Ordinance Section 5.14.4 (Building official designated): 'The Community Development Director shall serve as the building official. The building official or his duly authorized representative, is the authority charged with the administration and enforcement of the Graham County Building Code.' Because the adopted Building Code includes the 2003 IFC, that administration and enforcement authority extends to the fire code.; Zoning Ordinance Section 5.14.1 states the Graham County building code's purposes include regulating 'the site preparation and construction, alteration, moving, demolition, repair, use and occupancy of buildings, structures and building service equipment within the jurisdiction' and to 'Provide for issuance of permits and collection of fees'; Fire apparatus access is a published Certificate of Occupancy condition — Zoning Ordinance Section 5.13.7(4), whose preamble frames items 1-5 as 'an example of requirements that must be met' when applying for rezoning, building permits, or improvements of any kind: 'Prior to the issuance of a Certificate of Occupancy, the physical access (as indicated on the legal survey (if required) or as indicated on the approved site plan) must be completed, and must satisfy the requirements for fire apparatus access in accordance with the International Fire Code adopted by Graham County.'; Zoning Ordinance Section 5.14.3: a copy of the Graham County Building Codes is available for public inspection at the Planning and Zoning Department, 2nd floor, 921 Thatcher Blvd., Safford, during regular working hours — the adopted code text is not published online; Apply through the County's iWorQ citizen portal (Building / Addition / Remodel application) or in person at Planning & Zoning; upload the Plot Plan Sketch and building plans or the submission will be rejected. If your project isn't listed, confirm with Graham County Planning and Zoning Department at 928-428-0410 before starting work.

No. The Graham County Fee Schedule (REV 08/02/2022) contains no fire-specific line item, and the iWorQ citizen portal offers no fire application. Fire protection system work is billed through the County's general valuation-based building permit formula plus the $100.00 administrative fee. Confirm the intake path with Planning & Zoning at 928-428-0410. Source: https://www.graham.az.gov/DocumentCenter/View/569/Fee-Schedule-PDF

Unincorporated Graham County does not publish a plan-review timeline for this permit. Contact Graham County Planning and Zoning Department at 928-428-0410 for current turnaround.

You'll need: Building plans; Plot Plan Sketch. Depending on your project, Unincorporated Graham County may also ask for: Special Power of Attorney form. See the required-documents checklist on this page for details on each.

Unincorporated Graham County requires 2 inspection(s) for a fire sprinkler / fire alarm permit (fire protection system), in order: Rough / concealed fire protection piping and wiring, Final / Certificate of Occupancy. Schedule each through Graham County Planning and Zoning Department (928-428-0410).

Apply through Graham County Planning and Zoning Department at 921 Thatcher Boulevard, 2nd Floor, Safford, AZ 85546. Phone: 928-428-0410. Office hours: Monday - Thursday, 7:00 a.m. - 6:00 p.m. (per the County's Department Directory listing for Planning & Zoning at 921 Thatcher Boulevard). No public-facing department email address was found published on the County's Planning & Zoning page, Permits & Hearing Forms page, or FAQ pages as of this review; contact by phone at 928-428-0410 or in person.. Official information: https://www.graham.az.gov/277/Planning-Zoning.

Yes. Planning and Zoning Ordinance Section 5.14.2(7) adopts the International Fire Code, 2003 edition, as part of the Graham County Building Code, and the County's own Planning & Zoning page lists the 2003 International Fire Code under 'Codes Adopted by Graham County.' Source: https://www.graham.az.gov/277/Planning-Zoning

The County's building official. Zoning Ordinance Section 5.14.4 provides that the Community Development Director shall serve as the building official and is the authority charged with the administration and enforcement of the Graham County Building Code — which includes the adopted 2003 International Fire Code. Source: https://www.graham.az.gov/DocumentCenter/View/574/County-Zoning-Ordinance-PDF

Sources & verification

Key facts verified against official sources. Last reviewed 2026-08-15.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Graham County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.