Commercial Building Permit (New Construction, Addition, Tenant Improvement) — Unincorporated Graham County, Arizona · Requirements sheet
Verified 2026-08-01 · Source: https://www.graham.az.gov/277/Planning-Zoning
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction, Addition, Tenant Improvement) in Unincorporated Graham County, Arizona
Required for commercial construction in unincorporated Graham County. The County does NOT operate a separately-named commercial permit process: its published Fee Schedule (rev. 08/02/2022) and Planning and Zoning Ordinance define a single 'Building Permit — Site permit for residential, commercial and industrial,' with commercial projects distinguished only by (1) a higher valuation rate ($125 per usable square foot vs. $100 residential) fed into the same Total-Valuation fee bracket table (Ordinance Section 5.15), and (2) a commercial-specific plan review fee of 65% of the building permit fee ('Plan Review for Development Plans for Commercial Development,' Ordinance Section 3.8 fee table). Commercial plans are reviewed against the 2003 IBC and 2003 IEBC as adopted (Ordinance Section 5.14.2), with fire apparatus access per the adopted 2003 IFC required before a Certificate of Occupancy is issued. Applications are submitted through the County's iWorQ online portal.
Verified 2026-08-01 · Source
When you need this permit
- Building permit required before erecting, constructing, reconstructing, altering, placing, or using any structure — including commercial buildings — in unincorporated Graham County (Ordinance Section 5.6.2); the permit must be obtained and paid for PRIOR to any improvement activity (Ordinance Section 5.13.7)
- Apply through the County's iWorQ online permit portal (https://grahamcounty.portal.iworq.net/portalhome/grahamcounty); upload building plans and a plot plan sketch (plus a Special Power of Attorney form if an agent/contractor applies for the owner) or the submission will be rejected
- Commercial plans are reviewed against the 2003 International Building Code and, for work on existing buildings, the 2003 International Existing Building Code, as adopted in Ordinance Section 5.14.2
- An approved septic system (required for residential and commercial use) must be in place or assured before occupancy is permitted; septic approval is handled by the Graham County Health Department as a parallel track (Ordinance Section 5.6.2(1))
- A drainage plan addressing on- and off-site drainage impact must be presented and approved by the County Engineer prior to permit issuance where drainage review applies; required drainage improvements must be completed, inspected, approved, and easements recorded before a Certificate of Occupancy is requested (Ordinance Section 5.13.7)
- Physical access must be completed and satisfy the fire apparatus access requirements of the International Fire Code adopted by Graham County (2003 IFC) before a Certificate of Occupancy is issued (Ordinance Section 5.13.7(4))
- The Zoning Official issues a Certificate of Occupancy after inspection before any building may be occupied for commercial or manufacturing purposes (Ordinance Section 5.6.2(1))
- Commercial use must be allowed in the parcel's land use zone (C-N, C-G, C-RE, C-M, M, or M-X, or via Conditional Use Permit in other zones); zoning approval by the Board of Supervisors, where required, must be obtained prior to builds and can take up to 90 days (Ordinance Sections 4.10-4.15, 5.13.7)
- Permit is valid for one year from date of issuance to start construction; a renewal permit is handled as a new permit (Ordinance Section 5.6.2)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Set Back Inspection
When the building pad is done and concrete forms are set — BEFORE any plumbing goes in (County's published six-stage sequence; the guidance sheet is written for new residential construction but is the County's only published inspection sequence and is cross-applicable to the same trades on commercial work)
- 2
Footings / Stem Wall / Underground Plumbing
BEFORE concrete is poured; all rebar must be visible
- 3
Sheathing & Framing
BEFORE any paper goes on the roof
- 4
Rough Electrical / Mechanical / Top-Out Plumbing / Gas Test
AFTER wiring is run and plumbing is in
- 5
Drywall Nailing
AFTER drywall is up and BEFORE any tape goes on
- 6
Final / Certificate of Occupancy
Everything complete; a failed final costs a $50 re-inspection fee. For commercial occupancy the Zoning Official issues a Certificate of Occupancy after inspection, and fire apparatus access (per the adopted 2003 IFC) and any required drainage improvements must be complete before the C of O is issued (Ordinance Sections 5.6.2(1), 5.13.7)
See the full Unincorporated Graham County inspection guide — scheduling & re-inspection fees →
Tips
- Graham County has NO separately-named commercial building permit or tenant-improvement permit: the Fee Schedule defines one unified 'Building Permit — Site permit for residential, commercial and industrial,' and a full-text search of the current 233-page Zoning Ordinance (2026-08-01) finds no tenant-improvement, remodel, or commercial-alteration permit process anywhere. Interior tenant-improvement/alteration work falls under the same Section 5.6.2 building-permit requirement ('erect, construct, reconstruct, ALTER, place, or use any structure') and would be reviewed under the adopted 2003 International Existing Building Code — how the County values a TI project for fee purposes (the $125/sq ft commercial rate is written for whole-building usable square footage) is not published; confirm valuation of alteration-only work with the Department (928-428-0410) before budgeting.
- Budget three fee components for commercial work: the valuation-based building permit fee ($125/sq ft usable x the Section 5.15 bracket table), a plan-review fee of 65% of the building permit fee (the ordinance's fee table words this line 'Plan Review for Development Plans for Commercial Development'), and the flat $100 administrative fee. Worked example from the published formula: a 2,000 sq ft commercial building = $250,000 valuation, giving a $512.00 permit fee ($287 + $1.50 x 150), plus $332.80 plan review (65%), plus $100 administrative = $944.80 total.
- Agricultural exemption (relevant in this heavily agricultural county): Ordinance Section 3.11 (Statutory Exemptions), implementing A.R.S. § 11-830, provides that the Ordinance 'shall not prevent, restrict, or otherwise regulate' the use or occupation of land or improvements for railroad, mining, metallurgical, grazing, or general agricultural purposes if the tract is at least five (5) contiguous commercial acres. A barn or ag-use building on a qualifying tract may therefore sit outside the County's permit reach — but the exemption is statutory and use-specific (a farm STORE or other commercial use does not qualify), so confirm a specific building's status with the Department before skipping the permit; building without a required permit costs up to 5X the normal fee.
- Commercial use must be allowed in the parcel's zoning (C-N, C-G, C-RE, C-M, M, or M-X, or by Conditional Use Permit — $350 application fee — elsewhere); where Board of Supervisors zoning approval is required first, the Ordinance itself warns it 'can potentially take up to 90 days' (Section 5.13.7). Most unincorporated county land is zoned 'A' (General/Agricultural), which does not permit commercial use outright.
- The County's adopted commercial codes are the 2003 IBC/IEBC/IFC family — materially older than the 2018-2024 cycles used by many incorporated Arizona cities. The Ordinance is also internally inconsistent on the NEC and mechanical-code editions (see this file's codesAdopted notes); confirm governing editions with the Department before finalizing commercial plans.
- Zoning-violation penalties are three times higher for commercial/industrial uses than residential ($300 initial / $600 non-compliance / $60 daily, vs. $100/$200/$20 for agricultural-residential) per the Ordinance's enforcement penalty table — another reason not to start commercial work ahead of the permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Graham County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Graham County.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Unincorporated Graham County
Commercial Building Permit (New Construction, Addition, Tenant Improvement) in other cities
Look up this fee in a different city →