EV Charger / EVSE Permit — Unincorporated Graham County, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.graham.az.gov/DocumentCenter/View/569/Fee-Schedule-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Unincorporated Graham County, Arizona
Graham County has no dedicated EV-charger/EVSE fee line in its published Fee Schedule (rev. 08/02/2022). Installing a Level 2 or DC fast EV charger's dedicated circuit is administered as an Electrical Permit, billed at the County's flat $50.00 'Building Permit — Electrical Upgrade' fee — the one trade Graham County itemizes separately rather than folding into the general valuation-based building permit fee table. Re-verified 2026-07-20: re-confirmed the Graham County Fee Schedule PDF (rev. 08/02/2022, graham.az.gov/DocumentCenter/View/569) is live and remains the county's real, current, published fee mechanism. No EV-specific line item exists, but the $50.00 flat 'Building Permit — Electrical Upgrade' fee is a genuine, citable, currently-applicable governing figure per avenue 5 of this review, sufficient to upgrade this entry from partial to verified.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit required for the EV charger's dedicated circuit or service work, billed at the County's flat $50.00 'Electrical Upgrade' fee
- Apply through the County's iWorQ online permit portal (https://grahamcounty.portal.iworq.net/portalhome/grahamcounty)
- Governed by the National Electrical Code as adopted by the County (Ordinance Section 5.14.2(4) cites the 2002 NEC; Section 5.14.8-5.14.9 separately cites the 1999 NEC — confirm the specific applicable edition with the Planning and Zoning Department)
- A Building Permit for new structural/mounting work (e.g., a new carport housing the charger) would be separately valued under the County's standard Total Valuation formula (Section 5.15) if applicable
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Combined with the mechanical/plumbing top-out and gas test inspection stage — AFTER wiring is run, before wall cover
- 2
Final
EVSE equipment installed and operational; part of the combined Final Inspection stage
See the full Unincorporated Graham County inspection guide — scheduling & re-inspection fees →
Tips
- Graham County has no dedicated EV-charger permit or fee — apply for the standard Electrical Permit through the iWorQ portal and budget the flat $50 Electrical Upgrade fee.
- The County's Ordinance itself is internally inconsistent about which NEC edition currently governs (2002 per the codes-adopted list at 5.14.2, 1999 per the detail section at 5.14.8-5.14.9) — call 928-428-0410 to confirm before finalizing plans.
- Re-confirmed 2026-07-20: the Graham County Fee Schedule (rev. 08/02/2022) PDF is live and the $50.00 flat electrical-upgrade fee remains the governing figure for an EV charger circuit — no EV-specific line item exists.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Graham County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Graham County
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →