Solar PV Permit — Unincorporated Graham County, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.graham.az.gov/DocumentCenter/View/569/Fee-Schedule-PDF
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Unincorporated Graham County, Arizona
Graham County has no dedicated solar/photovoltaic fee line in its published Fee Schedule (rev. 08/02/2022); a rooftop or ground-mounted residential PV installation is processed as a combination of a valuation-based Building Permit (for the racking/mounting/structural work) and an Electrical Permit (for the wiring and interconnection, billed at the County's flat $50 'Building Permit — Electrical Upgrade' fee). Arizona counties are separately bound by A.R.S. § 11-323 ('Solar construction permits; standards'), a statewide statute setting mandatory minimum standards for how counties must process residential solar permits — simplified plan-submittal content, no mandatory professional-engineer stamp, and permit fees that must be cost-justified and publicly documented.
Verified 2026-07-20 · Source
When you need this permit
- Building Permit required for the array's structural/mounting work, valued under the County's standard Total Valuation fee-bracket formula (Planning and Zoning Ordinance Section 5.15) — same formula used for other residential construction, not a solar-specific rate
- Electrical Permit required for the PV wiring, inverter, and point of interconnection — billed at the County's flat $50.00 'Electrical Upgrade' fee per the Fee Schedule (the one trade Graham County itemizes separately rather than folding into the general building permit fee)
- Per A.R.S. § 11-323(A)(1), the county's required plan submittal for a photovoltaic system is limited to: system location on the construction plans (roof plan and elevation), panel mounting details, and a one-line or three-line electrical diagram (a diagram is not required if a qualified online automated permitting platform is used)
- Per A.R.S. § 11-323(B), Graham County may not require a professional engineer's stamp on a residential solar PV permit application unless it provides a written explanation of why the stamp is necessary for that specific project
- Per A.R.S. § 11-323(C)-(D), any building/permit fee the County assesses for solar construction must be attributable to and not exceed the actual cost of issuing the permit, and the County's fee-calculation methodology must be publicly published, with a written itemized cost breakdown available on request
- Apply through the County's iWorQ online permit portal (https://grahamcounty.portal.iworq.net/portalhome/grahamcounty)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
PV wiring, combiner, and disconnect inspected before wall/roof cover, combined with the mechanical/plumbing top-out inspection stage per the County's standard inspection sequence
- 2
Final
Array mounting, bonding/grounding, and point of interconnection complete and operational
See the full Unincorporated Graham County inspection guide — scheduling & re-inspection fees →
Tips
- Graham County has no dedicated 'Solar Permit' fee — budget for both a valuation-based Building Permit (structural/mounting) and the flat $50 Electrical Upgrade fee, plus the $100 administrative fee.
- Arizona's A.R.S. § 11-323 caps what a county can charge for a solar permit to the actual cost of issuing it and requires the fee methodology to be publicly documented — if Graham County cannot produce a written cost breakdown on request, that is a statutory compliance question worth raising with the Planning and Zoning Department.
- The statute also limits what the County can require on your plan set (roof plan/elevation, mounting details, one-line/three-line diagram) and bars a mandatory PE stamp absent a written justification — useful leverage if a reviewer asks for more than that baseline.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Graham County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Graham County
Solar PV Permit in other cities
Compare solar pv permit fees across Arizona →
Look up this fee in a different city →