Demolition Permit in Lake Havasu City, Arizona

Required for demolition of any residential or commercial structure in Lake Havasu City, billed as a flat miscellaneous permit fee (with surcharge) under the City's Building Permit Retainers/Fees schedule.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required before demolishing a residential or commercial structure within Lake Havasu City limits
  • Owner authorization and site information required identifying the structure(s) to be demolished
  • All utilities must be terminated/capped before demolition
  • Asbestos survey/ADEQ notification (Arizona Department of Environmental Quality Asbestos Form) required prior to demolition where applicable — Lake Havasu City's Building Division publishes an 'ADEQ Asbestos Form' as part of its standard forms library
  • Project is not legally complete until an approved final inspection has occurred

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition Permit (flat fee, includes 1.25% surcharge)City of Lake Havasu City Building Permit Retainers/Fees handout (Development Services Department, rev. 01/03/22), Miscellaneous section, marked with a 1.25% surcharge asterisk
$75.94

Review timeline

Plan reviewLake Havasu City’s published plan-review target
10–10 business days

How long did your Demolition Permit permit actually take in Lake Havasu City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final

    Verifies utility termination, site condition, and debris removal; the project is not legally complete without an approved final inspection

See the full Lake Havasu City inspection guide — scheduling & re-inspection fees →

Tips

  • Demolition is billed as a flat $75.94 fee (a base amount plus the City's standard 1.25% surcharge applied to several miscellaneous permit categories) rather than a valuation-based fee, per the Building Permit Retainers/Fees handout.
  • Verify asbestos-abatement requirements with ADEQ using the City's published ADEQ Asbestos Form before applying — this is a City-published prerequisite form, not merely an informal recommendation.
  • Demolition is processed under the City's 'Miscellaneous' plan-review category at 10 business days per the published timeframes, consistent with Arizona's A.R.S. § 9-835 municipal time-frames requirement.

Frequently asked questions

Lake Havasu City requires a demolition permit for: Building permit required before demolishing a residential or commercial structure within Lake Havasu City limits; Owner authorization and site information required identifying the structure(s) to be demolished; All utilities must be terminated/capped before demolition; Asbestos survey/ADEQ notification (Arizona Department of Environmental Quality Asbestos Form) required prior to demolition where applicable — Lake Havasu City's Building Division publishes an 'ADEQ Asbestos Form' as part of its standard forms library; Project is not legally complete until an approved final inspection has occurred. If your project isn't listed, confirm with Lake Havasu City Development Services Department — Building Division at 928-453-4148 before starting work.

$75.94 flat fee (inclusive of the City's standard 1.25% surcharge), per the City of Lake Havasu City Building Permit Retainers/Fees handout, Miscellaneous section.

Demolition is processed under the City's 'Miscellaneous' category on its published plan-review timeframes, which allots 10 business days.

You'll need: Building Permit Application (Demolition); ADEQ Asbestos Form. See the required-documents checklist on this page for details on each.

Lake Havasu City requires 1 inspection(s) for a demolition permit, in order: Final. Schedule each through Lake Havasu City Development Services Department — Building Division (928-453-4148).

Apply through Lake Havasu City Development Services Department — Building Division at 2330 McCulloch Boulevard N, Lake Havasu City, AZ 86403. Phone: 928-453-4148, email: builderinfo@lhcaz.gov. Office hours: Building Official: Steve Blake (928-854-0716, blakesm@lhcaz.gov). Plans Examiners: Jerry Amann (928-854-0746, Amannj@lhcaz.gov) and Sylvia Butch. Combo Building Inspector/Plans Examiners: Chris Hayes, George Langley. Building Inspectors: Josh Boothe, Brian Drosselmeyer. Permit Technician Lead: Kristin Warren (buildingpermits@lhcaz.gov). Applications are submitted through the City's online MaintStar Customer Self Service portal (h2.maintstar.co/lakehavasu/Portal) or in person at the Development Services Department front counter, 2330 McCulloch Blvd N. Plan review does not begin until the City has verified the application submittal is complete; completeness review itself takes 7-10 business days before the formal plan-review clock starts. Source: City of Lake Havasu City Building Permits page (lhcaz.gov/229/Building-Permits and lhcaz.gov/development-permitting/building) and 2024 Code Letter to Contractors (Steven Blake, LHC Building Official, rev. 09-08-2025).. Official information: https://www.lhcaz.gov/229/Building-Permits.

Lake Havasu City, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). Lake Havasu City independently adopts and administers its own construction codes through its Development Services Department / Building Division; it does not defer permitting to Mohave County. Source: Lake Havasu City Building Permits page (lhcaz.gov/229/Building-Permits) and Lake Havasu City Code Chapter 12.08 (Building Codes), codelibrary.amlegal.com.; 2024 International Building Code (IBC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit A), effective February 1, 2026, replacing the prior 2018 edition. Source: Lake Havasu City Amendments to the 2024 Edition of the International Building Code (Exhibit A, Ordinance No. 25-1370).; 2024 International Residential Code (IRC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit B), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Residential Code (Exhibit B, Ordinance No. 25-1370).; 2024 International Mechanical Code (IMC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit C), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Mechanical Code (Exhibit C, Ordinance No. 25-1370).; 2024 International Plumbing Code (IPC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit E), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Plumbing Code (Exhibit E, Ordinance No. 25-1370).; 2024 International Fuel Gas Code (IFGC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments, effective February 1, 2026. Source: 2024 Code Letter to Contractors (rev. 09-08-2025), which lists the IFGC among the codes adopted with the 2024 suite; document list on lhcaz.gov/development-permitting/building includes 'Amendments To 2024 Intl Fuel Gas Code'.; 2024 International Property Maintenance Code (IPMC), adopted with the 2024 code suite effective February 1, 2026. Source: 2024 Code Letter to Contractors (rev. 09-08-2025); 'Amendments To 2024 Intl Property Maint Code' document on lhcaz.gov.; 2024 International Existing Building Code (IEBC), adopted with Lake Havasu City local amendments. Source: 'Amendments To 2024 Intl Existing Building Code' document, lhcaz.gov/development-permitting/building, and Lake Havasu City Code § 12.08.085 (International Existing Building Code), codelibrary.amlegal.com.; 2023 National Electrical Code (NEC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit F), effective February 1, 2026 (one edition behind the 2024 ICC suite, consistent with the NEC's own 3-year cycle). Source: Lake Havasu City Amendments to the 2023 Edition of the National Electrical Code (Exhibit F, Ordinance No. 25-1370).; 2024 International Fire Code (IFC), adopted by Ordinance No. 25-1371, amending City Code Chapter 12.12.010 (Adoption of International Fire Code); administered by the Lake Havasu City Fire Department / Fire Marshal's office. Source: Lake Havasu City Legistar record (File ID 25-4963/ordinance 25-1371) and Lake Havasu City Code Chapter 12.12 (International Fire Code), codelibrary.amlegal.com.; Transition/effective-date rule: the 2024 Codes and 2023 NEC took effect February 1, 2026 and apply to applications submitted on or after that date; they do NOT affect permits already submitted, in review, or under construction. Standard Plans previously approved under the 2018 Codes remain valid through August 1, 2026 (180 days from the new code effective date) and may be updated via an abbreviated cover-sheet process rather than a full plan resubmittal. Commercial/residential projects already in design under the 2018 Codes were allowed to submit under the 2018 Codes up to May 1, 2026 (90 days after the effective date). Source: Lake Havasu City 2024 Building Code Implementation Standards (rev. 09-23-2025).; Manufactured/mobile homes are addressed via a dedicated Mobile/Manufactured Home Building Permit Application, separate from the standard residential building permit track. Source: Lake Havasu City 'Mobile - Manufactured Home Building Permit Application' (lhcaz.gov/DocumentCenter/View/1153).; Building permit and plan-review fees are NOT set as flat dollar amounts within the adopted ICC codes themselves — the Master Fee Schedule (Development and Right-of-Way Services, Service Nos. S-033/S-034) states plan-check and permit fees for new buildings, additions, pools, and retaining walls are valuation-based, per 'Fee Schedule in Uniform Building Code' (i.e., the standard published ICC/Building Standards construction-cost valuation table), with a plan-check deposit/retainer of 5% of value collected up front and applied toward the actual cost. Separate itemized flat plan-review retainer fees by structure type are published in the Building Permit Retainers/Fees handout. Source: City of Lake Havasu City Master Fee Schedule (effective 02-01-2026, Rev. 12/10/2025) and Building Permit Retainers/Fees handout (Development Services Department, rev. 01/03/22).. Local amendments apply — see the Lake Havasu City overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lake Havasu City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.