Commercial Building Permit (New Construction / Multi-Family) in Lake Havasu City, Arizona

Required for new commercial structures and new multi-family residential projects in Lake Havasu City. Reviewed under the City's unified 'New Commercial Structures, Tenant Improvements, and Multi-Family Projects' development-review process, using the current commercial code suite (2024 IBC/IMC/IPC/IFGC/IFC, 2023 NEC, ANSI A117.1-2017, 2010 ADA) as adopted and locally amended. See the separate Commercial Tenant Improvement (TI) Permit entry in this file for the City's distinct, faster TI review track.

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for new commercial structures and new multi-family residential projects within Lake Havasu City limits, processed through the City's Development Review / Permit Process for 'New Commercial Structures, Tenant Improvements, and Multi-Family Projects'
  • Step 1 - Pre-Application Meeting: applicant submits a Pre-Application - Commercial & Multi-Family form plus a conceptual site plan; City staff schedule a meeting where the project owner, architect, and contractor meet with the Development Review Committee (one representative each from Planning, Building, Engineering, Fire Prevention, and Stormwater Management) to discuss design review requirements, Building Division requirements, off-site improvements, utility connections, and Fire Department requirements; staff issue the discipline-specific submittal checklists at this meeting
  • Step 2 - Completeness Verification: plan review does not begin until City staff verify the submittal package is complete against the checklists issued at the pre-application meeting; incomplete packages are returned to the applicant; once complete, the applicant pays the planning and building review fees and plan review begins
  • Step 3 - Plan Review: construction plans are reviewed concurrently by Planning, Building, Engineering, Fire Prevention, and Stormwater Management for code compliance; all review comments are provided to the applicant together with the redlined plans
  • Step 4 - Corrections: the applicant is responsible for responding to all comments and required corrections; the review process may repeat as many times as necessary for the applicant to address code requirements
  • Step 5 - Permit Issuance: requires payment of all permit and plan-check fees, any off-site improvement guarantees, and Mohave County Health Department approval when required (food establishments; public/semi-public pools or spas, including those in an apartment/condominium/townhouse/motel/hotel and any residential housing unit with 4 or more units; pet shops/kennels/grooming establishments except veterinary clinics; public accommodations such as hotels/motels/inns; RV parks, mobile home parks, campgrounds; and school buildings). No permit is issued until the general contractor's City business license number and State contractor's license number are on file, and, for projects with an estimated value over $50,000, an Arizona Department of Revenue bond exemption certificate has been provided Contractor
  • Registrant requirement: every plan sheet must be stamped by an Arizona registrant, except projects exempt under A.R.S. § 32-144
  • Current commercial code suite: 2024 IBC, 2024 IMC, 2023 NEC, 2024 IPC, 2024 IFGC, 2024 IFC, ANSI A117.1-2017, and the 2010 ADA Standards, plus Lake Havasu City local amendments; automatic fire sprinklers are required on ALL multi-family and commercial occupancies -- a stricter rule than the City's residential track, where the base IRC automatic-sprinkler section (R309) is deleted by City amendment
  • Design parameters per the Building Division's Plan Acceptance Criteria: wind design by IBC Table 1604.5 Risk Category -- 93 mph (Risk Category I), 99 mph (Risk Category II), 106 mph (Risk Category III), 110 mph (Risk Category IV); wind exposure B or C as determined by the project engineer; design rainfall 1.5 inches/hour; seismic zone calculated by the project engineer (no single fixed seismic design category is pre-published for commercial, unlike the City's residential Seismic Design Category D)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 7 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity of Lake Havasu City Master Fee Schedule (effective 02-01-2026), Service No. S-034, Building Permitting and Inspection Process -- the same valuation-based mechanism documented elsewhere in this file for new buildings, additions, and pools applies to commercial/multi-family new construction
Valuation-based per the fee schedule referenced in the Uniform Building Code (standard ICC/Building Standards construction-cost valuation table); no separate City-specific flat dollar table is published
Building Plan Check/Retainer Fee (deposit)City of Lake Havasu City Master Fee Schedule, Service No. S-033, Building Plan Check/Retainer Fees
Deposit of 5% of valuation, applied toward the actual plan-check cost

Review timeline

Plan reviewLake Havasu City’s published plan-review target
35–35 business days

How long did your Commercial Building Permit (New Construction / Multi-Family) permit actually take in Lake Havasu City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour; verifies soils report or 1,500 psf design compliance and foundation plan

  2. 2

    Underground/Rough Utilities

    Underground plumbing, electrical, and fire-line work verified against approved civil, plumbing, and electrical plans before cover

  3. 3

    Framing/Structural

    Structural framing and connections verified against sealed structural calculations and structural details sheet

  4. 4

    Fire Sprinkler / Fire Alarm Rough-In and Final

    Hydraulic test of the fire sprinkler system and fire alarm device verification against NICET-stamped (or Fire Protection Engineer-sealed) plans -- required on all commercial and multi-family occupancies

  5. 5

    Final / Certificate of Occupancy

    All disciplines (Building, Planning, Engineering, Fire, Stormwater) sign off; ADA accessible route and means of egress verified; occupancy or use of the structure is not allowed until a Certificate of Occupancy is issued

See the full Lake Havasu City inspection guide — scheduling & re-inspection fees →

Tips

  • The same 'New Commercial Structures, Tenant Improvements, and Multi-Family Projects' packet and the same five discipline checklists (Building, Planning, Engineering, Fire, Stormwater) cover new construction, tenant improvements, and multi-family projects alike -- each checklist has a checkbox for which track applies. See the paired Commercial Tenant Improvement (TI) Permit entry in this file for the City's distinct, faster TI review timeline and its lighter Stormwater path for TI projects with no land disturbance.
  • Automatic fire sprinklers are required on ALL multi-family and commercial occupancies per the City's current Building/Fire Plan Acceptance Criteria -- a stricter rule than the residential track, where the base IRC sprinkler mandate (R309/R313) is deleted by City amendment.
  • No permit is issued until the general contractor's City business license number and State contractor's license number are on file, and, for projects estimated over $50,000, an Arizona Department of Revenue bond exemption certificate is provided. Contractor
  • GAP NOT FULLY RESOLVED: beyond the general valuation-based Building Permit Fee (Service No. S-034) and the 5%-of-valuation Plan Check/Retainer deposit (Service No. S-033) already established for this jurisdiction, no additional commercial-specific flat-dollar fee table could be independently confirmed in this research pass (2026-08-01) -- the live lhcaz.gov Master Fee Schedule PDF URL returned HTTP 404 and Wayback Machine access was blocked in this research session. Search-engine snippets referenced a possible Planning Division 'Design Review' fee split between new construction and tenant improvements, but two separate lookups returned internally contradictory dollar figures (which value applied to which track), so that fee is omitted here rather than reported as fact.

Frequently asked questions

Lake Havasu City requires a commercial building permit (new construction / multi-family) for: Building permit required for new commercial structures and new multi-family residential projects within Lake Havasu City limits, processed through the City's Development Review / Permit Process for 'New Commercial Structures, Tenant Improvements, and Multi-Family Projects'; Step 1 - Pre-Application Meeting: applicant submits a Pre-Application - Commercial & Multi-Family form plus a conceptual site plan; City staff schedule a meeting where the project owner, architect, and contractor meet with the Development Review Committee (one representative each from Planning, Building, Engineering, Fire Prevention, and Stormwater Management) to discuss design review requirements, Building Division requirements, off-site improvements, utility connections, and Fire Department requirements; staff issue the discipline-specific submittal checklists at this meeting; Step 2 - Completeness Verification: plan review does not begin until City staff verify the submittal package is complete against the checklists issued at the pre-application meeting; incomplete packages are returned to the applicant; once complete, the applicant pays the planning and building review fees and plan review begins; Step 3 - Plan Review: construction plans are reviewed concurrently by Planning, Building, Engineering, Fire Prevention, and Stormwater Management for code compliance; all review comments are provided to the applicant together with the redlined plans; Step 4 - Corrections: the applicant is responsible for responding to all comments and required corrections; the review process may repeat as many times as necessary for the applicant to address code requirements; Step 5 - Permit Issuance: requires payment of all permit and plan-check fees, any off-site improvement guarantees, and Mohave County Health Department approval when required (food establishments; public/semi-public pools or spas, including those in an apartment/condominium/townhouse/motel/hotel and any residential housing unit with 4 or more units; pet shops/kennels/grooming establishments except veterinary clinics; public accommodations such as hotels/motels/inns; RV parks, mobile home parks, campgrounds; and school buildings). No permit is issued until the general contractor's City business license number and State contractor's license number are on file, and, for projects with an estimated value over $50,000, an Arizona Department of Revenue bond exemption certificate has been provided; Registrant requirement: every plan sheet must be stamped by an Arizona registrant, except projects exempt under A.R.S. § 32-144; Current commercial code suite: 2024 IBC, 2024 IMC, 2023 NEC, 2024 IPC, 2024 IFGC, 2024 IFC, ANSI A117.1-2017, and the 2010 ADA Standards, plus Lake Havasu City local amendments; automatic fire sprinklers are required on ALL multi-family and commercial occupancies -- a stricter rule than the City's residential track, where the base IRC automatic-sprinkler section (R309) is deleted by City amendment; Design parameters per the Building Division's Plan Acceptance Criteria: wind design by IBC Table 1604.5 Risk Category -- 93 mph (Risk Category I), 99 mph (Risk Category II), 106 mph (Risk Category III), 110 mph (Risk Category IV); wind exposure B or C as determined by the project engineer; design rainfall 1.5 inches/hour; seismic zone calculated by the project engineer (no single fixed seismic design category is pre-published for commercial, unlike the City's residential Seismic Design Category D). If your project isn't listed, confirm with Lake Havasu City Development Services Department — Building Division at 928-453-4148 before starting work.

In Lake Havasu City, the published Building Permit Fee — Based on Valuation is: Valuation-based per the fee schedule referenced in the Uniform Building Code (standard ICC/Building Standards construction-cost valuation table); no separate City-specific flat dollar table is published. Additional published fees: Building Plan Check/Retainer Fee (deposit) — Deposit of 5% of valuation, applied toward the actual plan-check cost. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lake Havasu City's published plan-review target for a commercial building permit (new construction / multi-family) is 35–35 business days.

You'll need: Pre-Application - Commercial & Multi-Family; Permit and Zoning Clearance Application; Plan Acceptance Criteria - Building (New Construction); Plan Acceptance Criteria - Planning (New Construction); Plan Acceptance Criteria - Engineering (New Construction); Plan Acceptance Criteria - Fire (New Construction); Plan Acceptance Criteria - Stormwater (New Development). Depending on your project, Lake Havasu City may also ask for: Mohave County Health Department Notification Form; Arizona Department of Revenue Bond Exemption Certificate. See the required-documents checklist on this page for details on each.

Lake Havasu City requires 5 inspection(s) for a commercial building permit (new construction / multi-family), in order: Foundation/Footing, Underground/Rough Utilities, Framing/Structural, Fire Sprinkler / Fire Alarm Rough-In and Final, Final / Certificate of Occupancy. Schedule each through Lake Havasu City Development Services Department — Building Division (928-453-4148).

Apply through Lake Havasu City Development Services Department — Building Division at 2330 McCulloch Boulevard N, Lake Havasu City, AZ 86403. Phone: 928-453-4148, email: builderinfo@lhcaz.gov. Office hours: Building Official: Steve Blake (928-854-0716, blakesm@lhcaz.gov). Plans Examiners: Jerry Amann (928-854-0746, Amannj@lhcaz.gov) and Sylvia Butch. Combo Building Inspector/Plans Examiners: Chris Hayes, George Langley. Building Inspectors: Josh Boothe, Brian Drosselmeyer. Permit Technician Lead: Kristin Warren (buildingpermits@lhcaz.gov). Applications are submitted through the City's online MaintStar Customer Self Service portal (h2.maintstar.co/lakehavasu/Portal) or in person at the Development Services Department front counter, 2330 McCulloch Blvd N. Plan review does not begin until the City has verified the application submittal is complete; completeness review itself takes 7-10 business days before the formal plan-review clock starts. Source: City of Lake Havasu City Building Permits page (lhcaz.gov/229/Building-Permits and lhcaz.gov/development-permitting/building) and 2024 Code Letter to Contractors (Steven Blake, LHC Building Official, rev. 09-08-2025).. Official information: https://www.lhcaz.gov/229/Building-Permits.

Yes. The City's current Building and Fire Plan Acceptance Criteria state that automatic fire sprinklers are required on all multi-family and commercial occupancies -- unlike the residential track, where the base IRC sprinkler mandate is deleted by City amendment.

A Pre-Application - Commercial & Multi-Family meeting: submit the pre-application form and a conceptual site plan, and City staff will schedule a meeting with the Development Review Committee (Planning, Building, Engineering, Fire, and Stormwater) to walk through submittal requirements before you prepare full construction documents.

Sources & verification

Verified against official sources. Last reviewed 2026-08-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lake Havasu City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter