Residential Solar Photovoltaic (PV) Permit in Lake Havasu City, Arizona

Required for installation of rooftop residential solar photovoltaic systems in Lake Havasu City. Governed by the City's dedicated PV Utility-Interactive Systems Plan Submittal Checklist (rev. 05-04-2022) and the 2023 NEC as adopted and amended (Exhibit F, Ordinance No. 25-1370).

Verified 2026-07-06 · Source

When you need this permit

  • Photovoltaic disconnecting means must be installed at a readily accessible location outside the building or structure, nearest the point of entrance of the system conductors (NEC 690.13(A)(1) amendment)
  • Roof plan showing panel locations and existing roof height required (most zoning classifications cap roof-mounted additions at 15 ft max height)
  • Structural calculations and drawings sealed by an Arizona-licensed engineer required, showing connection of pre-manufactured module frames to the existing roof structure
  • Manufacturer specifications required for modules (short-circuit current Isc, open-circuit voltage Voc, maximum power Pmax) and inverter (maximum AC power output, disconnect info, ground-fault protection device)
  • Complete wiring diagram required: number of modules/strings, conductor/conduit sizing at each stage (string to combiner, combiner to inverter, inverter to back-feed breaker), DC system grounding per NEC 250.166 and 690.47(c), and location of main service/inverter/PV output meter
  • A Unisource Electric Letter of Approval is required at time of permit submittal
  • Electrical load calculations for the dwelling are required when de-rating the main service panel

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Photovoltaic System Permit — Based on Valuation / Fee ScheduleNo dedicated, separately itemized flat PV permit fee (distinct from the general building valuation structure) was found published on lhcaz.gov; PV permits are billed via the same Development Services fee structure referenced in Service No. S-034.
Valuation-based, consistent with the City's Uniform Building Code fee-schedule reference (Master Fee Schedule, Service Nos. S-033/S-034)

Review timeline

Plan reviewLake Havasu City’s published plan-review target
10–10 business days

How long did your Residential Solar Photovoltaic (PV) Permit permit actually take in Lake Havasu City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, grounding, and exterior disconnect location verified

See the full Lake Havasu City inspection guide — scheduling & re-inspection fees →

Tips

  • The PV disconnecting means must be OUTSIDE the building nearest the point of conductor entrance, per the City's NEC 690.13(A)(1) amendment — an interior-only disconnect location does not comply.
  • A Unisource Electric Letter of Approval is a hard submittal requirement in Lake Havasu City — this is specific to the local utility interconnection process, not a generic NEC requirement.
  • Most PV work is classified under the City's 'Miscellaneous' plan-review category at 10 business days per the published timeframes, consistent with Arizona's A.R.S. § 9-835 municipal time-frames requirement, though systems requiring main-panel de-rating or more complex structural review may take longer at the Building Official's discretion.

Frequently asked questions

The City's PV Utility-Interactive Systems Plan Submittal Checklist requires a Unisource Electric Letter of Approval to be submitted at the time of permit application, in addition to the standard structural, module/inverter, and wiring-diagram documentation.

In Lake Havasu City, the published Photovoltaic System Permit — Based on Valuation / Fee Schedule is: Valuation-based, consistent with the City's Uniform Building Code fee-schedule reference (Master Fee Schedule, Service Nos. S-033/S-034). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lake Havasu City's published plan-review target for a residential solar photovoltaic (pv) permit is 10–10 business days.

You'll need: PV Utility-Interactive Systems Plan Submittal Checklist (rev. 05-04-2022); PV System (Solar) Plan Submittal Requirements; Unisource Electric Letter of Approval. See the required-documents checklist on this page for details on each.

Lake Havasu City requires 2 inspection(s) for a residential solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through Lake Havasu City Development Services Department — Building Division (928-453-4148).

Apply through Lake Havasu City Development Services Department — Building Division at 2330 McCulloch Boulevard N, Lake Havasu City, AZ 86403. Phone: 928-453-4148, email: builderinfo@lhcaz.gov. Office hours: Building Official: Steve Blake (928-854-0716, blakesm@lhcaz.gov). Plans Examiners: Jerry Amann (928-854-0746, Amannj@lhcaz.gov) and Sylvia Butch. Combo Building Inspector/Plans Examiners: Chris Hayes, George Langley. Building Inspectors: Josh Boothe, Brian Drosselmeyer. Permit Technician Lead: Kristin Warren (buildingpermits@lhcaz.gov). Applications are submitted through the City's online MaintStar Customer Self Service portal (h2.maintstar.co/lakehavasu/Portal) or in person at the Development Services Department front counter, 2330 McCulloch Blvd N. Plan review does not begin until the City has verified the application submittal is complete; completeness review itself takes 7-10 business days before the formal plan-review clock starts. Source: City of Lake Havasu City Building Permits page (lhcaz.gov/229/Building-Permits and lhcaz.gov/development-permitting/building) and 2024 Code Letter to Contractors (Steven Blake, LHC Building Official, rev. 09-08-2025).. Official information: https://www.lhcaz.gov/229/Building-Permits.

Lake Havasu City, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). Lake Havasu City independently adopts and administers its own construction codes through its Development Services Department / Building Division; it does not defer permitting to Mohave County. Source: Lake Havasu City Building Permits page (lhcaz.gov/229/Building-Permits) and Lake Havasu City Code Chapter 12.08 (Building Codes), codelibrary.amlegal.com.; 2024 International Building Code (IBC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit A), effective February 1, 2026, replacing the prior 2018 edition. Source: Lake Havasu City Amendments to the 2024 Edition of the International Building Code (Exhibit A, Ordinance No. 25-1370).; 2024 International Residential Code (IRC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit B), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Residential Code (Exhibit B, Ordinance No. 25-1370).; 2024 International Mechanical Code (IMC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit C), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Mechanical Code (Exhibit C, Ordinance No. 25-1370).; 2024 International Plumbing Code (IPC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit E), effective February 1, 2026. Source: Lake Havasu City Amendments to the 2024 Edition of the International Plumbing Code (Exhibit E, Ordinance No. 25-1370).; 2024 International Fuel Gas Code (IFGC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments, effective February 1, 2026. Source: 2024 Code Letter to Contractors (rev. 09-08-2025), which lists the IFGC among the codes adopted with the 2024 suite; document list on lhcaz.gov/development-permitting/building includes 'Amendments To 2024 Intl Fuel Gas Code'.; 2024 International Property Maintenance Code (IPMC), adopted with the 2024 code suite effective February 1, 2026. Source: 2024 Code Letter to Contractors (rev. 09-08-2025); 'Amendments To 2024 Intl Property Maint Code' document on lhcaz.gov.; 2024 International Existing Building Code (IEBC), adopted with Lake Havasu City local amendments. Source: 'Amendments To 2024 Intl Existing Building Code' document, lhcaz.gov/development-permitting/building, and Lake Havasu City Code § 12.08.085 (International Existing Building Code), codelibrary.amlegal.com.; 2023 National Electrical Code (NEC), adopted by Ordinance No. 25-1370 with Lake Havasu City local amendments (Exhibit F), effective February 1, 2026 (one edition behind the 2024 ICC suite, consistent with the NEC's own 3-year cycle). Source: Lake Havasu City Amendments to the 2023 Edition of the National Electrical Code (Exhibit F, Ordinance No. 25-1370).; 2024 International Fire Code (IFC), adopted by Ordinance No. 25-1371, amending City Code Chapter 12.12.010 (Adoption of International Fire Code); administered by the Lake Havasu City Fire Department / Fire Marshal's office. Source: Lake Havasu City Legistar record (File ID 25-4963/ordinance 25-1371) and Lake Havasu City Code Chapter 12.12 (International Fire Code), codelibrary.amlegal.com.; Transition/effective-date rule: the 2024 Codes and 2023 NEC took effect February 1, 2026 and apply to applications submitted on or after that date; they do NOT affect permits already submitted, in review, or under construction. Standard Plans previously approved under the 2018 Codes remain valid through August 1, 2026 (180 days from the new code effective date) and may be updated via an abbreviated cover-sheet process rather than a full plan resubmittal. Commercial/residential projects already in design under the 2018 Codes were allowed to submit under the 2018 Codes up to May 1, 2026 (90 days after the effective date). Source: Lake Havasu City 2024 Building Code Implementation Standards (rev. 09-23-2025).; Manufactured/mobile homes are addressed via a dedicated Mobile/Manufactured Home Building Permit Application, separate from the standard residential building permit track. Source: Lake Havasu City 'Mobile - Manufactured Home Building Permit Application' (lhcaz.gov/DocumentCenter/View/1153).; Building permit and plan-review fees are NOT set as flat dollar amounts within the adopted ICC codes themselves — the Master Fee Schedule (Development and Right-of-Way Services, Service Nos. S-033/S-034) states plan-check and permit fees for new buildings, additions, pools, and retaining walls are valuation-based, per 'Fee Schedule in Uniform Building Code' (i.e., the standard published ICC/Building Standards construction-cost valuation table), with a plan-check deposit/retainer of 5% of value collected up front and applied toward the actual cost. Separate itemized flat plan-review retainer fees by structure type are published in the Building Permit Retainers/Fees handout. Source: City of Lake Havasu City Master Fee Schedule (effective 02-01-2026, Rev. 12/10/2025) and Building Permit Retainers/Fees handout (Development Services Department, rev. 01/03/22).. Local amendments apply — see the Lake Havasu City overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lake Havasu City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.