Fence and Wall Permit in Coolidge, Arizona

Required for fences and walls in Coolidge, with the application distinguishing pool barrier fencing from general fencing and subdivision perimeter fencing.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit application required for fences and walls; the application form specifically flags whether the fence is a Pool Barrier Fence and whether it is Subdivision Perimeter Fencing
  • Pool barrier fencing must comply with the City's adopted 2018 International Swimming Pool and Spa Code barrier provisions
  • Licensed Arizona contractor required per A.R.S. § 32-1122, unless filing an Owner/Builder Declaration Owner-builder

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationCity of Coolidge Building Permit Fee Schedule, Article 3; no dedicated flat fence/wall fee line was found in the published Fee Schedule — fences and walls are billed under the general valuation-based table according to construction value
Per the general Article 3 valuation-based schedule

Review timeline

Plan review
Not published — contact the department

How long did your Fence and Wall Permit permit actually take in Coolidge?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing

    Required for block/masonry walls before backfill

  2. 2

    Final

    Completed fence/wall verified against approved plans, including pool barrier compliance where applicable

See the full Coolidge inspection guide — scheduling & re-inspection fees →

Tips

  • As of July 2026, the City of Coolidge does not appear to publish a permit-specific plan review turnaround time for fence/wall permits on its public website or fee schedule, nor a dedicated flat fee (fences/walls are billed under the general Article 3 valuation table). There is no verifiable online source for either figure — call the Development Services Department at 520-723-6075.
  • The Fence/Wall Permit Application form itself distinguishes ordinary fencing from pool barrier fencing and subdivision perimeter fencing, indicating these are reviewed against different standards even though a single application form is used.

Frequently asked questions

Yes. The City of Coolidge Fence/Wall Permit Application specifically asks whether the fence is a Pool Barrier Fence, and such fencing must comply with the City's adopted 2018 International Swimming Pool and Spa Code barrier requirements.

In Coolidge, the published Building Permit Fee — Based on Valuation is: Per the general Article 3 valuation-based schedule. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Coolidge does not publish a plan-review timeline for this permit. Contact City of Coolidge Development Services Department — Building Safety Division at 520-723-6075 for current turnaround.

You'll need: Fence/Wall Permit Application. See the required-documents checklist on this page for details on each.

Coolidge requires 2 inspection(s) for a fence and wall permit, in order: Footing, Final. Schedule each through City of Coolidge Development Services Department — Building Safety Division (520-723-6075).

Apply through City of Coolidge Development Services Department — Building Safety Division at 131 W. Pinkley Avenue, Coolidge, AZ 85128. Phone: 520-723-6075, email: inspection@coolidgeaz.com. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Inspection requests are handled via a separate Inspection Line (520-723-6049); inspections take place the next business day if the Inspection Request Form is received by 3:30 p.m. the prior business day (no inspections on holidays/weekends). Building Official: Bill Jones (wjones@coolidgeaz.com). FAX 520-723-6079, TDD 520-723-4653.. Official information: https://www.coolidgeaz.com/development-services.

Coolidge, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities, A.R.S. § 9-802 for adoption of public records by ordinance reference). The City of Coolidge independently adopts and administers its own construction codes through its Development Services Department / Building Safety Division. Source: City of Coolidge Ordinance No. 23-13 (passed December 11, 2023, effective July 1, 2024), 'Adopting that certain document filed with the City Clerk and entitled 2023 Amendments to Title XV of the Coolidge City Code,' amending Coolidge City Code §§150.022, 150.023, 150.025.; 2018 International Building Code (IBC), as published by the International Code Council, adopted by reference as Code No. 1 (Coolidge City Code §150.022(A)), including Appendix C (Group U — Agricultural Buildings), Appendix F (Rodent Proofing), Appendix G (Flood-Resistant Construction), Appendix I (Patio Covers), and Appendix J (Grading), with City of Coolidge amendments (Exhibit A). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(A) and Exhibit A.; 2018 International Residential Code (IRC), as published by the International Code Council, adopted by reference as Code No. 2 (§150.022(B)), including Appendix A (Sizing/Capacities of Gas Piping), Appendix B (Sizing of Venting Systems), Appendix C (Exit Terminals of Mechanical Draft and Direct-Vent Venting Systems), Appendix H (Patio Covers), Appendix J (Existing Buildings and Structures), and Appendix Q (Tiny Houses), with City of Coolidge amendments (Exhibit B) — the IRC's own Chapter 1 Administration (Sections R101–R114) is deleted in favor of using the IBC's administrative provisions. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(B) and Exhibit B.; 2018 International Fuel Gas Code (IFGC), adopted by reference as Code No. 3 (§150.022(C)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(C).; 2018 International Mechanical Code (IMC), adopted by reference as Code No. 4 (§150.022(D)), with City of Coolidge amendments (Exhibit C) — IMC Chapter 1 Administration (Sections 101–109) deleted in favor of the IBC's administrative provisions. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(D) and Exhibit C.; 2018 International Plumbing Code (IPC), adopted by reference as Code No. 5 (§150.022(E)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(E).; 2018 International Fire Code (IFC), adopted by reference as Code No. 6 (§150.022(F)) as the City's uniform fire code, including Appendices A through O, with City of Coolidge amendments (Exhibit F). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(F) and Exhibit F.; 2018 International Property Maintenance Code (IPMC), adopted by reference as Code No. 7 (§150.022(G)), with City of Coolidge amendments (Exhibit D). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(G) and Exhibit D.; 2018 International Existing Building Code (IEBC), adopted by reference as Code No. 8 (§150.022(H)), with City of Coolidge amendments (Exhibit E). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(H) and Exhibit E.; 2018 International Energy Conservation Code (IECC), adopted by reference as Code No. 9 (§150.022(I)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(I).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference as Code No. 11 (§150.022(J)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(J).; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference as Code No. 12 (§150.022(K)), with City of Coolidge amendments (Exhibit G) — note the electrical code cycle is one edition behind the 2018 ICC set. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(K) and Exhibit G; confirmed independently on the City of Coolidge Building Code Information page (coolidgeaz.com) and the City's Commercial Plan Submittal handout.; 1997 Uniform Administrative Abatement of Dangerous Building Code (UABDBC), as published by the International Conference of Building Officials, adopted by reference as Code No. 13 (§150.022(L)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(L).; ICC/ANSI A117.1-2009 Accessibility and Usable Buildings and Facilities standard, adopted by reference (§150.022(M)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(M).; Fee authority: Coolidge City Code §109 (Building Code Administration, as amended by Ordinance No. 23-13) delegates all permit fees, plan review fees, and related charges to be 'as established by Council' — the operative fee amounts are set out in the City of Coolidge Building Permit Fee Schedule (approved and adopted by the Coolidge City Council January 12, 2009, effective February 12, 2009), which remains the fee schedule currently published on the City's website. Fee tables are derived from the May 2003 issue of the Building Safety Journal (International Code Council), adjusted by regional modifiers for Pinal County construction costs, per Coolidge City Code §201/Article 2 of the Fee Schedule. Source: City of Coolidge Building Permit Fee Schedule (adopted 2009); City of Coolidge Ordinance No. 23-13, Exhibit 1, §109.; Manufactured/factory-built homes are regulated by the State of Arizona Office of Manufactured Housing (A.R.S. § 41-4001 et seq.) for construction/installation standards; the City of Coolidge separately charges a Factory Built Building Installation fee ($150 residential, plus $40 per additional unit) and a Park Model Installation fee ($150, plus $50 for accessory structures) for local site placement. Source: City of Coolidge Building Permit Fee Schedule, Article 9.. Local amendments apply — see the Coolidge overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coolidge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.