Electric Vehicle Charging Station Permit — Coolidge, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://www.coolidgeaz.com/vertical/Sites/%7BAE188E70-DD7F-47BE-99EF-B58B70641DF9%7D/uploads/Building_Permit_Fee_Schedule.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electric Vehicle Charging Station Permit in Coolidge, Arizona
The City of Coolidge does not publish a dedicated EV charger/EVSE permit application, fee line, or webpage -- checked the Development Services page, Building Code Information page, Forms & Applications page, Ordinance No. 23-13 (2023 code-adoption ordinance, including Exhibit G's 2017 NEC amendments), and the Building Permit Fee Schedule directly; none name electric vehicle charging stations, EV chargers, or EVSE. An EV charger installation (a dedicated 240V circuit/outlet, most commonly a NEMA 14-50 receptacle, or a hardwired Level 2 unit) is electrical work and is processed as a standard Electrical Permit under the City's Article 4 fee schedule and the 2017 NEC as adopted by Ordinance No. 23-13, Exhibit G -- the same permit type and fee mechanism documented in this file's electrical-permit entry.
Verified 2026-07-20 · Source
When you need this permit
- No EV-charger-specific permit application exists; use the standard City of Coolidge Electrical Permit Application (Rev. 08/13/2020)
- Governed by the 2017 NEC as adopted and amended by the City of Coolidge, including NEC Article 625 (Electric Vehicle Power Transfer System) as part of the unamended NEC text -- no City-specific amendment to Article 625 was found
- A dedicated circuit/outlet installation (e.g., NEMA 14-50) is billed under the Article 4 Unit Fee Schedule's receptacle/outlet or service-upgrade line items depending on scope; a hardwired Level 2 charger is billed similarly as new equipment/circuit wiring
- Licensed Arizona contractor required per A.R.S. § 32-1122, unless filing an Owner/Builder Declaration under A.R.S. § 32-1121 Owner-builder
- Rough-in inspection required for new circuit wiring before concealment; final inspection required before energizing
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
New circuit wiring/conduit inspected before concealment
- 2
Final
Charger outlet or hardwired unit installed and connected, inspected before energizing
See the full Coolidge inspection guide — scheduling & re-inspection fees →
Tips
- There is no separate 'EV charger permit' in Coolidge -- a home or business charger installation is processed as an ordinary Electrical Permit under the same Article 4 fee schedule used for any new circuit or outlet.
- A simple dedicated 240V outlet (e.g., NEMA 14-50) is billed at the flat $22 electrical permit issuance fee plus the small per-outlet unit fee ($1.00); a project also requiring a panel or service upgrade should budget for the higher Service Unit Fee tiers ($27.25-$111.00) as well.
- NEC Article 625 (Electric Vehicle Power Transfer System) governs the installation under the City's adopted 2017 NEC; no Coolidge-specific amendment to Article 625 was found.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coolidge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Coolidge
Electric Vehicle Charging Station Permit in other cities
Compare electric vehicle charging station permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Coolidge project checklist
Describe your project once and get every permit, document, and fee it triggers in Coolidge — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →