Electric Vehicle Charging Station Permit in Coolidge, Arizona

The City of Coolidge does not publish a dedicated EV charger/EVSE permit application, fee line, or webpage -- checked the Development Services page, Building Code Information page, Forms & Applications page, Ordinance No. 23-13 (2023 code-adoption ordinance, including Exhibit G's 2017 NEC amendments), and the Building Permit Fee Schedule directly; none name electric vehicle charging stations, EV chargers, or EVSE. An EV charger installation (a dedicated 240V circuit/outlet, most commonly a NEMA 14-50 receptacle, or a hardwired Level 2 unit) is electrical work and is processed as a standard Electrical Permit under the City's Article 4 fee schedule and the 2017 NEC as adopted by Ordinance No. 23-13, Exhibit G -- the same permit type and fee mechanism documented in this file's electrical-permit entry.

Verified 2026-07-20 · Source

When you need this permit

  • No EV-charger-specific permit application exists; use the standard City of Coolidge Electrical Permit Application (Rev. 08/13/2020)
  • Governed by the 2017 NEC as adopted and amended by the City of Coolidge, including NEC Article 625 (Electric Vehicle Power Transfer System) as part of the unamended NEC text -- no City-specific amendment to Article 625 was found
  • A dedicated circuit/outlet installation (e.g., NEMA 14-50) is billed under the Article 4 Unit Fee Schedule's receptacle/outlet or service-upgrade line items depending on scope; a hardwired Level 2 charger is billed similarly as new equipment/circuit wiring
  • Licensed Arizona contractor required per A.R.S. § 32-1122, unless filing an Owner/Builder Declaration under A.R.S. § 32-1121 Owner-builder
  • Rough-in inspection required for new circuit wiring before concealment; final inspection required before energizing

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit IssuanceCity of Coolidge Building Permit Fee Schedule, Article 4; the base issuance fee applicable to any electrical permit including an EV charger circuit
$22.00
Receptacle/Switch/Light Outlets, first 20 fixtures, eachCity of Coolidge Building Permit Fee Schedule, Article 4, Unit Fee Schedule item 1; applicable to a dedicated NEMA 14-50 or similar EV charger receptacle -- no distinct EV-specific line item is published
$1.00
Service, 600 volts or less, up to 200 amps (if a panel/service upgrade is needed to support charger load)City of Coolidge Building Permit Fee Schedule, Article 4, Unit Fee Schedule item 8
$27.25
Service, 600 volts or less, over 200 to 1,000 ampsCity of Coolidge Building Permit Fee Schedule, Article 4, Unit Fee Schedule item 8
$55.50

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle Charging Station Permit permit actually take in Coolidge?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    New circuit wiring/conduit inspected before concealment

  2. 2

    Final

    Charger outlet or hardwired unit installed and connected, inspected before energizing

See the full Coolidge inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'EV charger permit' in Coolidge -- a home or business charger installation is processed as an ordinary Electrical Permit under the same Article 4 fee schedule used for any new circuit or outlet.
  • A simple dedicated 240V outlet (e.g., NEMA 14-50) is billed at the flat $22 electrical permit issuance fee plus the small per-outlet unit fee ($1.00); a project also requiring a panel or service upgrade should budget for the higher Service Unit Fee tiers ($27.25-$111.00) as well.
  • NEC Article 625 (Electric Vehicle Power Transfer System) governs the installation under the City's adopted 2017 NEC; no Coolidge-specific amendment to Article 625 was found.

Frequently asked questions

Coolidge requires an electric vehicle charging station permit for: No EV-charger-specific permit application exists; use the standard City of Coolidge Electrical Permit Application (Rev. 08/13/2020); Governed by the 2017 NEC as adopted and amended by the City of Coolidge, including NEC Article 625 (Electric Vehicle Power Transfer System) as part of the unamended NEC text -- no City-specific amendment to Article 625 was found; A dedicated circuit/outlet installation (e.g., NEMA 14-50) is billed under the Article 4 Unit Fee Schedule's receptacle/outlet or service-upgrade line items depending on scope; a hardwired Level 2 charger is billed similarly as new equipment/circuit wiring; Licensed Arizona contractor required per A.R.S. § 32-1122, unless filing an Owner/Builder Declaration under A.R.S. § 32-1121; Rough-in inspection required for new circuit wiring before concealment; final inspection required before energizing. If your project isn't listed, confirm with City of Coolidge Development Services Department — Building Safety Division at 520-723-6075 before starting work.

The base Electrical Permit Issuance fee is $22.00, plus applicable Unit Fee Schedule line items -- typically $1.00 for the dedicated outlet/receptacle, or the higher Service fee tiers ($27.25 to $111.00) if a panel or service upgrade is also needed, per the City of Coolidge Building Permit Fee Schedule, Article 4.

Coolidge does not publish a plan-review timeline for this permit. Contact City of Coolidge Development Services Department — Building Safety Division at 520-723-6075 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Coolidge requires 2 inspection(s) for an electric vehicle charging station permit, in order: Rough-In, Final. Schedule each through City of Coolidge Development Services Department — Building Safety Division (520-723-6075).

Apply through City of Coolidge Development Services Department — Building Safety Division at 131 W. Pinkley Avenue, Coolidge, AZ 85128. Phone: 520-723-6075, email: inspection@coolidgeaz.com. Office hours: Monday - Friday, 8 a.m. - 5 p.m. Inspection requests are handled via a separate Inspection Line (520-723-6049); inspections take place the next business day if the Inspection Request Form is received by 3:30 p.m. the prior business day (no inspections on holidays/weekends). Building Official: Bill Jones (wjones@coolidgeaz.com). FAX 520-723-6079, TDD 520-723-4653.. Official information: https://www.coolidgeaz.com/development-services.

Coolidge, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities, A.R.S. § 9-802 for adoption of public records by ordinance reference). The City of Coolidge independently adopts and administers its own construction codes through its Development Services Department / Building Safety Division. Source: City of Coolidge Ordinance No. 23-13 (passed December 11, 2023, effective July 1, 2024), 'Adopting that certain document filed with the City Clerk and entitled 2023 Amendments to Title XV of the Coolidge City Code,' amending Coolidge City Code §§150.022, 150.023, 150.025.; 2018 International Building Code (IBC), as published by the International Code Council, adopted by reference as Code No. 1 (Coolidge City Code §150.022(A)), including Appendix C (Group U — Agricultural Buildings), Appendix F (Rodent Proofing), Appendix G (Flood-Resistant Construction), Appendix I (Patio Covers), and Appendix J (Grading), with City of Coolidge amendments (Exhibit A). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(A) and Exhibit A.; 2018 International Residential Code (IRC), as published by the International Code Council, adopted by reference as Code No. 2 (§150.022(B)), including Appendix A (Sizing/Capacities of Gas Piping), Appendix B (Sizing of Venting Systems), Appendix C (Exit Terminals of Mechanical Draft and Direct-Vent Venting Systems), Appendix H (Patio Covers), Appendix J (Existing Buildings and Structures), and Appendix Q (Tiny Houses), with City of Coolidge amendments (Exhibit B) — the IRC's own Chapter 1 Administration (Sections R101–R114) is deleted in favor of using the IBC's administrative provisions. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(B) and Exhibit B.; 2018 International Fuel Gas Code (IFGC), adopted by reference as Code No. 3 (§150.022(C)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(C).; 2018 International Mechanical Code (IMC), adopted by reference as Code No. 4 (§150.022(D)), with City of Coolidge amendments (Exhibit C) — IMC Chapter 1 Administration (Sections 101–109) deleted in favor of the IBC's administrative provisions. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(D) and Exhibit C.; 2018 International Plumbing Code (IPC), adopted by reference as Code No. 5 (§150.022(E)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(E).; 2018 International Fire Code (IFC), adopted by reference as Code No. 6 (§150.022(F)) as the City's uniform fire code, including Appendices A through O, with City of Coolidge amendments (Exhibit F). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(F) and Exhibit F.; 2018 International Property Maintenance Code (IPMC), adopted by reference as Code No. 7 (§150.022(G)), with City of Coolidge amendments (Exhibit D). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(G) and Exhibit D.; 2018 International Existing Building Code (IEBC), adopted by reference as Code No. 8 (§150.022(H)), with City of Coolidge amendments (Exhibit E). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(H) and Exhibit E.; 2018 International Energy Conservation Code (IECC), adopted by reference as Code No. 9 (§150.022(I)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(I).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted by reference as Code No. 11 (§150.022(J)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(J).; 2017 National Electrical Code (NEC), as published by the National Fire Protection Association (NFPA 70), adopted by reference as Code No. 12 (§150.022(K)), with City of Coolidge amendments (Exhibit G) — note the electrical code cycle is one edition behind the 2018 ICC set. Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(K) and Exhibit G; confirmed independently on the City of Coolidge Building Code Information page (coolidgeaz.com) and the City's Commercial Plan Submittal handout.; 1997 Uniform Administrative Abatement of Dangerous Building Code (UABDBC), as published by the International Conference of Building Officials, adopted by reference as Code No. 13 (§150.022(L)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(L).; ICC/ANSI A117.1-2009 Accessibility and Usable Buildings and Facilities standard, adopted by reference (§150.022(M)). Source: City of Coolidge Ordinance No. 23-13, Exhibit 1, §150.022(M).; Fee authority: Coolidge City Code §109 (Building Code Administration, as amended by Ordinance No. 23-13) delegates all permit fees, plan review fees, and related charges to be 'as established by Council' — the operative fee amounts are set out in the City of Coolidge Building Permit Fee Schedule (approved and adopted by the Coolidge City Council January 12, 2009, effective February 12, 2009), which remains the fee schedule currently published on the City's website. Fee tables are derived from the May 2003 issue of the Building Safety Journal (International Code Council), adjusted by regional modifiers for Pinal County construction costs, per Coolidge City Code §201/Article 2 of the Fee Schedule. Source: City of Coolidge Building Permit Fee Schedule (adopted 2009); City of Coolidge Ordinance No. 23-13, Exhibit 1, §109.; Manufactured/factory-built homes are regulated by the State of Arizona Office of Manufactured Housing (A.R.S. § 41-4001 et seq.) for construction/installation standards; the City of Coolidge separately charges a Factory Built Building Installation fee ($150 residential, plus $40 per additional unit) and a Park Model Installation fee ($150, plus $50 for accessory structures) for local site placement. Source: City of Coolidge Building Permit Fee Schedule, Article 9.. Local amendments apply — see the Coolidge overview page for the full list.

No. The City does not publish a dedicated EV charger/EVSE permit application or fee line. An EV charger installation is processed as a standard Electrical Permit under the City's Article 4 fee schedule and the adopted 2017 NEC, the same as any other electrical circuit or outlet installation.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coolidge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.