Residential Building Permit (New Construction) — Coolidge, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.coolidgeaz.com/development-services
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Coolidge, Arizona
Required for new single-family and two-family dwelling construction in the City of Coolidge. Reviewed against the 2018 IRC and City of Coolidge amendments (Ordinance No. 23-13, effective July 1, 2024). Applications are submitted at the Development Services Office at 131 W. Pinkley Avenue.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family and two-family dwelling construction within Coolidge city limits
- Plans must comply with the 2018 IRC and City of Coolidge amendments, including Climatic and Geographic Design Criteria (90 mph wind, Exposure C; Seismic Design Category B, masonry/concrete to Category C minimum; 32°F winter design temperature; moderate-to-heavy termite potential; 18-inch minimum foundation depth)
- Two (2) sets of construction documents required: floor plan, foundation plan/details, roof and floor/wall framing plans/details, exterior elevations, mechanical/plumbing/electrical plans, truss diagrams, structural engineering calculations, and soils report
- Site plan required showing north point, boundary dimensions, easements, ingress/egress, utility easements (electric, gas, telephone, water, sewer, cable), structures, fences/walls, exterior lighting, and gross square footage
- Landscape plan required per City Zoning Code, Article XII
- Licensed Arizona contractor required per A.R.S. § 32-1122, unless filing an Owner/Builder Declaration under A.R.S. § 32-1121 Owner-builder
- Automatic fire sprinklers are NOT required (IRC §R313 deleted per A.R.S. § 9-807 state preemption)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour; verifies 18-inch minimum foundation depth and 10-inch minimum spread footing thickness per City of Coolidge amendments
- 2
Framing
Structural framing, connections, and egress per 2018 IRC and City of Coolidge amendments (metal framing anchors, floor-to-floor strap ties, truss-to-top-plate connections)
- 3
Building Weather-Tight (Frame Inspection)
Building must be weather-tight at the time of the frame inspection per Coolidge amendment to §110.304
- 4
Final / Certificate of Occupancy
All work complete per approved plans; building address numbers (4-inch minimum, durable material) must be displayed prior to final inspection/CO issuance
See the full Coolidge inspection guide — scheduling & re-inspection fees →
Tips
- As of July 2026, the City of Coolidge does not appear to publish a permit-specific plan review turnaround time (in business days) for new residential building permits on its public website, in its Building Permit Fee Schedule, or in Ordinance No. 23-13 (the 2023 code-adoption ordinance). The City publishes permit requirements, submittal checklists, and fee schedules, but not a category-specific review-timeline document of the kind required for A.R.S. § 9-835 compliance. A phrase referencing 'up to 45 business days to complete first review' appears in the City's indexed forms page, but on inspection this text is boilerplate belonging to a linked third-party utility/interconnection submittal document, not a City of Coolidge-authored building-permit timeline — it was not used here as it cannot be verified as Coolidge's own review-time commitment. There is no verifiable Coolidge-specific online source for this figure — call the Development Services Department directly at 520-723-6075.
- All permits (except demolition) expire 24 months after issuance if final inspection has not been approved; separately, any permit expires after 180 days of inactivity (no work commenced, or work suspended/abandoned) or 180 days after the last approved inspection.
- Plan review fee (65% of the building permit fee) is due at the time of submittal, separate from and in addition to the building permit fee itself, which is due before permit issuance.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coolidge building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Coolidge
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Coolidge project checklist
Describe your project once and get every permit, document, and fee it triggers in Coolidge — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →