Fire Alarm System Permit (via Central Arizona Fire and Medical Authority) — Dewey-Humboldt, Arizona · Requirements sheet
Verified 2026-07-23 · Source: https://www.cazfire.gov/273/Fire-Code-and-Fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Alarm System Permit (via Central Arizona Fire and Medical Authority) in Dewey-Humboldt, Arizona
As with fire sprinkler systems, Dewey-Humboldt has no fire-alarm permitting function of its own and defers entirely to Central Arizona Fire and Medical Authority (CAFMA). CAFMA's Fee Schedule and Construction Guidelines treat 'Fire Alarm' as its own distinct construction-permit line item with its own fee, separate and priced differently from the Fire Sprinkler System permit line item, which is why this file documents it as a separate permit product rather than folding it into the sprinkler entry.
Verified 2026-07-23 · Source
When you need this permit
- Fire detection and alarm system plans/specifications must be submitted directly to the CAFMA Fire Prevention Division (not the Town) -- four sets of plans required, per CAFMA's Construction Guidelines for Contractors and Architects (REF: IFC 105.4)
- A CAFMA permit or affidavit is required for any installation or modification of a fire alarm system; forms are available at www.cazfire.gov or at CAFMA Administrative Headquarters (8603 E. Eastridge Dr., Prescott Valley, AZ 86314; 928-772-7711)
- All plans are approved, approved with corrections, or rejected by the CAFMA Fire Code Official (IFC 105.4); no specific published business-day review timeframe was found in CAFMA's Construction Guidelines or Fee Schedule (see reviewTimelineNote)
- CAFMA permits are valid for 180 days from approval; a written extension request must be submitted before expiration, and after 365 days a new permit is required regardless of extensions
- 24-hour advance notice is required to schedule a CAFMA inspection; system monitoring and supervision requirements apply per CAFMA's adopted fire-alarm standards
- Applicable CAFMA fees must be paid at time of plan submission
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring, device placement, and conduit runs inspected before concealment; 24-hour notice required to CAFMA
- 2
Final / Acceptance Test
Full system functional and monitoring-connection test witnessed by the CAFMA Fire Code Official before occupancy sign-off; failed inspections, failure to install per plans, or failure to pretest each carry a $125 reinspection fee
See the full Dewey-Humboldt inspection guide — scheduling & re-inspection fees →
Tips
- Fire alarm permitting in Dewey-Humboldt is NOT a Town function at all -- submit plans and fees directly to CAFMA's Fire Prevention Division (928-772-7711, www.cazfire.gov), not to the Town's Community Development office.
- CAFMA prices Fire Alarm ($483 new / $308 modification) as a distinct, separately-priced construction permit line item from Fire Sprinkler Systems ($683 new / $433 modification, commercial) -- a combined sprinkler-and-alarm project pays both fee lines, not a single bundled fee.
- CAFMA permits expire after 180 days (with a written extension request available before expiration) and cannot be extended past 365 days total -- track this separately from the Town's own 2-year building permit validity window.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dewey-Humboldt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Dewey-Humboldt
Fire Alarm System Permit (via Central Arizona Fire and Medical Authority) in other cities
Look up this fee in a different city →
Now live
Build your Dewey-Humboldt project checklist
Describe your project once and get every permit, document, and fee it triggers in Dewey-Humboldt — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →