Building Permit (New Construction, incl. Single-Family Residence, ADU, Garage/Carport, Room Addition, Manufactured Home) — Dewey-Humboldt, Arizona · Requirements sheet
Verified 2026-07-06 · Source: https://www.dhaz.gov/2203/Building-Permit
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit (New Construction, incl. Single-Family Residence, ADU, Garage/Carport, Room Addition, Manufactured Home) in Dewey-Humboldt, Arizona
Dewey-Humboldt does not split new residential construction into narrowly separate permit types the way some larger cities do — a single Building Permit Application covers new single-family residences, accessory dwelling units, garages, carports, decks, patio covers, room additions, remodels, cell towers, swimming pools, and retaining walls, reviewed against the 2018 IBC/IRC and Town amendments. A separate, similarly-formatted Manufactured Home Permit application applies specifically to manufactured/mobile home placement.
Verified 2026-07-06 · Source
When you need this permit
- Building permit required for new single-family residence, ADU, garage, carport, deck, patio cover, room addition, remodel, cell tower, swimming pool, or retaining wall construction within Town limits
- MUST have an approved septic permit from Yavapai County BEFORE submitting building plans to the Town — the Town cannot begin plan review until the septic system location and size are known
- Plans must comply with the 2018 IRC/IBC and Town amendments, including the Table R301.2(1) Climatic and Geographic Design Criteria (115 mph wind, Exposure C; Seismic Design Category C; 30 psf roof snow load; 18-inch frost depth; moderate-to-heavy termite potential)
- For projects not exempt under A.R.S. § 32-1121, the contractor must hold a current, valid Arizona ROC license (verify at roc.az.gov/licensing); Owner-Builder projects must certify compliance with A.R.S. § 32-1121(A)(5) (sole owner occupancy, not for sale/rent within 1 year) or § 32-1121(A)(6) (Owner-Developer contracting with a licensed General Contractor) Owner-builderContractor
- Submittal checklist (varies slightly by scope) includes: signed Building Permit Application, 2 sets of full construction plans, 2 AZ-stamped truss calculations (where applicable), 1 Plot Plan (8.5"x11"), 2 Site Plans (18"x24" minimum), Affidavit of Site Soil / Soils Report, Directions to Site, Residential Outdoor Lighting compliance, and a deposit/one-time fee
- Permit becomes invalid 2 years after issuance; work must commence within 180 days and inspections must occur at least every 180 days or the permit becomes null and void (one 180-day extension available at Building Official's discretion)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation/Footing
Before concrete pour; verifies footing reinforcement per § 150.03 amendment to IRC R403.1
- 2
Framing
Structural framing, connections, egress per 2018 IRC and Town Design Criteria
- 3
Final
All work complete per approved plans; 24-hour notice required to schedule; field plans and inspection card must be present on-site
See the full Dewey-Humboldt inspection guide — scheduling & re-inspection fees →
Tips
- The Town's own FAQ states plainly: 'Permits are typically approved in one to two weeks' (5-10 business days), though it notes exceptions can occur — this is the Town's own published review-timeframe statement (dhaz.gov/FAQ.aspx), not a formal A.R.S. § 9-835 timeframe-guideline document (the Town does not appear to publish one of those in the Buckeye/Cottonwood style).
- The single biggest hidden-timeline risk is the Yavapai County septic permit prerequisite — the Town cannot start its own plan review clock until an approved county septic permit is in hand, and the Town's FAQ warns this county-side step alone can take 4-6 weeks during peak season, on top of the Town's own 1-2 week review.
- Fees are a Yavapai County pass-through plus a flat 42% Town administration surcharge on both the permit fee and the plan review fee — get a project valuation estimate from the Building Official (928-632-7362) before budgeting, since the underlying county valuation table was not independently re-verifiable live at time of writing.
- Manufactured Home Permits use a nearly identical application/checklist to the Residential Building Permit but substitute '2 sets of plans and footings approved by State of AZ Manufactured Housing' for the truss-calculation requirement.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Dewey-Humboldt building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Dewey-Humboldt
Building Permit (New Construction, incl. Single-Family Residence, ADU, Garage/Carport, Room Addition, Manufactured Home) in other cities