Lafayette building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Lafayette, Colorado.
Verified 2026-07-05 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1290 S. Public Road, Lafayette, CO 80026
- Phone
- 303-661-1451
- Office hours
- City Hall public access hours Monday-Friday, 8am-5pm; Building staff available via phone/email during regular business hours. Main city line (303) 665-5588; Building Division direct line (303) 661-1451; Planning staff (303) 661-1270.
- Website
- Official site
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU) Permit
- 1
Foundation
Before concrete pour, per 36-inch minimum frost depth (if new construction)
- 2
Rough Frame
Framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if new footings)
Before concrete pour, per 36-inch minimum frost depth
- 2
Rough Frame
Framing complete, connection to existing structure verified
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
Applies to: Residential Building Permit (New Single-Family / Two-Family / Multi-Family / Townhome)
- 1
Foundation/Footing
Before concrete pour, per 36-inch minimum frost depth
- 2
Framing
Structural framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete; required for issuance of a Certificate of Occupancy (issued for new single-family homes, two-family homes [one CO per unit], townhomes [one CO per unit], and multi-family buildings [one CO per building])
Applies to: Electrical Permit
- 1
Rough Electrical
Wiring and panel installed before concealment
- 2
Final Inspection
Devices installed, panel labeled, system energized and verified
Applies to: EV Charger / EVSE Permit
- 1
Rough Electrical
Wiring and panel/breaker installed before concealment
- 2
Final Inspection
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; devices installed and system energized
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Ductwork, flues, and equipment placement before concealment
- 2
Final Inspection
Equipment operational, combustion air and venting verified
Applies to: Plumbing Permit
- 1
Rough Plumbing
Pipe, drain, waste, and vent installation before concealment
- 2
Final Inspection
Fixtures connected, no leaks, proper venting verified
Final inspection only: Demolition Permit, Fence Permit, Roofing Permit (Reroof), Solar Photovoltaic (PV) Permit, Solar Thermal Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lafayette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Lafayette building permits