Skip to main content
PermitBase

Electrical Permit in Lafayette, Colorado

Required for installation, alteration, or repair of electrical systems in Lafayette, excluding minor device replacement/repair which is exempt. Falls under the City's Quick Permit category (excluding solar or projects with engineered plans). Governed by the 2023 NEC as adopted. Electrical contractors must hold a Colorado Electrical Board (DORA) state license plus a City of Lafayette Electrical Contractor License (no City license fee).

Verified 2026-07-05 · Source

When you need this permit

  • Quick Permit category covers Electrical work excluding Solar or projects with engineered plans
  • Replacement of electrical devices or minor electrical repairs is exempt from permitting
  • Contractors must hold a current Colorado Electrical Board (DORA) State Master License and State Contractor License, plus a City of Lafayette Electrical Contractor License (no City fee, but copies of both State licenses required) Contractor
  • Contractors apply for Quick Building Permits via the MyGov Online Portal; the City verifies contractor license standing before processing Contractor
  • Governed by the 2023 NEC as adopted by the 2023 Lafayette Colorado Building Code

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Permit fee — valuation-based (Exhibit A Fee Schedule)Effective 1-1-26; no separate flat electrical fee is published (unlike AC/Furnace/Roof/Solar PV/Water Heater, which get a flat $100 fee)
$30.00 minimum, scaling per valuation tiers
Plan Check Fee
65% of the Building Permit Fee (where plan review applies)
Electrical Reinspection Fee
$75.00 per inspection

Review timeline

Plan reviewLafayette’s published plan-review target
2–2 business days

How long did your Electrical Permit permit actually take in Lafayette?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

See the full Lafayette inspection guide — scheduling & re-inspection fees →

Tips

  • Lafayette's Electrical Contractor License carries no City fee (unlike General, Mechanical, Plumbing, or Special contractor licenses) — but the State Master and Contractor License copies are still required as a prerequisite. Contractor
  • Quick Permits apply only to electrical work WITHOUT engineered plans — a project requiring engineered plans is not eligible for the 2-business-day Quick Permit track and instead follows the applicable full-review timeline.

Frequently asked questions

Yes. In addition to a Colorado Electrical Board (DORA) State Master License and State Contractor License, electricians must hold a City of Lafayette Electrical Contractor License (no City fee) before a permit can be issued.

In Lafayette, the published Permit fee — valuation-based (Exhibit A Fee Schedule) is: $30.00 minimum, scaling per valuation tiers. Additional published fees: Plan Check Fee — 65% of the Building Permit Fee (where plan review applies); Electrical Reinspection Fee — $75.00 per inspection. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lafayette's published plan-review target for an electrical permit is 2–2 business days.

You'll need: Quick Permit Application (MyGov Online Portal); City of Lafayette Electrical Contractor License. See the required-documents checklist on this page for details on each.

Lafayette requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Lafayette Planning & Building Department, Building Division (303-661-1451).

Apply through City of Lafayette Planning & Building Department, Building Division at 1290 S. Public Road, Lafayette, CO 80026. Phone: 303-661-1451, email: buildingpermits@lafayetteco.gov. Office hours: City Hall public access hours Monday-Friday, 8am-5pm; Building staff available via phone/email during regular business hours. Main city line (303) 665-5588; Building Division direct line (303) 661-1451; Planning staff (303) 661-1270.. Official information: https://www.lafayetteco.gov/92/Planning-Building-Department.

Lafayette, Colorado has adopted: 2021 International Building Code (IBC) — adopted with an effective date of August 1, 2023, per the 2023 Lafayette Colorado Building Code. Source: City of Lafayette Building Code & Design Information page, https://www.lafayetteco.gov/361/Building-Code-Design-Information; 2021 International Residential Code (IRC) — adopted with the same August 1, 2023 effective date; includes a local amendment requiring Class 4 Impact Resistant Shingles (effective March 15, 2021) for reroofing. Source: same page as above; 2021 International Existing Building Code (IEBC); 2021 International Fire Code (IFC); 2021 International Energy Conservation Code (IECC) — includes local commercial low-slope roof reflectance/emittance requirements per IECC Section C402.3, Table C402.3; 2021 International Fuel Gas Code (IFGC); 2021 International Mechanical Code (IMC); 2021 International Plumbing Code (IPC); 2021 International Property Maintenance Code (IPMC); 2021 International Swimming Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC) — the City's live Solar Permit Application Process document states 'All work shall comply with the 2023 National Electric Code without amendments.' (re-grounded 2026-07-16 on a live primary source after the Solar Photovoltaic Plan Review and Inspections webpage that previously carried this quote was removed from the site). Source (PDF): https://www.lafayetteco.gov/DocumentCenter/View/17165/Lafayette-Solar--Permit-Process; 2023 Lafayette Colorado Building Code — the City's consolidated adoption document incorporating the 2021 I-Code package plus local strengthening amendments and the 2023 NEC; effective August 1, 2023. Source (PDF): https://www.lafayetteco.gov/DocumentCenter/View/36791/2023-Lafayette-Colorado-Building-Code-Final; Colorado Wildfire Resiliency Code — adopted statewide in 2025; applies within State-mapped low- or medium-risk wildfire areas in Lafayette (128 acres total: 44 acres of open space on the southeast edge of the city, 84 acres along the west side near Nyland Way and Brittney Lane). Requires non-combustible building materials for new construction in mapped areas and defines defensible-space/fuel-reduction guidelines within 30 feet of structures. Source: City of Lafayette Building Code & Design Information page, https://www.lafayetteco.gov/361/Building-Code-Design-Information. Local amendments apply — see the Lafayette overview page for the full list.

If the work qualifies as a Quick Permit (excluding solar or projects requiring engineered plans), the City's estimated processing time is 2 business days, applied for through the MyGov Online Portal.

Sources & verification

Verified against official sources. Last reviewed 2026-07-05.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lafayette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.