EV Charger / EVSE Permit in Lafayette, Colorado
Electric vehicle charging equipment (EVSE) installation in Lafayette is processed as ordinary electrical work under the City's 'Quick Permit' category (Electrical, excluding Solar or projects with engineered plans), governed by the 2023 NEC as adopted. The City's Building Permit Fee Schedule (Exhibit A, effective 1-1-26) lists a flat $100 fee only for a specific named list of residential categories (AC, Furnace, Fence, Roof, Sewer Repair, Shed, Siding, Solar PV, Water Heater, & Windows) — EV chargers/EVSE are NOT on that list, so a standalone EVSE circuit is billed under the general valuation-based fee table instead. Under Colorado's HB24-1173 (Electric Vehicle Charging System Permits Act), Lafayette qualifies as a 'covered municipality' (population over 10,000) and was required to take a compliance action by December 31, 2025; the City adopted Resolution No. 2025-74, electing to continue using its existing permitting review process rather than adopting the Colorado Energy Office's EV charger model land use code or a new expedited standards/review process.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permit required for EVSE/EV charger circuit installation, alteration, or repair, governed by the 2023 NEC as adopted by the 2023 Lafayette Colorado Building Code
- Qualifies for the City's Quick Permit category (2-business-day estimated processing) if the installation does not require engineered plans; work requiring engineered plans follows the applicable full-review track instead
- Contractors must hold a current Colorado Electrical Board (DORA) State Master License and State Contractor License, plus a City of Lafayette Electrical Contractor License (no City license fee) Contractor
- No dedicated EVSE fee line exists on the Exhibit A fee schedule — EV chargers are not among the flat-$100 residential categories (AC, Furnace, Fence, Roof, Sewer Repair, Shed, Siding, Solar PV, Water Heater, & Windows), so the general valuation-based Building Permit Fee table applies
- Under HB24-1173, Lafayette (a 'covered municipality') adopted Resolution No. 2025-74 on or before the December 31, 2025 statutory deadline, electing to continue its existing permitting review process for EV charging system permits rather than adopting the state's model land use code or new statutory standards
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Wiring and panel/breaker installed before concealment
- 2
Final Inspection
EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; devices installed and system energized
See the full Lafayette inspection guide — scheduling & re-inspection fees →
Tips
- Lafayette's Exhibit A fee schedule gives Solar PV its own flat $100 fee category but does NOT extend that same flat treatment to EV chargers — a standalone EVSE installation is billed under the general valuation-based table instead, typically starting at the $30 minimum tier for low-valuation work.
- Under HB24-1173, Lafayette chose (via Resolution No. 2025-74) to keep its existing permitting process rather than adopt the Colorado Energy Office's EV charger model code or a new expedited standards/review track — so EV charger permitting in Lafayette follows the same Quick Permit electrical process as any other non-engineered electrical work, not a distinct fast-tracked EV-specific procedure.
- Quick Permits apply only to electrical work WITHOUT engineered plans — a large commercial EVSE installation requiring engineered plans is not eligible for the 2-business-day Quick Permit track.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lafayette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lafayette
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Lafayette project checklist
Describe your project once and get every permit, document, and fee it triggers in Lafayette — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →