Required for construction of new commercial buildings and commercial additions in Lafayette. The City's Apply for Building Permits page lists 'Commercial Addition, New Commercial, New Multi-Family' as its own commercial permit category with a published 4-8 week first-comments review estimate, explicitly requiring Site Plan and Architectural approval plus Civil Construction Document (CD) approval BEFORE building permit submittal. Reviewed under the 2021 IBC as adopted by the 2023 Lafayette Colorado Building Code (effective August 1, 2023); submitted and reviewed entirely by email/electronic plan review; issued by the Planning & Building Department, Building Division.

Verified 2026-08-02 · Source

When you need this permit

  • Site Plan and Architectural approval AND Civil CD approval must be obtained PRIOR to building permit submittal — the City's page states verbatim: 'Commercial Addition, New Commercial, and New Multi-Family require Site Plan and Architectural approval and Civil CD approval prior to permit submittal. Submitting a permit before obtaining these approvals will cause delays to these review estimates.'
  • Plans must comply with the 2021 IBC (plus 2021 IECC, IMC, IPC, IFC, IFGC, IEBC and 2023 NEC) as adopted by the 2023 Lafayette Colorado Building Code, effective August 1, 2023
  • Design criteria per the City's current Building Code & Design Information page (as published 2026-08-02): 36-inch frost depth; 40 psf snow load (roof and ground); 145 mph wind speed — note the City simplified this listing sometime after 2026-07-05, when it published 30 psf snow / 105 mph base wind with Risk Category Vult values up to 145 mph; confirm governing design values with the Building Division for your specific risk category
  • Commercial low-slope roofs directly above conditioned space must meet 2021 IECC Section C402.3 (Table C402.3) minimum roof reflectance/emittance
  • General contractor must hold a City of Lafayette General Class A Contractor License ($175, required for all commercial work over 2,000 sq ft) or General Class B ($125, commercial work up to 2,000 sq ft); licenses obtained/renewed via the MyGov portal Contractor
  • If the parcel falls within a State-mapped wildfire-risk area under the Colorado Wildfire Resiliency Code (128 mapped acres in Lafayette), non-combustible building materials and defensible-space standards apply
  • Complete Building Permit Application submitted electronically by email to buildingpermits@lafayetteco.gov — application and each plan/document as separate, descriptively-named PDFs; paper copies not accepted; 25MB email cap (larger plan sets via Dropbox/FTP)
  • Utility Service Application required for new commercial projects — obtained by emailing BuildingPermits@lafayetteco.gov

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $2,001.00 to $25,000.00City of Lafayette Building Permit Fee Schedule, Exhibit A, effective 1-1-26, re-confirmed live 2026-08-02; lower tiers: $1-$500 = $30.00 flat; $501-$2,000 = $30.00 + $3.35/$100
$80.25 for the first $2,000.00 plus $15.40 for each additional $1,000.00 or fraction thereof, to and including $25,000.00
Building Permit Fee — valuation $100,001.00 to $500,000.00Intermediate tiers: $25,001-$50,000 = $434.45 + $11.11/$1,000; $50,001-$100,000 = $712.20 + $7.70/$1,000; $500,001-$1,000,000 = $3,561.10 + $5.22/$1,000
$1,097.20 for the first $100,000.00 plus $6.16 for each additional $1,000.00 or fraction thereof
Building Permit Fee — valuation $1,000,001.00 and up
$6,176.10 for the first $1,000,000.00 plus $4.01 for each additional $1,000.00 or fraction thereof
Plan Check FeeApplies to residential and Commercial/Industrial alike per the fee schedule's fee-description table
65% of the Building Permit Fee
City Use Tax
3.87% of 60% of total value (0.02322 x value)
Boulder County Use Tax
1.335% of 60% of total value (0.00801 x value)
Affordable Housing Fee (Commercial/Industrial)Non-residential column of the fee schedule's fee-description table
$1.00 per square foot of gross floor area of structure
Service Expansion Fee (Commercial/Industrial)
$0.15 per gross building sq. ft.
Parks & Rec Fee (Commercial/Industrial)
$0.35 per gross sq. ft. of building
Public Arts Fee (Commercial/Industrial)
$0.05 per gross sq. ft. of building
Water/Water Reclamation Tap FeesProperties outside the legal City boundary pay double the listed water tap, water reclamation tap, and water rights fees
By tap size per Exhibit B (e.g., 3/4-inch water tap $20,300 + $346 meter; 2-inch tap $108,200 + $1,287 meter; water reclamation 3/4-inch $6,350)
Work performed without an issued permit
Double the building permit fee

Review timeline

Plan reviewLafayette’s published plan-review target
20–40 business days

How long did your Commercial Building Permit (New Commercial / Commercial Addition) permit actually take in Lafayette?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Before concrete pour, per the City's 36-inch minimum frost depth

  2. 2

    Framing/Structural

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment (2023 NEC, 2021 IPC, 2021 IMC as adopted)

  4. 4

    Final Inspection / Certificate of Occupancy

    All work complete per approved plans; Certificate of Occupancy issued before the building may be occupied. Inspections scheduled through the City's inspection request line; see the City's Inspections page

See the full Lafayette inspection guide — scheduling & re-inspection fees →

Tips

  • The single biggest schedule risk on New Commercial and Commercial Addition projects in Lafayette is sequencing: Site Plan/Architectural approval and Civil CD approval are hard prerequisites, and the 4-8 week building-permit review clock effectively assumes they are done — submitting early causes delays per the City's own caveat.
  • Beyond the base permit + 65% plan check fee, commercial projects carry substantial per-square-foot add-ons: $1.00/sq ft Affordable Housing, $0.35/sq ft Parks & Rec, $0.15/sq ft Service Expansion, $0.05/sq ft Public Arts, plus combined City+County use taxes of roughly 3.13% of total value — budget these into total permit cost.
  • As of 2026-08-02 the City's Building Checklists section reads 'Update checklists will be available soon' — commercial submittal checklists are temporarily unpublished, so confirm current submittal requirements with the Building Division (303-661-1451) before assembling a plan set.
  • The City's published design criteria changed between 2026-07-05 and 2026-08-02: the Building Code & Design Information page now lists 40 psf snow load and 145 mph wind speed (previously 30 psf and 105 mph base with Risk Category Vult tiers). Verify the governing values for your building's risk category with the Building Division.
  • General Class A City contractor license ($175) is required for all commercial work over 2,000 sq ft; Class B ($125) covers commercial up to 2,000 sq ft. Contractor

Frequently asked questions

Commercial Addition, New Commercial, and New Multi-Family projects require Site Plan and Architectural approval and Civil CD approval through the Planning Department before building permit submittal. Submitting a permit before obtaining these approvals will delay the City's published review estimates.

In Lafayette, the published Building Permit Fee — valuation $2,001.00 to $25,000.00 is: $80.25 for the first $2,000.00 plus $15.40 for each additional $1,000.00 or fraction thereof, to and including $25,000.00. Additional published fees: Building Permit Fee — valuation $100,001.00 to $500,000.00 — $1,097.20 for the first $100,000.00 plus $6.16 for each additional $1,000.00 or fraction thereof; Building Permit Fee — valuation $1,000,001.00 and up — $6,176.10 for the first $1,000,000.00 plus $4.01 for each additional $1,000.00 or fraction thereof; Plan Check Fee — 65% of the Building Permit Fee; City Use Tax — 3.87% of 60% of total value (0.02322 x value); Boulder County Use Tax — 1.335% of 60% of total value (0.00801 x value); Affordable Housing Fee (Commercial/Industrial) — $1.00 per square foot of gross floor area of structure; Service Expansion Fee (Commercial/Industrial) — $0.15 per gross building sq. ft.; Parks & Rec Fee (Commercial/Industrial) — $0.35 per gross sq. ft. of building; Public Arts Fee (Commercial/Industrial) — $0.05 per gross sq. ft. of building; Water/Water Reclamation Tap Fees — By tap size per Exhibit B (e.g., 3/4-inch water tap $20,300 + $346 meter; 2-inch tap $108,200 + $1,287 meter; water reclamation 3/4-inch $6,350); Work performed without an issued permit — Double the building permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City's published estimate is 4 to 8 weeks for first comments, then 1 to 2 weeks for each subsequent review cycle — and that assumes Site Plan/Architectural approval and Civil Construction Document approval were completed before permit submittal. The City labels this an estimate, not a guaranteed turnaround.

You'll need: Building Permit Application; Site Plan / Architectural Approval and Civil Construction Documents (approved); Utility Service Application; Construction Drawings. See the required-documents checklist on this page for details on each.

Lafayette requires 4 inspection(s) for a commercial building permit (new commercial / commercial addition), in order: Footing/Foundation, Framing/Structural, Rough Electrical / Plumbing / Mechanical, Final Inspection / Certificate of Occupancy. Schedule each through City of Lafayette Planning & Building Department, Building Division (303-661-1451).

Apply through City of Lafayette Planning & Building Department, Building Division at 1290 S. Public Road, Lafayette, CO 80026. Phone: 303-661-1451, email: buildingpermits@lafayetteco.gov. Office hours: City Hall public access hours Monday-Friday, 8am-5pm; Building staff available via phone/email during regular business hours. Main city line (303) 665-5588; Building Division direct line (303) 661-1451; Planning staff (303) 661-1270.. Official information: https://www.lafayetteco.gov/92/Planning-Building-Department.

Lafayette, Colorado has adopted: 2021 International Building Code (IBC) — adopted with an effective date of August 1, 2023, per the 2023 Lafayette Colorado Building Code. Source: City of Lafayette Building Code & Design Information page, https://www.lafayetteco.gov/361/Building-Code-Design-Information; 2021 International Residential Code (IRC) — adopted with the same August 1, 2023 effective date; includes a local amendment requiring Class 4 Impact Resistant Shingles (effective March 15, 2021) for reroofing. Source: same page as above; 2021 International Existing Building Code (IEBC); 2021 International Fire Code (IFC); 2021 International Energy Conservation Code (IECC) — includes local commercial low-slope roof reflectance/emittance requirements per IECC Section C402.3, Table C402.3; 2021 International Fuel Gas Code (IFGC); 2021 International Mechanical Code (IMC); 2021 International Plumbing Code (IPC); 2021 International Property Maintenance Code (IPMC); 2021 International Swimming Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC) — the City's live Solar Permit Application Process document states 'All work shall comply with the 2023 National Electric Code without amendments.' (re-grounded 2026-07-16 on a live primary source after the Solar Photovoltaic Plan Review and Inspections webpage that previously carried this quote was removed from the site). Source (PDF): https://www.lafayetteco.gov/DocumentCenter/View/17165/Lafayette-Solar--Permit-Process; 2023 Lafayette Colorado Building Code — the City's consolidated adoption document incorporating the 2021 I-Code package plus local strengthening amendments and the 2023 NEC; effective August 1, 2023. Source (PDF): https://www.lafayetteco.gov/DocumentCenter/View/36791/2023-Lafayette-Colorado-Building-Code-Final; Colorado Wildfire Resiliency Code — adopted statewide in 2025; applies within State-mapped low- or medium-risk wildfire areas in Lafayette (128 acres total: 44 acres of open space on the southeast edge of the city, 84 acres along the west side near Nyland Way and Brittney Lane). Requires non-combustible building materials for new construction in mapped areas and defines defensible-space/fuel-reduction guidelines within 30 feet of structures. Source: City of Lafayette Building Code & Design Information page, https://www.lafayetteco.gov/361/Building-Code-Design-Information. Local amendments apply — see the Lafayette overview page for the full list.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Lafayette.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.