Accessory Dwelling Unit (ADU) Permit — Lafayette, Colorado · Requirements sheet
Verified 2026-07-05 · Source: https://www.lafayetteco.gov/362/Apply-for-Building-Permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Accessory Dwelling Unit (ADU) Permit in Lafayette, Colorado
Required for construction of a new Accessory Dwelling Unit in Lafayette. New ADUs are classified with New Single-Family/Two-Family/Multi-Family permits under the City's longer new-construction review track, distinct from the faster Quick/Small Residential tracks. The City publishes separate checklists for detached ADUs (or ADUs requiring an addition) versus attached ADUs that do not require an addition.
Verified 2026-07-05 · Source
When you need this permit
- New Accessory Dwelling Units are grouped with New Single-Family Dwelling, Two-Family Dwelling, and Multi-Family Townhomes under the Residential Permits category (not Quick Permits or Small Residential Permits)
- ADU plans must be submitted no larger than 24 x 36 inches
- Use the detached-ADU checklist for detached ADUs or ADUs requiring an addition; use the separate attached-ADU checklist for attached ADUs that do not require an addition
- Projects in the Old Town Neighborhood Overlay District (which explicitly lists ADUs among covered project types) must additionally meet the Old Town Neighborhood Additional Requirements, Overlay District Regulations, and Dimensional Standards
- Accessory Dwelling Units under 750 sq ft do not require separate water taps, water meters, or water rights if the existing tap is adequate for the increased fixture count; otherwise the owner must install a new tap and pay the difference in tap/meter costs
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
Before concrete pour, per 36-inch minimum frost depth (if new construction)
- 2
Rough Frame
Framing complete before cover
- 3
Rough Electrical / Plumbing / Mechanical
Trade rough-ins before concealment
- 4
Final Inspection
All work complete per approved plans
See the full Lafayette inspection guide — scheduling & re-inspection fees →
Tips
- New ADUs follow the LONGER 8-12 week review track (grouped with new single-family/multi-family construction), not the faster 2-3 week Small Residential track — plan the project timeline accordingly.
- An ADU under 750 sq ft can avoid new water tap/meter/water rights costs entirely if the existing tap can serve the added fixture count — a meaningful cost consideration when sizing the unit.
- Use the correct checklist: detached ADUs (or ADUs requiring an addition) versus attached ADUs with no addition have separate submittal checklists — using the wrong one can cause review delays.
- Old Town Lafayette ADU projects carry additional overlay-district requirements beyond the base ADU checklist.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-05.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lafayette building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Lafayette
Accessory Dwelling Unit (ADU) Permit in other cities
Compare accessory dwelling unit (adu) permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Lafayette project checklist
Describe your project once and get every permit, document, and fee it triggers in Lafayette — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.