Salida building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Salida, Colorado.
Verified 2026-07-06 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- City of Salida Community Development Department: The Touber Building, 448 E. First Street, Suite 112, Salida, CO 81201. Chaffee County Building Safety Department: 104 Crestone Ave., Room 125 (2nd Floor), Salida, CO 81201 (mailing: P.O. Box 699, Salida, CO 81201)
- Phone
- City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208
- Office hours
- City of Salida Community Development: Monday-Thursday, 8:00 a.m.-5:00 p.m. (per the City's own Contact Information block on the Building Permit Review page). Chaffee County Building Safety Department: operates on a 4-day work week (Monday-Thursday), inspections performed Monday-Thursday excluding federal holidays; inspection requests must arrive by 4:00 p.m. the business day before the desired inspection date (Friday afternoon requests roll to Tuesday).
- Website
- Official site
Inspection sequence
- 1
City Zoning / Fire Safety / Site Plan Review Sign-off
Pre-construction review by City of Salida Community Development for zoning compliance, fire safety, and (for larger projects) Site Plan Review or Conditional Use Permit compliance under Chapter 16 — required before the application is forwarded to the County
- 2
Fire District Plan Review
Separate review/inspection track by Chaffee County Fire Protection District or South Arkansas Fire Protection District depending on jurisdiction, per the County's own Application for a Construction Review
- 3
Foundation / Footing
Performed by Chaffee County Building Safety Department before concrete pour
- 4
Framing
Performed by Chaffee County
- 5
MEP Rough-In
Mechanical, electrical, and plumbing rough-in; commercial buildings with occupant load over 10 require full MEP plans and COMcheck; each trade requires its own separate permit
- 6
Final Inspection (County) + Municipal Sign-Off (City of Salida) + Fire Department Final
A County final inspection, City of Salida municipal sign-off, and (where applicable) a fire district final inspection are required before a Certificate of Occupancy is issued
Applies to: Residential Building Permit (New Construction, Single-Family, ADU, Additions)
- 1
Foundation / Footing
Performed by Chaffee County Building Safety Department before concrete pour
- 2
Framing
Performed by Chaffee County; engineered truss design documentation must be available on-site even though not required at application
- 3
MEP Rough-In
Mechanical, electrical, and plumbing rough-in before walls closed; each trade requires its own separate permit
- 4
Final Inspection (County) + Municipal Sign-Off (City of Salida)
Both a County final inspection and City of Salida municipal sign-off are required before a Certificate of Occupancy is issued, per the County's own Residential Building Application
Applies to: Accessory Dwelling Unit (ADU) Building Permit
- 1
Foundation / Framing
Performed by Chaffee County, same sequence as new construction
- 2
MEP Rough-In
Each trade requires its own permit
- 3
Final Inspection (County) + Municipal Sign-Off (City)
Both required before Certificate of Occupancy
Applies to: Electrical Permit
- 1
Service Underground System
Per the County's own required-inspections list on the Electrical Permit Application
- 2
Rough-In
Prior to insulation and drywall
- 3
Final
Prior to occupancy
Applies to: Plumbing Permit
- 1
Underground / Under-slab
Before concrete pour
- 2
Rough-In
Before walls closed
- 3
Final
Fixtures connected, no leaks, proper venting
Applies to: Residential Addition / Remodel Building Permit
- 1
Foundation (if new footings)
Performed by Chaffee County
- 2
Framing / Rough Trades
Framing and MEP rough-in before concealment
- 3
Final Inspection (County) + Municipal Sign-Off (City)
Both required before Certificate of Occupancy
Applies to: Solar Photovoltaic (PV) Permit
- 1
Service Underground System
Per Chaffee County's required-inspections list
- 2
Rough-In
Prior to insulation and drywall; roof-mount racking/attachment verified before module installation
- 3
Final
Prior to occupancy/energizing the system
Applies to: Demolition / Abatement Permit
- 1
Utility Disconnection Verification
Utilities must be inspected prior to covering/capping; each utility provider signs off on the permit form
- 2
Final
Confirms structure removed and all utilities safely disconnected
Applies to: EV Charger / EVSE Permit (Chaffee County Electrical Permit)
- 1
Rough-In
Circuit wiring, breaker, and conduit before any wall/finish closure, if applicable
- 2
Final
Charger mounted, connections verified, GFCI/breaker protection confirmed prior to energizing
Applies to: Fire Sprinkler / Fire Alarm System Permit
- 1
Certificate of Occupancy (Final) Inspection
Included in the Commercial Business and Multi-Residential Plan Review fee, per the department's own 2026 Fees and Charges schedule
- 2
Annual Sprinkler / Fire Alarm System Test and Inspection
Post-installation, ongoing: sprinkler and fire alarm systems must be inspected and tested within the past year by a licensed contractor, with a copy of the test report given to (sprinkler) or available on request to (alarm) the Fire Department inspector
Applies to: Mechanical / HVAC Permit
- 1
Rough-In / Equipment
Equipment installation and ductwork before walls closed
- 2
Final
Equipment operational, combustion air and venting verified
Applies to: Roofing Permit
- 1
Mid-Roof / In-Progress
Required for all re-roof permits; verifies ice/water barrier, underlayment, drip edge, and flashing installation before shingles are installed past the ice/water barrier
- 2
Final
Confirms completed roof assembly per approved plans and manufacturer instructions
Final inspection only: Change of Use Permit (Change of Use Notification), Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Salida building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Salida building permits