Solar Photovoltaic (PV) Permit in Salida, Colorado

Required for installing a rooftop or ground-mount photovoltaic system in Salida. Because solar triggers the City's zoning/fire review, TWO fees and TWO reviewing authorities apply: the City of Salida Community Development Department (zoning compliance/fire safety sign-off, required first) and the Chaffee County Building Safety Department (which issues the actual Electrical Permit for the PV installation and performs inspections).

Verified 2026-07-20 · Source

When you need this permit

  • City of Salida zoning/fire safety sign-off required first, per Salida Municipal Code Chapter 16, before the application is forwarded to the County
  • Chaffee County Electrical Permit Application must be submitted for the PV installation itself, with the SOLAR mounting system (Pole/Ground/Roof, AC or DC) box completed
  • DC and AC wiring must be installed by a licensed electrical contractor unless the Colorado homeowner clause applies (owner-occupant, property not for sale/rental, owner personally performs the work) Owner-builder
  • Required County inspections: service underground system, rough-in prior to insulation/drywall, and final prior to occupancy/energizing

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

City of Salida zoning/fire review feeCity of Salida Residential Building Permit Application and 2026 Fees and Charges for Community Development Services schedule
20% of the county building permit fee, minimum $50.00 residential / $100.00 commercial
Chaffee County Solar Electrical Permit FeeChaffee County Electrical Permit Application, Section C 'Solar Fees' (Revised 04/01/22). Worked example on the County's own form: 5,500 watts x $4.00 = $22,000 valuation; 22 x $10.00 = $220.00 + $65.00 base = $285.00 total. This fee structure implements the statewide caps of C.R.S. § 24-48.5-113 (HB21-1284).
Valuation computed at $4.00 per watt, then fee = $65.00 base + $10.00 per $1,000 of that valuation; capped at $500.00 for a Residential Unit and $1,000.00 for a Commercial Unit

Review timeline

Plan review
Not published — contact the department

How long did your Solar Photovoltaic (PV) Permit permit actually take in Salida?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Service Underground System

    Per Chaffee County's required-inspections list

  2. 2

    Rough-In

    Prior to insulation and drywall; roof-mount racking/attachment verified before module installation

  3. 3

    Final

    Prior to occupancy/energizing the system

See the full Salida inspection guide — scheduling & re-inspection fees →

Tips

  • Solar in Salida is a two-agency process: the City reviews zoning/fire compliance first (fee = 20% of the county fee, min $50 residential/$100 commercial), and only after City sign-off does Chaffee County issue the actual Electrical Permit for the PV system and perform inspections.
  • The County's solar fee is capped regardless of system size: $500 max residential, $1,000 max commercial, per C.R.S. § 24-48.5-113 (HB21-1284) — larger systems become proportionally cheaper per watt once the cap is hit.
  • SolarAPP+ (gosolarapp.org) automated permitting was not found listed as active for Salida or Chaffee County as of this review; confirm current status directly if instant permitting is desired.

Frequently asked questions

Salida requires a solar photovoltaic (pv) permit for: City of Salida zoning/fire safety sign-off required first, per Salida Municipal Code Chapter 16, before the application is forwarded to the County; Chaffee County Electrical Permit Application must be submitted for the PV installation itself, with the SOLAR mounting system (Pole/Ground/Roof, AC or DC) box completed; DC and AC wiring must be installed by a licensed electrical contractor unless the Colorado homeowner clause applies (owner-occupant, property not for sale/rental, owner personally performs the work); Required County inspections: service underground system, rough-in prior to insulation/drywall, and final prior to occupancy/energizing. If your project isn't listed, confirm with Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 before starting work.

In Salida, the published City of Salida zoning/fire review fee is: 20% of the county building permit fee, minimum $50.00 residential / $100.00 commercial. Additional published fees: Chaffee County Solar Electrical Permit Fee — Valuation computed at $4.00 per watt, then fee = $65.00 base + $10.00 per $1,000 of that valuation; capped at $500.00 for a Residential Unit and $1,000.00 for a Commercial Unit. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Salida does not publish a plan-review timeline for this permit. Contact Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 for current turnaround.

You'll need: Chaffee County Electrical Permit Application; City of Salida zoning/fire review submittal. See the required-documents checklist on this page for details on each.

Salida requires 3 inspection(s) for a solar photovoltaic (pv) permit, in order: Service Underground System, Rough-In, Final. Schedule each through Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) (City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208).

Apply through Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida Community Development Department: The Touber Building, 448 E. First Street, Suite 112, Salida, CO 81201. Chaffee County Building Safety Department: 104 Crestone Ave., Room 125 (2nd Floor), Salida, CO 81201 (mailing: P.O. Box 699, Salida, CO 81201). Phone: City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208, email: City of Salida (zoning/land use/building permit inquiries): planning@cityofsalida.com; Commercial Permit Inquiries/Major Impact Review: kristen.hodges@cityofsalida.com. Chaffee County Building Safety Department: bdepartment@chaffeecounty.org (electronic plan submittals: eplans@chaffeecounty.org). Office hours: City of Salida Community Development: Monday-Thursday, 8:00 a.m.-5:00 p.m. (per the City's own Contact Information block on the Building Permit Review page). Chaffee County Building Safety Department: operates on a 4-day work week (Monday-Thursday), inspections performed Monday-Thursday excluding federal holidays; inspection requests must arrive by 4:00 p.m. the business day before the desired inspection date (Friday afternoon requests roll to Tuesday).. Official information: https://www.cityofsalida.com/commdev/page/building-permit-review and https://www.chaffeecounty.org/departments/building_department/index.php.

Salida, Colorado has adopted: 2021 International Building Code (IBC) — adopted by the City of Salida per the City's own Building Permit Review page: 'The City adopted the 2021 International Codes for Building, Residential, Existing Buildings, Plumbing, Mechanical, Energy Conservation, Fuel Gas and Property Maintenance with the 2021 IECC and the 2021 National Electric Code.' Chaffee County Building Safety Department's own Adopted Codes & Design Criteria page independently confirms the same 2021 I-Code suite (IBC, IRC, IFC, IPC, IMC, IFGC, IECC, IEBC) is the edition actually enforced county-wide, including for Salida.; 2021 International Residential Code (IRC) — same dual-source confirmation as above; 2021 International Existing Building Code (IEBC); 2021 International Plumbing Code (IPC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC) — Chaffee County's Residential Building Application requires an IECC Compliance Path Certificate, Manual J/S/D submittal, and blower-door/duct/ventilation testing by a RESNET- or BPI-certified tester; 2021 International Property Maintenance Code — named on the City's own adopted-codes list; 2023 National Electrical Code (NFPA 70 / NEC) — City of Salida's own page states '2021 IECC and the 2021 National Electric Code,' but Chaffee County Building Safety Department's Adopted Codes & Design Criteria page (the agency that actually issues and enforces electrical permits) lists the 2023 NEC as currently adopted; this is a genuine, honestly-flagged discrepancy between the City's own page text and the County's live enforced edition — applicants should confirm the currently enforced NEC edition directly with Chaffee County Building Safety Department at time of submittal; 2017 ICC A117.1 Accessible and Usable Buildings and Facilities — Chaffee County Adopted Codes & Design Criteria page; Colorado Wildfire Resiliency Code (effective July 1, 2026) and 2021 International Wildland-Urban Interface Code (IWUIC) — Chaffee County Adopted Codes & Design Criteria page; note several IWUIC-specific submittal requirements on the County's own Residential Building Application are explicitly scoped to 'Unincorporated Chaffee County Only,' meaning some (not all) IWUIC provisions may not directly apply within Salida city limits — confirm scope with the County Building Department for any given IWUIC provision; Colorado Model Electric Ready & Solar Ready Code — Chaffee County Adopted Codes & Design Criteria page; the County's Residential Building Application requires roof load design for future solar panels and a solar-ready zone/interconnection pathway on submitted plans; Salida Municipal Code Chapter 16, Land Use and Development — governs zoning compliance, setbacks, dimensional standards, landscaping, and parking; reviewed by the City of Salida Community Development Department as the mandatory first step before any County building-permit review begins. Local amendments apply — see the Salida overview page for the full list.

Two: a City of Salida zoning/fire safety sign-off (20% of the county fee, minimum $50 residential/$100 commercial) followed by a Chaffee County Electrical Permit for the PV system itself, capped at $500 residential/$1,000 commercial per Colorado's statewide solar fee cap.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Salida building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.