Roofing Permit in Salida, Colorado

Required for re-roofing or roof repair on any structure in Salida. Issued and inspected by the Chaffee County Building Safety Department under the 2021 IRC roofing provisions (R905) and, where applicable, the 2021 IWUIC. A separate permit is required for each structure.

Verified 2026-07-06 · Source

When you need this permit

  • A SEPARATE PERMIT IS REQUIRED FOR EACH STRUCTURE, per the County's own Roofing Permit Application
  • If the structure is in a Historical District, contact the municipality (City of Salida) planning department for review before applying
  • A mid-roof (in-progress) inspection is required for all re-roof permits — do not install shingles past the ice/water barrier until this inspection is complete
  • Underlayment, ice/water barrier, shingle attachment, and drip edge must comply with 2021 IRC R905.1.1, R905.1.2, R905.2.6, and R905.2.8.5 respectively; roof valley flashing (where applicable within Unincorporated Chaffee County) must meet 2021 IWUIC Section 504 standards — confirm with the County whether this specific IWUIC provision extends inside Salida city limits for your project
  • Applicant/permit holder is responsible for providing safe roof access (properly set and secured ladder) for inspection; failure to provide access results in inspection disapproval

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Roofing Permit FeeChaffee County Application for Roofing Permit; fee is valuation-based with a stated $100.00 minimum, per the form's own fee block
$100.00 minimum

Review timeline

Plan review
Not published — contact the department

How long did your Roofing Permit permit actually take in Salida?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Mid-Roof / In-Progress

    Required for all re-roof permits; verifies ice/water barrier, underlayment, drip edge, and flashing installation before shingles are installed past the ice/water barrier

  2. 2

    Final

    Confirms completed roof assembly per approved plans and manufacturer instructions

See the full Salida inspection guide — scheduling & re-inspection fees →

Tips

  • Do not install shingles past the ice/water barrier before the mid-roof inspection — the County's own form warns this will prevent verification of underlayment and may result in disapproval.
  • If your structure is in a Historical District within Salida, contact the City of Salida planning department before applying — the County's own form flags this as a separate review track.

Frequently asked questions

Salida requires a roofing permit for: A SEPARATE PERMIT IS REQUIRED FOR EACH STRUCTURE, per the County's own Roofing Permit Application; If the structure is in a Historical District, contact the municipality (City of Salida) planning department for review before applying; A mid-roof (in-progress) inspection is required for all re-roof permits — do not install shingles past the ice/water barrier until this inspection is complete; Underlayment, ice/water barrier, shingle attachment, and drip edge must comply with 2021 IRC R905.1.1, R905.1.2, R905.2.6, and R905.2.8.5 respectively; roof valley flashing (where applicable within Unincorporated Chaffee County) must meet 2021 IWUIC Section 504 standards — confirm with the County whether this specific IWUIC provision extends inside Salida city limits for your project; Applicant/permit holder is responsible for providing safe roof access (properly set and secured ladder) for inspection; failure to provide access results in inspection disapproval. If your project isn't listed, confirm with Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 before starting work.

In Salida, the published Roofing Permit Fee is: $100.00 minimum. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Salida does not publish a plan-review timeline for this permit. Contact Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208 for current turnaround.

You'll need: Chaffee County Application for Roofing Permit. See the required-documents checklist on this page for details on each.

Salida requires 2 inspection(s) for a roofing permit, in order: Mid-Roof / In-Progress, Final. Schedule each through Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) (City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208).

Apply through Two-agency split: City of Salida Community Development Department (zoning/fire/Land-Use-Code review and City permit fee, first step) + Chaffee County Building Safety Department (I-Code plan review, permit issuance, fees, and inspections, second step) at City of Salida Community Development Department: The Touber Building, 448 E. First Street, Suite 112, Salida, CO 81201. Chaffee County Building Safety Department: 104 Crestone Ave., Room 125 (2nd Floor), Salida, CO 81201 (mailing: P.O. Box 699, Salida, CO 81201). Phone: City of Salida: 719-539-4555 (fax 719-539-5271). Chaffee County Building Safety Department: 719-539-2124 (Option 1 for inspections, Option 2 for applications/fees); fax 719-530-9208, email: City of Salida (zoning/land use/building permit inquiries): planning@cityofsalida.com; Commercial Permit Inquiries/Major Impact Review: kristen.hodges@cityofsalida.com. Chaffee County Building Safety Department: bdepartment@chaffeecounty.org (electronic plan submittals: eplans@chaffeecounty.org). Office hours: City of Salida Community Development: Monday-Thursday, 8:00 a.m.-5:00 p.m. (per the City's own Contact Information block on the Building Permit Review page). Chaffee County Building Safety Department: operates on a 4-day work week (Monday-Thursday), inspections performed Monday-Thursday excluding federal holidays; inspection requests must arrive by 4:00 p.m. the business day before the desired inspection date (Friday afternoon requests roll to Tuesday).. Official information: https://www.cityofsalida.com/commdev/page/building-permit-review and https://www.chaffeecounty.org/departments/building_department/index.php.

Salida, Colorado has adopted: 2021 International Building Code (IBC) — adopted by the City of Salida per the City's own Building Permit Review page: 'The City adopted the 2021 International Codes for Building, Residential, Existing Buildings, Plumbing, Mechanical, Energy Conservation, Fuel Gas and Property Maintenance with the 2021 IECC and the 2021 National Electric Code.' Chaffee County Building Safety Department's own Adopted Codes & Design Criteria page independently confirms the same 2021 I-Code suite (IBC, IRC, IFC, IPC, IMC, IFGC, IECC, IEBC) is the edition actually enforced county-wide, including for Salida.; 2021 International Residential Code (IRC) — same dual-source confirmation as above; 2021 International Existing Building Code (IEBC); 2021 International Plumbing Code (IPC); 2021 International Mechanical Code (IMC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC) — Chaffee County's Residential Building Application requires an IECC Compliance Path Certificate, Manual J/S/D submittal, and blower-door/duct/ventilation testing by a RESNET- or BPI-certified tester; 2021 International Property Maintenance Code — named on the City's own adopted-codes list; 2023 National Electrical Code (NFPA 70 / NEC) — City of Salida's own page states '2021 IECC and the 2021 National Electric Code,' but Chaffee County Building Safety Department's Adopted Codes & Design Criteria page (the agency that actually issues and enforces electrical permits) lists the 2023 NEC as currently adopted; this is a genuine, honestly-flagged discrepancy between the City's own page text and the County's live enforced edition — applicants should confirm the currently enforced NEC edition directly with Chaffee County Building Safety Department at time of submittal; 2017 ICC A117.1 Accessible and Usable Buildings and Facilities — Chaffee County Adopted Codes & Design Criteria page; Colorado Wildfire Resiliency Code (effective July 1, 2026) and 2021 International Wildland-Urban Interface Code (IWUIC) — Chaffee County Adopted Codes & Design Criteria page; note several IWUIC-specific submittal requirements on the County's own Residential Building Application are explicitly scoped to 'Unincorporated Chaffee County Only,' meaning some (not all) IWUIC provisions may not directly apply within Salida city limits — confirm scope with the County Building Department for any given IWUIC provision; Colorado Model Electric Ready & Solar Ready Code — Chaffee County Adopted Codes & Design Criteria page; the County's Residential Building Application requires roof load design for future solar panels and a solar-ready zone/interconnection pathway on submitted plans; Salida Municipal Code Chapter 16, Land Use and Development — governs zoning compliance, setbacks, dimensional standards, landscaping, and parking; reviewed by the City of Salida Community Development Department as the mandatory first step before any County building-permit review begins. Local amendments apply — see the Salida overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Salida building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.