How to schedule
Inspections are requested through the building department below.
- Address
- 360 Main Street, Delta, CO 81416
- Phone
- 970-874-7909
- Office hours
- Not published on the City's Building page or any retrieved City document this session; inspection requests are called in from 8:00 a.m. to 4:30 p.m. at 970-874-7909, per the City's Inspection Guidelines (updated 6-12-2023). General City Hall address is 360 Main Street, Delta, CO 81416, main line (970) 874-7566.
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction)
- 1
Footing Trenches
Required for footing, trenches, formed footings, and drilled piers/caissons with reinforcing steel in place; includes rebar ground for electrical (concrete-encased electrode)
- 2
Foundation
Forms with reinforcing steel in place, ready for concrete, before concrete is placed
- 3
Damp-proofing
Required only for basements
- 4
Rough Mechanical / Rough Electrical (underground)
Only if part of the system will be covered by concrete before the entire rough-in is complete
- 5
Roof and Wall Sheathing
Before dry-in or house wrap
- 6
House Wrap, Window Flashing, Flashing at Concrete Porches
- 7
Rough Plumbing
Made when rough-in is complete and water/air is in the lines per code; performed by the State of Colorado Plumbing Inspector, not the City
- 8
Rough Mechanical
All ductwork/piping completely roughed in, ready for drywall
- 9
Rough Electrical
Electrical rough-in complete, all circuits made up, panel set, grounding complete, ready for drywall but without insulation; performed by the City of Delta
- 10
Framing
Not requested until all framing complete, roof on, and all plumbing/heating/electrical rough-ins completed and approved
- 11
Insulation (walls)
- 12
Lathing or Drywall
Prior to taping and finishing
- 13
Final Inspections
Electrical, Mechanical, and Building Final Inspections signed off by the City of Delta; Plumbing Final Inspection signed off by the State of Colorado. Certificate of Occupancy issues automatically after all finals are complete.
Applies to: Residential Addition / Remodel Permit
- 1
Foundation (if applicable)
- 2
Rough Mechanical / Electrical
City handles electrical inspection in-city; mechanical rough-in inspected by the City
- 3
Rough Plumbing
Performed by the State of Colorado Plumbing Inspector, not the City
- 4
Framing
- 5
Insulation / Drywall
- 6
Final Inspection
Building/Electrical/Mechanical finals by the City; Plumbing final by the State
Applies to: Electrical Permit
- 1
Rough Electrical (underground, if applicable)
- 2
Rough Electrical
Circuits made up, boxes/plaster rings installed, panel set, grounding complete, ready for drywall
- 3
Final Electrical
Signed off by the City of Delta
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical (underground, if applicable)
- 2
Rough Mechanical
All ductwork/piping roughed in, ready for drywall
- 3
Final Mechanical
Signed off by the City of Delta as part of the overall building-permit final inspection process
Applies to: EV Charger / EVSE Permit (Electrical Permit)
- 1
Rough Electrical (if applicable)
- 2
Final Electrical
Charger circuit/unit installed, breaker sized correctly, energized; signed off by the City of Delta
Applies to: Plumbing Permit (Issued by the State of Colorado, Not the City)
- 1
Rough Plumbing
Performed by the State of Colorado Plumbing Inspector
- 2
Final Plumbing
Signed off by the State of Colorado, separate from the City's Building Final
Applies to: Re-Roof Permit
- 1
Roof and Wall Sheathing
Before dry-in, per the general Inspection Guidelines sequence
- 2
Final Inspection
Signed off by the City of Delta as part of the overall building-permit final process
Applies to: Solar Permit
- 1
Structural/Roof-Mount Inspection
Verifies racking attachment and roof penetration sealing against the engineer analysis submitted with the application
- 2
Electrical Inspection
Verifies the one-line diagram, disconnects, rapid shutdown control, and interconnection wiring against the Technical Permit's photovoltaic work type
Final inspection only: Demolition Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Delta building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Delta building permits
Get alerts for Delta
We'll email you when Delta's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.