EV Charger / EVSE Permit (Electrical Permit) in Delta, Colorado

Installation of an electric vehicle charging station in Delta is NOT a standalone permit type — it is processed as ordinary electrical work through the same Technical Permit Application used for the City's electrical-permit entry, with 'Electrical' checked as the type of work. The City's 2026 Schedule of City Fees and Charges (Table 3C) has no distinct EV-charger/EVSE fee line; a dedicated EV charging circuit or wall-mounted Level 2 unit is billed under the existing 'Service Change / Other Minor Electrical Installation' flat fee ($100.00), the same line item any other minor electrical addition uses. The City of Delta itself issues and inspects electrical permits in-city (the opposite authority split from several peer Colorado cities in this corpus, e.g. Montrose, where the State handles electrical) — confirmed directly on the Technical Permit Application form and Table 3C of the Fee Schedule, both fetched and reviewed this session; no page, form, or fee table mentions EV chargers, EVSE, or electric vehicles by name.

Verified 2026-07-20 · Source

When you need this permit

  • Technical Permit Application with 'Electrical' checked as type of work — the same shared form used for mechanical, fireplace/stove, temporary power, and photovoltaic work
  • If installing at a new structure, the associated Building Permit must be issued before the Technical (electrical) Permit can be issued
  • Work must be performed by a licensed Colorado electrical contractor, or by the homeowner personally on their own sole/owner-occupied residence under the Homeowner Clause Owner-builder
  • If the electrical permit is not filed in advance of work commencing, the inspection fee is doubled pursuant to C.R.S. § 12-115-121(3), per the City's own fee-schedule language already documented on this file's electrical-permit entry
  • Colorado HB24-1173 (Electric Vehicle Charging System Permits, 2024) requires municipalities of 10,000+ population (per 2020 Census) to adopt streamlined EV-charging land-use permitting by December 31, 2025; Delta's 2020 Census population (~9,000) is below that statutory threshold, and no City of Delta ordinance, land-use code amendment, or adoption of the state's EV Charging Model Land Use Code was found published on the City's site in this session — so the City's generic electrical-permit process (not a HB24-1173-specific streamlined process) is what currently governs an EV charger installation there

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Service Change / Other Minor Electrical Installation (applies to a dedicated EV charger circuit or wall-mounted Level 2 unit)City of Delta 2026 Schedule of City Fees and Charges, Section 3-F, Table 3C — the same flat fee line used for any minor electrical installation; no distinct EV-charger/EVSE line item exists on the fee table
$100.00
Plan ReviewPer Table 3C, same as the file's general electrical-permit entry
65% of permit fee, if submittal documents are required by code
Use TaxWaived if the electrical valuation is already included in an associated building permit's valuation, per Section 3-F
3% of cost of materials

Review timeline

Plan reviewDelta’s published plan-review target
1+ business days

How long did your EV Charger / EVSE Permit (Electrical Permit) permit actually take in Delta?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical (if applicable)

  2. 2

    Final Electrical

    Charger circuit/unit installed, breaker sized correctly, energized; signed off by the City of Delta

See the full Delta inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate 'EV charger permit' in Delta — apply for a standard Electrical Permit via the Technical Permit Application, checking 'Electrical' as the type of work.
  • Budget the flat $100.00 'Service Change / Other Minor Electrical Installation' fee unless the charger installation is bundled into a larger building or solar project, in which case it may instead fall under that project's valuation-based fee.
  • Delta's own population is below the 10,000-resident threshold that triggers Colorado HB24-1173's mandatory streamlined EV-charging land-use permitting — do not assume Delta has adopted the state's EV Charging Model Land Use Code without confirming directly with the Building Department (970-874-7909).

Frequently asked questions

Delta requires an ev charger / evse permit (electrical permit) for: Technical Permit Application with 'Electrical' checked as type of work — the same shared form used for mechanical, fireplace/stove, temporary power, and photovoltaic work; If installing at a new structure, the associated Building Permit must be issued before the Technical (electrical) Permit can be issued; Work must be performed by a licensed Colorado electrical contractor, or by the homeowner personally on their own sole/owner-occupied residence under the Homeowner Clause; If the electrical permit is not filed in advance of work commencing, the inspection fee is doubled pursuant to C.R.S. § 12-115-121(3), per the City's own fee-schedule language already documented on this file's electrical-permit entry; Colorado HB24-1173 (Electric Vehicle Charging System Permits, 2024) requires municipalities of 10,000+ population (per 2020 Census) to adopt streamlined EV-charging land-use permitting by December 31, 2025; Delta's 2020 Census population (~9,000) is below that statutory threshold, and no City of Delta ordinance, land-use code amendment, or adoption of the state's EV Charging Model Land Use Code was found published on the City's site in this session — so the City's generic electrical-permit process (not a HB24-1173-specific streamlined process) is what currently governs an EV charger installation there. If your project isn't listed, confirm with City of Delta Building Department (Community Development) at 970-874-7909 before starting work.

In Delta, the published Service Change / Other Minor Electrical Installation (applies to a dedicated EV charger circuit or wall-mounted Level 2 unit) is: $100.00. Additional published fees: Plan Review — 65% of permit fee, if submittal documents are required by code; Use Tax — 3% of cost of materials. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Delta's published plan-review target for an ev charger / evse permit (electrical permit) is 1+ business days.

You'll need: Technical Permit Application. See the required-documents checklist on this page for details on each.

Delta requires 2 inspection(s) for an ev charger / evse permit (electrical permit), in order: Rough Electrical (if applicable), Final Electrical. Schedule each through City of Delta Building Department (Community Development) (970-874-7909).

Apply through City of Delta Building Department (Community Development) at 360 Main Street, Delta, CO 81416. Phone: 970-874-7909, email: comdev@cityofdelta.net. Office hours: Not published on the City's Building page or any retrieved City document this session; inspection requests are called in from 8:00 a.m. to 4:30 p.m. at 970-874-7909, per the City's Inspection Guidelines (updated 6-12-2023). General City Hall address is 360 Main Street, Delta, CO 81416, main line (970) 874-7566.. Official information: https://www.cityofdelta.net/cd/page/building.

Delta, Colorado has adopted: 2018 International Building Code (IBC) — per the City of Delta Building Department page (https://www.cityofdelta.net/cd/page/building); 2018 International Existing Building Code (IEBC); 2018 International Residential Code (IRC); 2018 International Fire Code (IFC); 2018 International Mechanical Code (IMC); 2018 International Plumbing Code (IPC) — adopted per the City's own Building page, but plumbing permitting/inspection itself is performed by the State of Colorado, not the City (see localAmendments); 2018 International Fuel Gas Code (IFGC); 2012 International Energy Conservation Code (IECC); 2023 National Electrical Code (NEC) — electrical permitting IS performed by the City of Delta (unlike several peer home-rule cities in this corpus, e.g. Montrose, where the State Electrical Board handles it); NOTE — code-edition discrepancy found and not silently reconciled: the City's own 2026 Schedule of Fees and Charges (Table 3A, Building Permit Fees valuation table) is explicitly headed 'Group (2024 International Building Code)', a newer edition than the 2018 IBC named on the Building Department page itself. Both are official City-published documents retrieved directly this session; the discrepancy is surfaced here rather than guessed at — confirm the currently-enforced IBC edition directly with the Building Department (970-874-7909) before relying on either figure for design compliance.. Local amendments apply — see the Delta overview page for the full list.

No. The City of Delta has no distinct EV-charger or EVSE permit or fee line. An EV charging station is installed under a standard Electrical Permit (Technical Permit Application, 'Electrical' checked), billed at the flat $100.00 'Service Change / Other Minor Electrical Installation' fee on Table 3C of the City's 2026 Schedule of City Fees and Charges.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Delta building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.