Residential Addition / Remodel Permit — Delta, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.cityofdelta.net/cd/page/applications-and-requirements
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Addition / Remodel Permit in Delta, Colorado
Required for additions, remodels, and foundation/change-of-use work on existing residential structures in Delta, using the same Building Permit Application as new construction (with 'Addition', 'Remodel', 'Foundation', or 'Change of Use' checkboxes). Detached accessory sheds ≤200 sq ft with no electrical/plumbing are exempt from a building permit; see localAmendments for the full permit-exempt work list.
Verified 2026-07-06 · Source
When you need this permit
- Same Building Permit Application used for new construction, with 'Addition,' 'Remodel,' 'Foundation,' or 'Change of Use' selected as the type of work
- Two (2) plot plans showing lot dimensions, projections, and distances to property lines/structures
- Two (2) sets of architectural/floor plans, foundation plan, and mechanical plans as applicable to project scope
- Change-of-use projects must state the FROM and TO use on the application
- Detached accessory structures (sheds, playhouses) ≤200 sq ft with no electrical or plumbing work do NOT require a building permit, per the City's 'Work Exempt from Permits' bulletin
- Decks ≤30 inches above grade and ≤20 sq ft, siding (except stucco), and window replacement with no structural change are also permit-exempt
- Separate permits required by the City for electrical, solar, and mechanical work; separate State permit for plumbing
- Applicant must disclose asbestos-inspection status for materials to be disturbed
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation (if applicable)
- 2
Rough Mechanical / Electrical
City handles electrical inspection in-city; mechanical rough-in inspected by the City
- 3
Rough Plumbing
Performed by the State of Colorado Plumbing Inspector, not the City
- 4
Framing
- 5
Insulation / Drywall
- 6
Final Inspection
Building/Electrical/Mechanical finals by the City; Plumbing final by the State
See the full Delta inspection guide — scheduling & re-inspection fees →
Tips
- Check the City's 'Work Exempt from Permits' bulletin before applying — many small residential projects (sheds ≤200 sq ft with no utilities, small decks, siding, window replacement without structural change) need NO building permit at all in Delta.
- Fences and retaining walls ≤4 feet do not require a City building permit in Delta, though fence height/construction rules under Municipal Code 15.04.060 and 17.04.240 still apply.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Delta building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Delta
Residential Addition / Remodel Permit in other cities
Compare residential addition / remodel permit fees across Colorado →
Look up this fee in a different city →