Building Permit — Gunnison, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.gunnisonco.gov/departments/building/building___sign_permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit in Gunnison, Colorado
Required for construction, enlargement, alteration, repair, moving, demolition, or change of occupancy of a building or structure within City of Gunnison limits, per the 2021 IBC/IRC as adopted and locally amended in Municipal Code Chapter 14.10. Issued and reviewed directly by the City's own Building Office (Community Development Department) — Gunnison County has no jurisdiction within City limits and there is no joint city-county building authority. This is the City's single UNIFIED permit for both residential (IRC) and commercial/multi-family (IBC) construction, including tenant improvements: neither the City's Building & Sign Permits page, the Community Development Applications & Forms page, nor the Jan. 1, 2026 Fee Table publishes a separate commercial building permit application, commercial permit type, or tenant-improvement permit. Commercial projects use the same Building Permit application and the same valuation-based Appendix L fee brackets, differing only in fee INPUTS — a 2.30% Regional Building Valuation Multiplier per sq ft versus 1.60% residential, a 65% Plan Review Fee versus 30% under the IRC, and a $600 pre-application Site Development Review tier versus $300.
Verified 2026-08-02 · Source
When you need this permit
- Property must be within City of Gunnison limits (Gunnison County's Building Office explicitly excludes all incorporated cities/towns, including Gunnison, from its jurisdiction)
- Parcel must have adequate public facilities — sewage disposal, water, electricity, drainage/water quality, fire protection, roads, transportation, pedestrian circulation, and refuse — per the Land Development Code and Building/Fire Codes
- Occupancy will not be granted until City water, sewer, and electrical utilities are in place and functional
- Work not listed under the IRC/IBC 'Building Exemptions' list (e.g., detached accessory structures under 120-200 sq ft, fences ≤8 ft, retaining walls ≤4 ft, re-roofing/re-siding without structural alteration) requires a permit
- Electrical and plumbing scopes of work are permitted and inspected separately by the State of Colorado, not the City
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Preapplication admin review fee per submittal review — the commercial/multi-family pre-application tier that precedes a commercial Building Permit submittal. Show full citationHide
Preapplication admin review fee per submittal review — the commercial/multi-family pre-application tier that precedes a commercial Building Permit submittal. The 1-and-2-unit residential counterpart ('Site Development Review') is $300.00 per submittal review. Community Development, Building and Planning Fee Table, effective January 1, 2026.Chapter 14.10 on ecode360.com (ecode360.com/47882243) does render client-side, but was successfully loaded and read via a real browser (not a plain fetch), confirming Section 109.2 still directs that… Show full citationHide
Chapter 14.10 on ecode360.com (ecode360.com/47882243) does render client-side, but was successfully loaded and read via a real browser (not a plain fetch), confirming Section 109.2 still directs that 'a fee shall be determined in accordance with the attached permit fee schedule, Appendix L' (unchanged as of ecode360's 'legislation through 03-24-2026' currency notice). Appendix L itself is not transcribed into ecode360's codified section text (it is an attached exhibit), so it was located in the original enacting document instead: Ordinance No. 9, Series 2022, City of Gunnison, '2021 PERMIT FEE SCHEDULE APPENDIX L' table, adopted 11/08/2022 — linked from the City Clerk Ordinances page (gunnisonco.gov/departments/city_clerk/ordinances.php) at gunnisonco.gov/departments/city_clerk/ordinance.no9.series2022.pdf. This valuation-to-fee bracket table is the 'base building permit fee' that the Jan. 1, 2026 Fee Table's Plan Review Fee percentages (65%/30%) and Regional Building Valuation Multiplier are layered on top of. Also re-checked the full Jan. 1, 2026 Community Development Fee Table PDF (2 pages) and the citywide Resolution No. 3, Series 2026 fee schedule (10-page scanned PDF, OCR'd in full) — neither reproduces this bracket table; it remains solely in the 2022 ordinance exhibit, which has not been found superseded by any later ordinance (Ordinance No. 4, Series 2025 amended only the Chapter 14.10 appeals process, not fees).Review timeline
Inspection process
- 1
Footing/Foundation
Per the City-adopted 2021 IBC/IRC; a City-specific inspection checklist/sequence was not found separately published online as of 2026-07-19.
- 2
Framing
Structural framing inspection consistent with the adopted 2021 IBC/IRC.
- 3
Final
Final building inspection prior to occupancy; City occupancy is withheld until water, sewer, and electrical utilities are in place and functional.
See the full Gunnison inspection guide — scheduling & re-inspection fees →
Tips
- Gunnison County has NO jurisdiction inside City of Gunnison limits — the County's own Building Office page states this explicitly. Do not contact Gunnison County Community Development for a City of Gunnison building permit; use the City's own Building Office (201 W. Virginia Ave., 970.641.8151).
- Electrical and plumbing permits/inspections within City limits are handled by the State of Colorado (Division of Professions and Occupations), not the City Building Office — the City's own pages list a Local State Electrical Inspector and Local State Plumbing Inspector rather than City-side electrical/plumbing permit staff.
- The City's Finance Department fee-schedule index page states current City fees were set by 'Resolution No. 3, Series 2026' effective June 1, 2026, but the linked Community Development, Building and Planning Fee Table PDF itself is stamped 'Fees effective January 1, 2026 per Resolution No. 25, Series 2025.' The figures in this entry come from that linked PDF -- the Jan. 1, 2026 / Resolution No. 25, Series 2025 version. Confirm with the Building Office (970.641.8151) whether a newer resolution has since revised these line items.
- Commercial projects: this entry is the commercial building permit — Gunnison publishes no separate commercial application, commercial permit type, or tenant-improvement permit, per the Building & Sign Permits page, the Applications & Forms page, and the Jan. 1, 2026 Fee Table. Budget the commercial-specific fee inputs: 2.30% Regional Building Valuation Multiplier per sq ft (vs 1.60% residential), 65% Plan Review Fee (vs 30% IRC), and the $600 Preliminary Site Development Review pre-application tier (vs $300 for 1-2 unit residential).
- TENANT IMPROVEMENTS: there is no standalone TI/tenant-finish permit or fee line — interior alteration of a commercial space is processed as an ordinary Building Permit under the Appendix L valuation brackets, and if the tenancy changes the occupancy classification, the Change of Use/Occupancy fee also applies ($225.00 up to $5,000 valuation; % per IBC/IRC table above $5,000, per the Jan. 1, 2026 Fee Table).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gunnison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Gunnison's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Gunnison yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Gunnison lands. Privacy.
Other permits in Gunnison
Building Permit in other cities
Compare building permit fees across Colorado →
Look up this fee in a different city →