EV Charger / Electric Vehicle Charging Station Permit — Gunnison, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.gunnisonco.gov/departments/building/building___sign_permits.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit in Gunnison, Colorado
Installing an EV charger circuit in Gunnison is electrical work, and per the City's general electrical carve-out (documented on the Building & Sign Permits page and consistent with this corpus's existing solar-pv-permit entry for Gunnison), electrical permits and inspections within City limits are administered directly by the State of Colorado (DORA Division of Professions and Occupations, Electrical Board), not the City of Gunnison. The City does not issue or fee-assess electrical permits at all -- there is no City fee line for EV chargers because the City is not the issuing authority for the electrical scope. A City of Gunnison Building Permit is required IN ADDITION only if the installation includes new structural work (e.g., a carport or accessory structure to house the charger), billed under the City's general valuation-based Base Building Permit Fee, the same mechanism documented for solar's structural/racking scope.
Verified 2026-07-20 · Source
When you need this permit
- The EV charger circuit itself must be permitted and inspected directly through the State of Colorado DORA Electrical Board (apply at dpo.colorado.gov/EandP/Permits) -- not through the City of Gunnison, which has no electrical permitting function
- Local State Electrical Inspector for Gunnison: Dustin Behounek, 303.869.3451, per the City's own Building Department and Building & Sign Permits pages
- A City of Gunnison Building Permit is required only if new structural work (e.g., a carport, canopy, or accessory structure) is built to house the charger -- submitted to the City's Building Office, not the County (Gunnison County's Building Office has no jurisdiction within City limits)
- Unlike solar, which is subject to Colorado's statewide $500 local-government fee cap for residential installations (C.R.S. 24-48.5-113), no equivalent statutory fee cap was found for EV charger permits
- Governed by the City's adopted 2021 IBC/IRC (Municipal Code Chapter 14.10) for any structural component, and the state-adopted NEC for the electrical scope
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State of Colorado Electrical Inspection
Scheduled directly with the State of Colorado Electrical Board, not the City -- verifies the new circuit, breaker sizing, and disconnect per NEC Article 625
See the full Gunnison inspection guide — scheduling & re-inspection fees →
Tips
- Do not contact the City of Gunnison Building Office to schedule an EV charger electrical inspection -- electrical work within City limits is administered entirely by the State of Colorado (Local State Electrical Inspector Dustin Behounek, 303.869.3451).
- A simple residential Level 2 charger mounted on an existing garage wall does not need a City building permit at all -- only the State electrical permit.
- Unlike solar, which benefits from Colorado's statewide $500 local-fee cap (C.R.S. 24-48.5-113), EV charger permits have no equivalent statutory fee cap -- but since the City itself doesn't charge an electrical fee at all (the State does), this distinction mainly matters if a City structural permit is also triggered.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Gunnison building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Gunnison
EV Charger / Electric Vehicle Charging Station Permit in other cities
Compare ev charger / electric vehicle charging station permit fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Gunnison project checklist
Describe your project once and get every permit, document, and fee it triggers in Gunnison — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →