Wellington building inspections

Inspection sequence, scheduling, and re-inspection fees for building permits in Wellington, Colorado.

Reviewed 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
8225 Third Street, P.O. Box 127, Wellington, CO 80549
Phone
970-821-5078 (Building Department direct); 970-568-3381 (Town main line, ext. 115 for building permit verification)
Office hours
Monday-Friday, 8:00 a.m. to 5:00 p.m., Municipal Services Building, 8225 Third Street (across from Centennial Park). Plan review and inspections are conducted by SAFEbuilt, the Town's contracted building-department partner, not Town staff directly; inspection scheduling calls to SAFEbuilt (970-674-1036 or 866-671-1036) must be placed before 4 p.m. for next-business-day scheduling.

Published scheduling rules

  • SAFEbuilt (not Town staff directly) performs plan review and inspections for Wellington — direct SAFEbuilt correspondence (resubmittals, inspection scheduling) to their published channels (safebuiltcoloradoplanreview@safebuilt.com for plans; 970-674-1036 or 866-671-1036 for inspections), not the Town's general line. (Residential Building Permit (New Construction))
  • All permits related to a project must be issued, signed off, and on the job site BEFORE a final inspection is requested; work performed without a permit, or a final inspection requested before required permits are on site, may be subject to fines under the adopted International Fire Code (Fire Sprinkler / Fire Alarm System Permit)
  • At least 2 business days' advance notice is required to schedule an inspection (Fire Sprinkler / Fire Alarm System Permit)
  • Wellington contracts building-department functions (plan review and inspections) out to SAFEbuilt — direct plan resubmittals and inspection scheduling calls go to SAFEbuilt (safebuiltcoloradoplanreview@safebuilt.com; 970-674-1036 / 866-671-1036), not the Town's general line, even though applications and payments are still processed through the Town's Community Core/Connect portal. (General)
  • Wellington splits ALL permits into three tracks with materially different processes: 'Permits With Plan Review' (Residential Addition, PV System, Accessory Structure, Basement Finish, Deck, Pergola/Patio Cover, Pole Barn, Shed — full SAFEbuilt review, 5-business-day target), 'One Stop Permits — No Plan Review' (Re-roof, Furnace/AC, Water Heater, Siding, Windows, misc. trade permits, Demolition, Fence, Construction Trailer — pay and schedule inspection directly, no published SLA), and 'Zoning Permits' (small Sheds under 120 sq ft/10 ft height, Fences — reviewed by Planning, not Building). (General)

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Addition)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Fire Protection / Suppression System

    Required only where a fire protection or suppression system (e.g., Type I hood suppression, fire sprinklers) is part of the design

  5. 5

    Final Inspection

    All work complete per approved plans and applicable codes; for restaurant/food-service projects, Larimer County Health Department approval must be on the jobsite before final inspection will be approved

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Insulation

    Wall, ceiling, floor insulation and exterior windows installed, before wall coverings

  4. 4

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  5. 5

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Commercial Tenant Finish / Remodel (Tenant Improvement) Permit

  1. 1

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment; only applicable trades for the scope of work

  2. 2

    Framing

    Required only if the project includes structural modifications (e.g., bearing wall removal)

  3. 3

    Fire Protection / Suppression System

    Required only where a hood suppression system or fire sprinklers are part of the design

  4. 4

    Final Inspection

    All work complete per approved plans; for restaurant/food-service tenant finishes, Larimer County Health Department approval must be on the jobsite before final inspection will be approved

Applies to: Residential Addition / Remodel Permit

  1. 1

    Framing (additions only)

    Structural connection to existing structure verified

  2. 2

    Insulation

    Required before wall coverings are installed

  3. 3

    Rough Electrical / Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Deck / Patio Cover / Pergola Permit

  1. 1

    Footing/Foundation

    Before concrete pour, for deck posts/footings

  2. 2

    Framing

    Structural framing and ledger-board connection before decking/roofing installed

  3. 3

    Final Inspection

    Guardrails, stairs, and structural connections complete

Applies to: Change of Use / Change of Occupancy Permit

  1. 1

    WFPD Fire-Code Compliance Inspection

    Performed by the Wellington Fire Protection District as part of Occupancy/Business Change Permit issuance, to confirm the building and property comply with the adopted Fire Code

  2. 2

    Building Final Inspection (if construction accompanies the change of use)

    Required only if physical construction or alteration is part of the project scope

Applies to: Electric Vehicle (EV) Charging Station / EVSE Permit

  1. 1

    Rough Electrical

    EVSE circuit wiring and disconnect placement before concealment

  2. 2

    Final Inspection

    Charging equipment installed, system energized and verified per 2026 NEC Article 625

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

Applies to: Fire Sprinkler / Fire Alarm System Permit

  1. 1

    Rough-In (Underground Fire Line / Sprinkler / Alarm)

    Piping, wiring, and device placement before concealment, per the approved plan set

  2. 2

    Final Inspection

    All related permits must be issued, signed off, and on the job site before this inspection is requested; at least 2 business days' advance notice required to schedule

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar Photovoltaic (PV) System Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wellington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Wellington building permits

Get alerts for Wellington

We'll email you when Wellington's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.