Solar Photovoltaic (PV) System Permit in Wellington, Colorado

Required for rooftop and ground-mount photovoltaic solar installations in Wellington. Falls under the Town's 'Permits With Plan Review' track ('Residential Alteration' category), reviewed alongside the Colorado Model Electric and Solar Ready Code adopted with the 2024 I-Codes.

Reviewed 2026-07-20 · Source

When you need this permit

  • Reviewed under the 'Permits With Plan Review' track, using the SAFEbuilt PV System Building Guide and the Wellington Project Checklist PV System document
  • Interacts with the Colorado Model Electric and Solar Ready Code, adopted alongside the 2024 I-Codes effective January 1, 2026, and HB22-1362's statewide solar/EV-readiness floor
  • Electrical scope of the installation billed under the state-mandated electrical fee schedule (CRS 12-23-117), not the Town's building valuation table
  • All contractors must hold a current Town of Wellington Contractor License plus applicable Colorado state electrical trade license Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Fee (PV/solar electrical scope)
From State Electrical Fee Schedule (CRS 12-23-117), plus Town surcharge up to 15% above state base rate
Permit Issuance
$25 flat

Review timeline

Plan reviewWellington’s published plan-review target
5+ business days

How long did your Solar Photovoltaic (PV) System Permit permit actually take in Wellington?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

See the full Wellington inspection guide — scheduling & re-inspection fees →

Tips

  • PV/Solar in Wellington is a plan-review-track permit (not a One Stop permit) — budget for the Town's published 5-business-day first-review cycle, plus any resubmittal rounds.
  • The electrical portion of a solar installation is billed under the state electrical fee schedule (CRS 12-23-117), the same mechanism used for a standalone electrical permit.

Frequently asked questions

Wellington requires a solar photovoltaic (pv) system permit for: Reviewed under the 'Permits With Plan Review' track, using the SAFEbuilt PV System Building Guide and the Wellington Project Checklist PV System document; Interacts with the Colorado Model Electric and Solar Ready Code, adopted alongside the 2024 I-Codes effective January 1, 2026, and HB22-1362's statewide solar/EV-readiness floor; Electrical scope of the installation billed under the state-mandated electrical fee schedule (CRS 12-23-117), not the Town's building valuation table; All contractors must hold a current Town of Wellington Contractor License plus applicable Colorado state electrical trade license. If your project isn't listed, confirm with Town of Wellington Planning and Building Department at 970-821-5078 (Building Department direct); 970-568-3381 (Town main line, ext. 115 for building permit verification) before starting work.

In Wellington, the published Electrical Fee (PV/solar electrical scope) is: From State Electrical Fee Schedule (CRS 12-23-117), plus Town surcharge up to 15% above state base rate. Additional published fees: Permit Issuance — $25 flat. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Wellington's published plan-review target for a solar photovoltaic (pv) system permit is 5+ business days.

You'll need: Permit Application — PV System; Wellington Project Checklist — PV System. See the required-documents checklist on this page for details on each.

Wellington requires 2 inspection(s) for a solar photovoltaic (pv) system permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Wellington Planning and Building Department (970-821-5078 (Building Department direct); 970-568-3381 (Town main line, ext. 115 for building permit verification)).

Apply through Town of Wellington Planning and Building Department at 8225 Third Street, P.O. Box 127, Wellington, CO 80549. Phone: 970-821-5078 (Building Department direct); 970-568-3381 (Town main line, ext. 115 for building permit verification), email: Building@wellingtoncolorado.gov. Office hours: Monday-Friday, 8:00 a.m. to 5:00 p.m., Municipal Services Building, 8225 Third Street (across from Centennial Park). Plan review and inspections are conducted by SAFEbuilt, the Town's contracted building-department partner, not Town staff directly; inspection scheduling calls to SAFEbuilt (970-674-1036 or 866-671-1036) must be placed before 4 p.m. for next-business-day scheduling.. Official information: https://wellingtoncolorado.gov/554/Building.

Wellington, Colorado has adopted: 2024 International Building Code (IBC) — effective January 1, 2026; 2024 International Residential Code (IRC) — effective January 1, 2026; 2024 International Energy Conservation Code (IECC) — effective January 1, 2026; 2024 International Mechanical Code (IMC) — effective January 1, 2026; 2024 International Plumbing Code (IPC) — effective January 1, 2026; 2024 International Fire Code (IFC) — effective January 1, 2026; 2024 International Property Maintenance Code (IPMC) — effective January 1, 2026; 2024 International Existing Building Code (IEBC) — effective January 1, 2026; 2024 International Swimming Pool and Spa Code (ISPSC) — effective January 1, 2026; 2026 National Electrical Code (NFPA 70-NEC) — effective January 1, 2026 (per the Town's Building Department page; note this is one code cycle ahead of the 2023 NEC used by most other 2026-era Colorado jurisdictions in this corpus — verified directly against the Town's own 'Building Code Update' announcement, not assumed); 2025 Colorado Wildfire Resiliency Code, Version 1.0 — adopted alongside the 2024 I-Codes; Colorado Model Electric and Solar Ready Code — adopted alongside the 2024 I-Codes, addressing HB22-1362's statewide energy/electric-readiness floor; Local Amendments — Ordinance No. 15-2025 (adopted on first reading October 14, 2025 and second reading/adoption November 12, 2025; effective January 1, 2026) replace the Town's prior 2018 I-Code local amendments (originally under Ordinance No. 5-2019) and Ordinance No. 8-2019 (2019 building fee schedule) as the current governing local amendment package. Ordinance No. 15-2025 is codified on Municode (a JavaScript single-page application at library.municode.com/co/wellington); bare curl/automated fetch still returns HTTP 200 with no static text, but CORRECTED 2026-07-23: the full codified text IS retrievable via a live browser session (Municode renders client-side JS content that a headless curl fetch cannot execute) — confirmed directly against Chapter 18, Articles 1-4 (IBC/IRC/IPC/IMC amendments), version 'JUL 10, 2026 (CURRENT)', which quotes Ordinance No. 15-2025's full section-by-section amendment text verbatim, including the IRC R401.2 foundation/soils-report amendment. The Town's own Building Department webpage 'Building Departments News & Update' section (dated 11.25.2025) remains a valid corroborating first-party source for the adoption dates.; Previous code cycle (through December 31, 2025, now superseded): 2018 International Code editions (IBC, IRC, IECC, IMC, IPC, IFGC, IPMC, IEBC, IFC) under Ordinance No. 5-2019, and 2023 NEC. The Town's own Contractors/Homeowners webpages still host several 2018-cycle 'SAFEbuilt Building Guide' packets (Re-Roof 2018, Accessory Structure 2018, Deck/Porches 2018, Patio Covers 2018, Pole Barn 2018, Swimming Pools 2018, PV System 2019) that have not yet been refreshed to reference the 2024 I-Codes as of this review — treated as legacy/stale content rather than the governing code list, consistent with the Town's own live 'Current (Effective January 1, 2026)' code list.. Local amendments apply — see the Wellington overview page for the full list.

The electrical fee for the PV system's electrical scope follows the same state-mandated fee schedule as a standalone electrical permit (CRS 12-23-117), but PV System itself is categorized as a 'Permits With Plan Review' item — meaning it goes through SAFEbuilt plan review (5-business-day first-comment target) rather than the no-plan-review 'One Stop' track used for standalone electrical work.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wellington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.