Electric Vehicle (EV) Charging Station / EVSE Permit in Wellington, Colorado
Wellington has two distinct layers relevant to EV charging: (1) A standard residential or single-unit EVSE circuit installation is not a separate permit type -- it is billed and processed through the Town's existing Electrical Permit (state-anchored CRS § 12-115-121 fee schedule (renumbered from the commonly-cited § 12-23-117 effective 10/1/2019), plus up to a 15% Town surcharge), the same 'One Stop Permits -- No Plan Review' track used for other standalone electrical work, since Wellington defers to Colorado State Electrical Board licensing and has no dedicated EV-charger fee line. (2) For EV charging SYSTEM/site installations (e.g., commercial or multi-stall charging stations), Wellington's Board of Trustees adopted Ordinance No. 15-2025 (enacted November 12, 2025) amending the Town's Land Use Code to comply with Colorado HB24-1173 (Electric Vehicle Charging System Permits Act) -- Wellington's 2020 Census population of 11,144 places it above the Act's 10,000-person 'covered municipality' threshold. Per the Town's own Planning Commission materials (September 8, 2025 meeting), staff recommended and the Town adopted the legislation's minimum Land Use Code amendment option (rather than the Colorado Energy Office's full model code, or an opt-out), establishing an administrative review process for EV charging infrastructure installations under 8 stalls.
Verified 2026-07-20 · Source
When you need this permit
- For a standard residential/single-unit EV charger circuit: no standalone EV-specific permit exists; apply for the Town's standard Electrical Permit through the Community Core/Connect 'One Stop Permits' track, the same as any other standalone electrical work
- Contractors must hold a current Colorado State Electrical Board (DORA) Master Electrician license, contemporaneously verified by SAFEbuilt at permit issuance per SB19-156, plus a Town of Wellington general Contractor License Contractor
- For an EV charging SYSTEM/site installation (commercial or multi-stall charging stations): subject to the administrative land-use review process established by Ordinance No. 15-2025 (enacted November 12, 2025), which amended the Town's Land Use Code to comply with Colorado HB24-1173 for installations under 8 stalls
- Wellington's 2020 Census population (11,144) exceeds the 10,000-person threshold making it a 'covered municipality' under HB24-1173, legally obligating the administrative-review/checklist and denial-appeal provisions the Act requires for covered jurisdictions that choose the custom-standards option
- Governed by the 2026 NEC as locally adopted (effective January 1, 2026), which includes Article 625 (Electric Vehicle Power Transfer System) provisions; the Town's own Building Department page separately notes 'improved energy efficiency and electrical readiness (solar, EV infrastructure)' as part of its 2024 I-Codes adoption
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
EVSE circuit wiring and disconnect placement before concealment
- 2
Final Inspection
Charging equipment installed, system energized and verified per 2026 NEC Article 625
See the full Wellington inspection guide — scheduling & re-inspection fees →
Tips
- A single residential EV charger circuit does not need the land-use administrative review created by Ordinance No. 15-2025 -- that process is for EV charging SYSTEM/site installations (commercial or multi-stall stations); a homeowner adding one EVSE circuit just needs the standard Electrical Permit.
- Wellington is one of the relatively few Colorado municipalities in this corpus large enough (2020 Census population 11,144) to be a mandatory 'covered municipality' under HB24-1173 -- it chose to amend its Land Use Code to the statute's minimum requirements (Ordinance No. 15-2025, November 12, 2025) rather than adopt the Colorado Energy Office's full model code or opt out.
- Electrical fees are state-anchored (CRS 12-23-117), not Town-set -- confirm the current amount with SAFEbuilt or the Building Department directly at permit application, since no locally tabulated current dollar figure is published.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Wellington building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Wellington
Electric Vehicle (EV) Charging Station / EVSE Permit in other cities
Compare electric vehicle (ev) charging station / evse permit fees across Colorado →
Look up this fee in a different city →